Lower Jurala Hydro Electric Project Explained

Name Official:Lower Jurala Hydro Electric Project
Dam Crosses:Krishna River
Location:Mulamalla Village, Jogulamba Gadwal district, Telangana
Construction Began:13 November 2008
Cost:Est Rs.1474.83 Crores
Status:UC
Purpose:P
Location Map:India Telangana#India
Coordinates:16.3131°N 77.7772°W
Plant Name:Lower Jurala Hydro Electric Project
Plant Operator:TSGENCO
Plant Commission:Unit-1 29 December 2013
[1]
Unit-2 10 January 2014
Unit-3 28 July 2016
Unit-4 28 July 2016
Unit-5 September 2016
Unit-6 September 2016
Plant Type:R
Plant Turbines:6 x 40MWBulb type [2]
Plant Capacity:240MW
Website:http://tsgenco.telangana.gov.in/

Lower Jurala Hydro Electric Project is a major on-going Hydro Electric Project near Mulamalla Village, Atmakur Mandal, Jogulamba Gadwal district, Telangana. The project construction was started in 2008, planned to completed it by 2014. But due to the delay it may completed by end of 2015. There will be 6 units, each can produce 40 MW power. The first unit was synchronized in December 2013 and the second unit was synchronized in January 2014 and connected to the grid.

Due to the quality issues in gates, along with units 1&2,unit-3 nearing erection completion and assemblies in various stages were inundated on 30 July 2014 late night flood water released from Jurala Project.

Units 3 and 4 were commissioned and declared of commercial operation of 40 MW each unit on 28 July 2016 confirmed by Mr. Venkata Rajam, COD Hydel, Telangana State Genco.

See also

External links

Notes and References

  1. Web site: Telangana - Projects under construction. Telangana Power Generation Corporation. 1 September 2014. 2 April 2015. https://web.archive.org/web/20150402154002/http://tsgenco.telangana.gov.in/getInfo.do?dt=7&oId=16&id=4. dead.
  2. Web site: Projects under Execution - Lower Jurala, India . Alstom technologies. 1 September 2014.