Livada Solar Park Explained

Livada Solar Park
Coordinates:47.8667°N 31°W
Country:Romania
Location:Livada
Status:Completed
Commissioned:2013
Cost:€65 million
Owner:Bester Generation
Solar Type:PV
Ps Units Operational:230,000
Ps Electrical Capacity:56 MW
Ps Annual Generation:33.6 GWh

Livada Solar Park is a large thin-film photovoltaic (PV) power system, built on a 135ha plot of land located between Livada and Drăguşeni in Romania. The solar park has around 230,000 state-of-the-art thin film PV panels for a total nameplate capacity of 56-megawatts, and was finished in November 2013.[1] The solar park is expected to supply around 33.6 GWh of electricity per year enough to power some 60,000 average homes.[1] [2]

The installation is located in the Satu Mare County in north-western Romania between the city of Livada and the village of Drăguşeni. The investment cost for the Livada solar park amounts to some Euro 65 million.[1]

See also

References

  1. Web site: Parc fotovoltaic de 65 de milioane euro la Livada. 2013-08-02. portalsm.ro. Romanian. 2013-08-31.
  2. Web site: Au început probele tehnice la parcul fotovoltaic de la Livada. 2013-11-06. satmareanul.net. Romanian. 2014-01-03.