Line 17 (Chengdu Metro) Explained
Line 17 of the Chengdu Metro is a metro line in Chengdu. The whole line will be 30.286 km when Phase 2 opens. The line uses 8-car Type-A trains operating up to 140 km/h speed powered by 25kV AC overhead lines.[3]
Phase 1 runs from Jinxing station in Wenjiang District to Jitouqiao station in Wuhou District. Phase 1 is 26.145 km long with 5.5 km running elevated and 20.6 km running underground. There are 9 stations with 2 elevated stations and 7 underground stations.[4] [5]
Phase 2, currently under construction, will extend the line west across central Chengdu to Gaohong station. It will be 24.8 km long, all underground with 18 additional stations.[6]
Progress
- On February 23, 2017, Sichuan Development and Reform Commission approved Line 17 Phase 1.[7]
- On February 27, 2017, Line 17 Phase 1 started construction.[8] [9]
- On Nov 11 2017, the first tunnel boring machine started digging section between Jiujiang North and Baifoqiao Stations.[10]
- On March 24, 2019, Line 17 phase 1 elevated section was completed.
- On April 9, 2019, Huangshi-Chengdu Fifth People's Hospital, Mingguang-#1 Vent Tunnel sections are completed.
- On August 5, 2019, main structures of all stations on Line 17 was completed.[11]
- On Jan 7 2020, Line 17 Phase 2's Beimenqiao Station started excavation, marking the start of station construction for Phase 2.
- On March 25, 2020, Line 17 Phase 1 finished track-laying.[12]
- On June 19, 2020, Chengdu Metro started 3-month trial operation for Line 17.[13]
- On June 24, 2020, Construction finished for Wutongmiao Depot (五桐庙停车场) for Line 17.[14]
- On December 18, 2020, Line 17 from Jinxing station to Jitouqiao station was opened.
- On Oct 20 2022, 16:40, Line 17 Phase 2's Longzhuayan - Qingshuihedaqiao section finished both tunnel construction. This section is 369.602m long.[15]
- On 12 Feb 2023, Line 19 Phase 2 is officially powered on.[16]
- On 21 Feb 2023, Line 19 Phase 2 signal and communication system started operational testing in Xinmiao Control Centre (新苗控制中心), and Phase 2 signal now synchronizes with Phase 1.[17]
- On 22 Feb 2023, Line 17 Phase 2 finished station's main power centre's land clearance.[18]
- On 20 March 2023, Line 19's Changshuncun Depot (长顺村停车场) is handover to operation.[19]
- On 28 March 2023, Line 19 Phase 2 finished 160 km/h high-speed train testing, entering 1–2 months of systematic testing.[20]
- On 28 March 2023, Chengdu Rail Transit 2023 Annal Media Gala was held in Wenjiashan Station of Line 19.[21]
- On 30 March 2023, Line 19 Phase 2 finished construction and handover to operation team for operational testing.[22]
- On 26 May 2023, all 45 trains of Line 19 Phase 2 are delivered.[23]
- On 6 September 2023, Chengdu Metro debuted Train Maintenance Bots (车辆巡检机器人), AI-Railway Maintenance Bots (轨道智能巡检机器人), and Power-line Surveillance AI (弓网在线监测装置) on Line 19. This is the first AI-Maintenance Robot & System in the world. Chengdu Metro will implement full AI-Operation by 2025.[24]
- On September 17, 2023, original Line 17 Phase 1: (Jinxing - Jitouqiao) splits into Line 19 Phase 1: (Jinxing - Jiujiang North) and new Line 17: (Jiujiang North - Jitouqiao), and 4-Car A-Train starts operation on Line 17. All passengers must transfer at the same platform at Jiujiang North between line 17 and line 19.[25] [26]
- On September 26, 2023, Line 18 and Line 19 starts co-operational testing.[27]
- On September 30, 2023, Line 17 Phase 2's People's Park station finished structure construction.[28]
- On Oct 3, 2023, Line 17 Phase 2's Qingshuihedaqiao station to Huanhhali station finished both tunnel construction.[29]
Operation
Opening - 2023 September
Line 17 Phase 1 and Line 19 Phase 1 were running in connection as one route.
