Koldam Dam Explained

Koldam
Name Official:Koldam Hydro Power Station
Location Map:India
Coordinates:31.3831°N 76.8711°W
Country:India
Location:Bilaspur district
Status:O
Construction Began:2004
Opening:2015
Owner:NTPC Limited
Dam Type:Embankment, rock-fill with clay core
Dam Height Thalweg:1530NaN0
Dam Height Foundation:1670NaN0
Dam Length:4740NaN0
Dam Width Crest:140NaN0
Dam Width Base:768.97 m
Dam Volume:120000000NaN0
Dam Elevation Crest:6480NaN0
Dam Crosses:Sutlej
Spillway Type:Chute with flip bucket, six radial gates
Spillway Capacity:165000NaN0
Res Capacity Total:5760000000NaN0[1]
Res Capacity Active:90 MCM
Res Capacity Inactive:486 MCM
Res Catchment:53770 Sq Km
Res Surface:12.5 Sq Km
Res Elevation:6420NaN0[2]
Res Max Length:400NaN0
Plant Hydraulic Head:131.20NaN0 (static)
Plant Commission:2015[3]
Plant Turbines:4 x 200 MW Francis-type
Plant Capacity:800 MW
Plant Annual Gen:3055 million units (3055 GWh)
Plant Capacity Factor:43.58

The Koldam Hydropower Station, commonly known as Koldam, is an embankment dam on the Sutlej River upstream of the Dehar Power House. It is 18 km from Bilaspur off the Chandigarh-Manali Highway (NH-21) near Barmana, Himachal Pradesh, India. The main purpose of the dam is hydroelectric power generation and it will support an 800 MW power station. The dam was constructed by NTPC Limited (erstwhile National Thermal Power Corporation Limited).[4]

Koldam project was first conceived in mid‐sixties and investigations on various possible sites had been in progress since 1966. Based on investigation carried out until 1975, a project report was prepared which envisaged construction of rockfill dam having an installed capacity of 600 MW. The work of investigation and studies was taken by HPSEB in October, 1984. The project capacity was revised to 800 MW, but work did not start for lack of funds. Subsequently, Koldam Hydro Project was taken over by NTPC in 2000 and Project Report was revised with a 167m high rock fill dam and Surface Power House located at toe of the dam with installed capacity of 4X200 MW.

The foundation stone for the dam was laid on 5 June 2000 by Prime Minister Atal Bihari Vajpayee. On 14 January 2004, main construction on the dam began. KB Dubey was the first Head of the Project (BUH) . The current BUH is NS Thakur (since 2020).

Due to problems associated with geological issues and declaration of part of reservoir area in 2006 as extension of Majathal Wildlife Sanctuary, the project got delayed. Attempts to impound the reservoir first failed in December 2013 due to problems with sealing the diversion tunnels. By 18 March 2014, a fourth attempt to seal the tunnels and fill the lake was underway.[5] Repairs were made and another unsuccessful impounding was reached in April 2014 as the diversion tunnel continued to leak.[6] Another period of impounding began on 3 November 2014 and finished on 3 January 2015. A tunnel still leaked though but authorities were confident they would have the power station operational by April.[7] Generator commissioning was originally scheduled for 2009 but was rescheduled to 2015.[8] [9]

Construction

The contract of construction of dam was awarded to Thailand's ITD Public Company Limited. A joint venture company of BHEL, Toshiba and Marubeni supplied turbines and generators.

Power generation capacity

Its installed capacity is of 800 MW (4x200 MW). The first 200 MW Francis turbine-generator was commissioned on 30 March 2015 and the third on 10 April 2015.[10] [11]

Unit number Capacity (MW) Date of commissioning Status
1 200 31 March 2015 commissioned.[12]
2 200 30 March 2015 commissioned
3 200 10 April 2015 commissioned
4 200 12 June 2015 commissioned
TOTAL 800

See also

Notes and References

  1. Web site: Heard. S.P.. Koldam hydroelectric Project a new hydroelectric project on the Satluj river in India.. 23 November 2011. P. . Gardron . R.C. . Senan . M. . Agarwal.
  2. Web site: Kol Dam Hydro Electric Power Project. Italian-Thai Development PLC. 23 November 2011. 3 December 2011. https://web.archive.org/web/20111203224000/http://www.itd-koldam.com/intro.php. dead.
  3. Web site: Kol Dam HEP commissioning now slated for 2013. Asian Power. 23 November 2011. 24 June 2011.
  4. News: BHEL starts NTPC's 800-MW Koldam hydro power plant - The Economic Times. The Economic Times. 2016-01-09.
  5. News: Impounding of water in NTPC's Koldam hydel project begins. 1 April 2014. Power Business View. 18 March 2014. 7 April 2014. https://web.archive.org/web/20140407172127/http://powerbusinessview.com/index.php/component/k2/item/1024-impounding-of-water-in-ntpc-s-koldam-hydel-project-begins. dead.
  6. News: NTPC conducts reservoir impounding for Kol dam project . 9 April 2014 . The Times of India . 13 May 2014.
  7. News: 2nd phase of impounding over, but leakage continues. 17 January 2015. The Tribune. 12 January 2015.
  8. Web site: Koldam Project of NTPC suffers major setback in Himachal. Jagran Post. 23 November 2011. 5 June 2011.
  9. Web site: 800 MW Koldam project commissioning extended to April 2014. MoneyControl. 2 August 2013. 15 December 2012.
  10. News: NTPC's First Hydropower Project Starts in Himachal. 1 April 2015. Press Trust of India. NDTV Convergence. 30 March 2015.
  11. News: NTPC Ltd commissions Unit 3 of 200 MW of Koldam Hydro Power Project. 13 May 2015. Equity Bulls. 19 April 2015. 18 May 2015. https://web.archive.org/web/20150518071948/http://www.equitybulls.com/admin/news2006/news_det.asp?id=157904. dead.
  12. Web site: BHEL commissions 4 sets of 200 MW each at Koldam Hydro Electric Project.