Lauingen Energy Park Explained
Lauingen Energy Park |
Image Alt: | solar park |
Coordinates: | 48.5369°N 10.4242°W |
Country: | Germany |
Location: | Lauingen |
Status: | O |
Construction Began: | 2008[1] |
Commissioned: | June 2010[2] |
Solar Type: | PV |
Ps Units Operational: | 306,084 (288,132 First Solar 17,952 Yingli) |
Ps Site Area: | 631NaN1 |
Ps Electrical Capacity: | 25.7 MW |
Ps Annual Generation: | 26.98 GWh[3] |
Ps Electrical Cap Fac: | 12.0% |
The Lauingen Energy Park is a 25.7–megawatt (MW) photovoltaic power station, located in Bavarian Swabia, Germany. It covers an area of 63ha and was commissioned in June 2010.
The project was built in three phases:
- The 10.0 MW Helmeringen 1 (already commissioned in 2009)
- The 9.4 MW Helmeringen 2
- The 6.3 MW Helmeringen 3 (built and commissioned in 2010)
The largest solar power station in Swabia was built by the German company Gehrlicher Solar and features the following key figures:
-
- 18 SMA solar inverters
- 3 Siemens central inverters
- a total of 664 km solar cable trays
- a projected generation of almost 27 million kilowatt-hours (kWh)
- an avoided 14,353 tons of CO2 per year
- powers about 7,500 average households with clean energy, where average means a three-person household with an annual electricity consumption of 3,500 kWh.
See also
Notes and References
- http://www.augsburger-allgemeine.de/dillingen/Groesster-Solarpark-Schwabens-in-Helmeringen-id4002526.html Größter Solarpark Schwabens in Helmeringen
- http://www.gehrlicher.com/fileadmin/content/pdfs/Factsheets/Factsheet_Lauingen_A4_en.pdf Factsheet - Lauingen Energy Park
- http://www.greentech-germany.com/gehrlicher-solar-ag-weiht-groesstes-solar-kraftwerk-schwabens-25-7-mwp-offiziell-ein-a16511 Gehrlicher Solar AG weiht größtes Solar-Kraftwerk Schwabens