Bridge Name: | Lane Avenue Bridge | ||||||||||||
Carries: | Lane Avenue | ||||||||||||
Crosses: | Olentangy River | ||||||||||||
Locale: | Columbus, Ohio, USA | ||||||||||||
Maint: | Franklin County Engineer | ||||||||||||
Designer: | Jones-Stuckey Ltd., Civil Engineering Firm, Columbus, Ohio | ||||||||||||
Design: | Cable Stayed | ||||||||||||
Pierswater: | 1 | ||||||||||||
Length: | 3700NaN0 | ||||||||||||
Lanes: | 4 westbound, 2 eastbound, 2 pedestrian | ||||||||||||
Begin: | 2002 | ||||||||||||
Complete: | 2003 | ||||||||||||
Open: | November 14, 2003 | ||||||||||||
Mapframe-Custom: |
| ||||||||||||
Mapframe-Caption: | Interactive map outlining the Lane Avenue Bridge | ||||||||||||
Coordinates: | 40.0065°N -83.022°W |
The Lane Avenue Bridge is a cable-stayed bridge over the Olentangy River in the American city of Columbus, Ohio. Designed by Jones-Stuckey Ltd., the construction was completed on November 14, 2003, after only sixteen months, five months ahead of schedule. The bridge is 113abbr=offNaNabbr=off in length, carrying six 3.5abbr=offNaNabbr=off wide lanes for vehicle traffic, as well as two 3.5 meter sidewalks. The cable stayed design was chosen for aesthetic reasons, as well as having a smaller potential for environmental degradation on the river environment. The anchorages for the cables, at 47 tons (104,000 lbs),[1] are noted as being the heaviest single pieces of steel ever to be galvanized. Total price for the project was US$15.6 million with the following funding sources:
Previously, traffic on Lane Avenue was carried by a 3 lane earth filled arch bridge, which opened in 1919. By 1998, it was determined that the bridge was deteriorating; thus a replacement was needed. Construction on the new bridge started on February 27, 2002, with the old bridge being demolished on November 25 of the same year, after the final home football game at Ohio Stadium, nearby.