Kirkthorpe Hydro Explained

Kirkthorpe Hydro
Location Map:West Yorkshire
Location Map Caption:Location within West Yorkshire
Coordinates:53.6865°N -1.4597°W
Country:England
Location:Kirkthorpe, Wakefield
Purpose:P
Status:O
Construction Began:April 2016
Opening:March 2017
Cost:£5.3 million ($7.6 million)
Plant Type:C
Plant Turbines:1
Plant Annual Gen:500 kW

Kirkthorpe hydro is a hydroelectric generating plant located on the River Calder at Kirkthorpe Weir, east of the City of Wakefield in West Yorkshire, England. The plant was opened in 2017 and expects to be generating electricity for 100 years. Kirkthorpe Weir is the highest industrial weir in Yorkshire and has prevented fish passing upstream to spawn; the new hydro project has a fish pass built into it.

At a nameplate capacity of 500 kW, along with another plant at Brotherton on the River Aire, the plant is jointly the largest hydroelectric generator in Yorkshire.[1]

History

Kirkthorpe Weir, which is a grade II listed structure, has been an obstruction for fish passing up the River Calder since it was built in 1827. It is a 4m (13feet) drop weir which is the highest in Yorkshire,[2] and was built to maintain a steady flow of water into the Aire and Calder Navigation which branches off just upstream of Kirkthorpe Weir on the left bank.[3] Barn Energy proposed building a hydroelectric power station on Kirkthorpe Weir, with permission being granted by Wakefield Council, on whose land the power station is located.[4] Work on the £5.3 million ($7.6 million) project was started in April 2016 and generation started in March 2017.[5] [6]

Special measures were taken to adopt a fish pass and a separate eel pass. The turbine channel has screen at both ends to prevent fish being sucked in from the top and also to stop larger fish entering from the bottom. The eel pass has a constant flow of water and is protected by overhead screens to prevent predation.[7] The power station has a 500 kW capacity which will generate 2.3 million units of electricity per year, enough to power over 800 homes.[8]

In 2019, the site was furnished with a 1,200 kWh lithium-ion battery.[9] As the turbine is generating constantly with water running through the power station, the unused electricity is stored in the battery which can be released at a time when supplies are lower.[10]

In 2019, Kirkthorpe Hydro along with Thrybergh Hydro, a sister project on the River Don also built by Barn Energy, were sold to JLEN in a £4.3 million deal.[11]

External links

Notes and References

  1. News: Hydropower station could start generating electricity to power homes . 20 July 2019 . Wakefield Express . 14 October 2016.
  2. News: Fearnley . Steve . Angling: Hydro's the 'weir' to go for anglers and the fish . 20 July 2019 . Yorkshire Evening Post . 28 March 2017.
  3. Web site: Kirkthorpe Weir and Hydropower Station . Wessex Archaeology . 21 July 2019.
  4. Web site: Work starts on £5.3m hydropower scheme in Yorkshire . www.waterbriefing.org . 20 July 2019 . 20 April 2016.
  5. News: Hydro-electric plant being built on River Calder . 20 July 2019 . Pontefract and Castleford Express . 18 April 2016.
  6. News: England's 500-kW Kirkthorpe small hydropower plant officially opens . 20 July 2019 . Hydro World . 15 March 2017.
  7. Web site: KIRKTHORPE HYDROPOWER: Bringing Salmonids back to the Calder Valley . wakefield.gov.uk . 20 July 2019 .
  8. News: Hydro-electric plant being built on River Calder . 23 July 2019 . infoweb.newsbank.com . 18 April 2016. subscription.
  9. Web site: Barn Energy installs batteries at 2 UK hydro schemes . renewablesnow.com . 21 July 2019.
  10. Web site: Blaber . Russ . Co-locating Battery Storage with Hydropower Generation . British-hydro.org . Cobalt Project Management Ltd . 23 July 2019 . 10 . June 2018.
  11. News: Snowden . Ros . Yorkshire green energy firm snapped up in multi-million pound deal . 20 July 2019 . The Yorkshire Post . 20 July 2019.