September 2023 - Now
Original Line 17 Phase 1: (Jinxing - Jitouqiao) splited into Line 19 Phase 1: (Jinxing - Jiujiang North) and new Line 17: (Jiujiang North - Jitouqiao), and 4-Car A-Train starts operation on Line 17. All passengers must transfer at the same platform at Jiujiang North between line 17 and line 19.[30] [31]
Future
When Line 17 Phase 2 and Line 19 Phase 2 are finished, the operation plan will be:[32]
Line 17 Section:Jiujiang North - Baifoqiao - Jitouqiao
Line 19 Section:Jinxing - Huangshi - Chengdu Fifth People's Hospital- Fengxihe - Wenquan Avenue - Mingguang - Jiujiang North
Stations
Station№ | Station name | Transfer | Distance
| Borough |
---|
| |
---|
|
17 01 | | | | | | Chenghua |
17 02 | | | | | |
17 03 | | | | | |
17 04 | | | (OSI:) | | |
17 05 | | | | | |
17 06 | | | | | |
17 07 | | | | | |
17 08 | | | | | |
17 09 | | | | | | Jinniu |
17 10 | | | | | |
17 11 | | | | | | Qingyang |
17 12 | | | | | |
17 13 | | | | | |
17 14 | | | | | |
17 15 | | | | | | Wuhou |
17 16 | | | | | |
17 17 | | | | | |
17 18 | Yanggongqiao | | | | |
17 19 | | | | —— | 0.000 |
17 20 | | | | 1.468 | 1.468 |
17 21 | | | | 4.179 | 5.647 | Shuangliu |
| |
Notes and References
- Web site: 12月18日五线齐发,成都轨道交通运营里程突破500公里!.
- News: 成都轨道交通17号线二期工程可行性研究及勘察设计总承包招标公告. 四川日报. 2017-08-01. 2017-08-01. zh.
- News: 成都轨道交通17号线二期工程可行性研究及勘察设计总承包招标公告. 四川日报. 2017-08-01. 2017-08-01. zh.
- Web site: 地铁19号线一期. 成都地铁 . 2017-10-16. 2017-10-16. zh .
- Web site: 轨道交通17号线一期. 2018-04-04.
- News: 成都轨道交通17号线二期工程可行性研究及勘察设计总承包招标公告. 四川日报. 2017-08-01. 2017-08-01. zh.
- News: 成都轨道交通11号线一期、17号线一期工程可研报告获批. 四川新闻网. 2017-02-23 . 2017-02-23 . zh .
- Web site: http://news.163.com/17/0228/08/CEBL3B71000187VI.html. zh:成都地铁17号线一期开建 预计2020年通车_网易新闻 . news.163.com. 2018-08-19.
- News: 成都地铁17号线一期开建 预计2020年通车. 网易. 2017-02-28. 2017-02-28. zh. https://web.archive.org/web/20180508185122/http://news.163.com/17/0228/08/CEBL3B71000187VI.html. 2018-05-08.
- News: 串联温江、武侯和双流 成都地铁17号线开始"打洞". 四川在线. 2017-11-29 . 2017-11-29. zh .
- News: 成都地铁17号线一期全线车站封顶 . 成都市温江区人民政府 . 2019-08-07 . zh .
- News: 成都轨道交通17号线一期"长轨通" 温江将迎双地铁时代.
- News: 即将开启空载调试、空载试运行 成都地铁9号线、17号线离开通也近了!.
- News: 成都地铁17号线列车有家啦!五桐庙停车场主体工程完工.
- Web site: 成都地铁17号线二期龙~清区间双线顺利贯通 . 2023-10-09. 2022-10-24. crcc 24.
- Web site: 195座车站封顶、23个TOD实施 成都轨道集团迎来一季度"开门红". zh.
- News: 2022-12-21. 地铁19号线二期年内试运营!成都轨交建设最新进展. zh.
- News: 2022-12-21. 地铁19号线二期年内试运营!成都轨交建设最新进展. zh.
- Web site: 195座车站封顶、23个TOD实施 成都轨道集团迎来一季度"开门红". zh.
- Web site: 热滑完成!成都地铁19号线二期提前通车有望.
- Web site: 成都轨道交通19号线二期举办"开门评风"媒体交流活动.
- Web site: 成都轨道交通19号线二期轨行区正式移交运营.
- Web site: 成都轨道交通19号线二期45列电客车全数交付 . . zh.
- Web site: 成都:创新引领科技赋能轨道交通高质量发展.
- Web site: 地铁17号线"一拆为二" 来看看会有哪些变化. zh.
- Web site: 成都地铁19号线二期开通在即 17号线将在九江北站"分家". zh.
- Web site: 离开通再近一步!成都地铁19号线二期最新消息. zh.
- Web site: 中铁广州局重点项目之成都地铁10号线项目. 2023-10-09. 中铁广州工程局城建公司 . 2023-09-29 . 中铁广州工程局城建公司 .
- Web site: 【e周发声】第247期-成都轨道交通17号线清水河大桥站~浣花里站区间双线贯通. 2023-10-09. 2023-10-09 .
- Web site: 地铁17号线"一拆为二" 来看看会有哪些变化. zh.
- Web site: 成都地铁19号线二期开通在即 17号线将在九江北站"分家". zh.
- News: 2018-03-29. 成都地铁17号线"最难建段"开始掘洞. zh. 四川在线. 2018-03-29.