This is a list of wind farms in Queensland, Australia. To be included on the list a wind farm must have a capacity of 10 megawatts (MW) or greater.
As of December 2023, Queensland has six operating wind farms with a total installed capacity of about 1025 MW.
width=20% | Project name | width=20% | Sponsoring company | width=20% | Coordinates | width=10% | Capacity (MW) | width=10% | width=20% | Notes | |
---|---|---|---|---|---|---|---|---|---|---|---|
Coopers Gap[1] [2] [3] | AGL Energy | 453 | $850 million investment,[4] 123 turbines | ||||||||
Dulacca Wind Farm | Octopus Investments | 181 | $450 million investment, 43 turbines | ||||||||
Mount Emerald Wind Farm[5] | RATCH-Australia Port Bajool | 180 | $2 dollar investment, 1 used and the cheapest turbine | ||||||||
Windy Hill Wind Farm | Built by Stanwell Corporation, now owned by RATCH-Australia | 12 | $20 million investment, 20 turbines | ||||||||
Kaban Green Power hub | Neoen | 156 | 2023 | Combined with 100 MW battery[6] | |||||||
Kennedy Energy Park Stage 1[7] [8] | Windlab | 43 | 2021 | Combined with 15 MW solar power and 2 MW / 4 MWh Battery. |
width=20% | Project name | width=20% | Sponsoring company | width=20% | Coordinates | width=10% | Capacity (MW) | width=10% | Status | width=20% | Notes |
---|---|---|---|---|---|---|---|---|---|---|---|
Archer Point Wind Farm | Wind Power Queensland | 120 | Feasibility | ||||||||
Clarke Creek Wind Farm[9] [10] | Lacour | 800 | Feasibility | Up to 195 turbines | |||||||
Crediton Wind Farm[11] | Transfield Services | 40 | Proposed | ||||||||
Crows Nest Wind Farm[12] | AGL Energy | 200 | Cancelled | $270 million investment, 40 turbines. Cancelled by AGL.[13] | |||||||
Forsayth Wind Farm[14] [15] | Infigen Energy | 75 | Planning approved | $250 million investment, 30 turbines | |||||||
Forest Wind[16] [17] [18] | CleanSight and Siemens Financial Services | 1200 | Planning approved | $2 billion investment, up to 226 turbines | |||||||
High Road Wind Farm[19] | Transfield Services | 50[20] | Planning approved | $90 million investment, 17 turbines | |||||||
Kennedy Energy Park Stage 2 | Windlab | 43 | Feasibility | Over $1.5 billion to construct, up to 300 wind turbines. | |||||||
Kidston Wind Project[21] | Genex Power | 258 | Feasibility | Expanded to 258MW in November 2022 [22] | |||||||
North Stradbroke Island | Stanwell Corporation | 15 | Proposed | ||||||||
Windy Hill Wind Farm Stage 2 | Proposed by Transfield Services | 12 | Cancelled | ||||||||
MacIntyre Wind Farm | Acciona & CleanCo | 1026[23] | Commissioned | Located in Cement Mills | |||||||
MacIntyre Wind Farm Herries Range | Acciona | align=“left” | 1000[24] | ||||||||
Lakeland Wind Farm | Windlab | 100 | Planning approved | [25] [26] [27] | |||||||
Banana Range Wind Farm | Lacour | 230 | Planning approved | Construction start expected Q1 2024[28] | |||||||
Kingaroy Wind Farm | Australia Energy Windfarm | 57.12 | Feasibility | [29] [30] |