Klaipėda Combined Heat and Power Plant explained

Gren Klaipėda Combined Heat and Power Plant
Name Official:Gren Klaipėda termofikacinė elektrinė
Country:Lithuania
Location:Klaipėda
Coordinates:55.6839°N 21.2005°W
Status:O
Construction Began:2011
Commissioned:2013
Cost:126 mil. EUR
Operator:Fortum Heat Lietuva
Th Fuel Primary:Biomass
Ps Electrical Capacity:20 MW
Ps Annual Generation:140 GWh (power)
400 GWh (heat)[1]

Gren Klaipėda, formerly Fortum Klaipėda, is combined heat and power plant in Klaipėda, Lithuania and it uses biomass and waste to produce energy.[2] Originally built in Klaipėda Free Economic Zone by Fortum Heat Lithuania which belongs to Finnish energy company Fortum.

Lithuanian president Dalia Grybauskaitė and Finnish president Sauli Niinistö both participated in the opening ceremony of the plant in 2013.[3]

Notes and References

  1. http://www.delfi.lt/verslas/energetika/klaipedoje-jau-gamina-energija-is-siuksliu.d?id=60820935 Klaipėdoje jau gamina energiją iš šiukšlių
  2. https://archive.today/20140118015829/http://www.15min.lt/naujiena/verslas/bendroves/fortum-klaipeda-i-jegaine-nori-atsivezti-atlieku-is-kitu-salies-regionu-663-382662 „Fortum Klaipėda“ į jėgainę nori atsivežti atliekų iš kitų šalies regionų
  3. http://www.delfi.lt/verslas/energetika/klaipedoje-atidaryta-termofikacine-elektrine-uz-435-mln-lt.d?id=61389851 Klaipėdoje atidaryta termofikacinė elektrinė už 126 mln. EUR