HCMC Metro Line 1 explained

Line 1
Tuyến số 1
Type:Rapid transit
System: Ho Chi Minh City Metro
Status:Under Construction
Locale:Ho Chi Minh City, Vietnam
Stations:14
Planopen:Q4 2024
Owner:Vietnam Railways
Operator:Management Authority of Urban Railways
Depot:Long Binh
Linelength:19.7km (12.2miles)
Map State:collapsed

Line 1 is a rapid transit line of the Ho Chi Minh City Metro, Vietnam.[1] Line 1 is the city's first metro line, connecting District 1 and Thu Duc City.[2] [3] The line began construction in 2012, initially scheduled for completion in 2018. The project's completion date has been delayed to the end of 2024.[4] [5] [6] Ticket prices will range from VND9,000-23,000 ($0.39-1) per trip.[7]

History

The line was designed by Nippon Koei. The above-ground section was constructed by a joint venture between the Japanese rail corporation Sumitomo Group and Vietnamese state-owned corporation Cienco 6. The underground section was constructed by two Japanese companies, Shimizu Corporation and Maeda Corporation. 83% of the project finance was provided by Japanese government loans through Japan International Cooperation Agency, while the rest was provided by the Vietnamese government.[8]

On 13 September 2017, the authorities announced that Line 1 would be delayed for two years. Cost overruns, audits, and delayed payments to contractors contributed to the delay. The targeted completion date was set for 2020.[9] Planners expect the route to serve more than 160,000 passengers daily upon launch, increasing to 635,000 by 2030 and 800,000 by 2040. All stations along the route are expected to accommodate the disabled, with automatic ticket vending machines, telephone booths, restrooms, subway doors and information bulletins accessible to the handicapped and visually impaired.

On 28 January 2019, MAUR Director of Project Management Unit Duong Huu Hoa stated that as of December 2018, construction progress of Line 1 has reached 62%, below the target of 65%. The project has been criticised by the local press for its repeated delays.[10]

By August 2022, the line is 92% complete. 17 Hitachi train sets have arrived and are undergoing testing.[11] [12]

By February 2024, the line is now 97.5% complete. Test runs have begone occurring, and MAUR are planning for commercial use in Q4 2024. [13]

Stations

The first three stations - Bến Thành, Opera House and Ba Son - are underground, with the remainder being on elevated track.[14]

Station symbolStation nameLayoutMetro transfersLocation
WardDistrictCity
UndergroundBến ThànhDistrict 1Ho Chi Minh City
Opera HouseUndergroundBến Nghé
Ba SonUnderground Tramway (planned)
Văn Thánh ParkElevatedPhường 22
Tân CảngElevated Line 5 (planned)Phường 25
Thảo ĐiềnElevated Monorail 2 (planned)Thảo ĐiềnThu Duc City
An PhúElevated
Rạch ChiếcElevatedAn Phú
Phước LongElevatedTrường Thọ
Bình TháiElevated
Thủ ĐứcElevatedBình Thọ
High Tech ParkElevatedLinh Trung
National UniversityElevated
Suối Tiên TerminalElevatedBình ThắngDĩ An

Notes and References

  1. Web site: Home . 2022-08-31 . maur.hochiminhcity.gov.vn.
  2. Web site: Preston . Robert . 2022-06-14 . Ho Chi Minh City metro to open in 2023 . 2022-08-31 . International Railway Journal . en-GB.
  3. Web site: VnExpress . Saigon metro depot readies after receiving all 17 trains . 2022-08-31 . VnExpress International – Latest news, business, travel and analysis from Vietnam . en.
  4. Web site: VnExpress . HCMC's first metro line delayed again - VnExpress International . 2024-03-14 . VnExpress International – Latest news, business, travel and analysis from Vietnam . en.
  5. News: 2022-08-18 . Vietnam Is Growing at 7%. Hanoi Can Do a Lot Better. . en . Bloomberg.com . 2022-09-01.
  6. Web site: Unfinished business: Vietnam's long-awaited urban commuter rail . 2022-10-11 . Nikkei Asia . en-GB.
  7. Web site: VnExpress . HCMC metro fare proposed at up to $1 - VnExpress International . 2022-08-31 . VnExpress International – Latest news, business, travel and analysis from Vietnam . en.
  8. Web site: Ho Chi Minh City metro to open in 2023 . Railway Journal . 14 June 2022 . Robert . Preston .
  9. Ho Chi Minh City selects underground contractors . . 26 July 2014 . 2015-04-25 . 2015-01-12 . https://web.archive.org/web/20150112084020/http://www.railwaygazette.com/news/news/asia/single-view/view/ho-chi-minh-city-selects-underground-contractors.html . dead .
  10. Web site: Nguy cơ tạm dừng dự án Metro số 1 TP.HCM: Hậu quả khôn lường!. 14 October 2017.
  11. Web site: VnExpress . Last trains arrive for first Saigon metro - VnExpress International . 2022-09-01 . VnExpress International – Latest news, business, travel and analysis from Vietnam . en.
  12. Web site: Nguyen . Ngoc . 2022-08-31 . Trains of HCMC's first metro line to conduct test runs in four months . 2022-09-01 . The Saigon Times . en-US.
  13. https://e.vnexpress.net/news/traffic/hcmc-s-metro-trains-to-run-on-trial-basis-throughout-tet-4710517.html
  14. Web site: 4.2 Alignment Layout 4.2 Alignment Layout . 2024-04-22 . hcmcmetroline1-scc.com.vn.