Kibo Gauteng Thermal Power Station Explained

Kibo Gauteng Thermal Power Station
Country:South Africa
Location:Gauteng Industrial Park, Gauteng
Construction Began:2022 Expected
Cost:US$12 million
Owner:Sustineri Energy
Operator:Sustineri Energy
Status:P
Th Fuel Primary:plastics
Ps Electrical Capacity:2.7MW
Commissioned:2023 Expected

Kibo Gauteng Thermal Power Station is a planned thermal power station in South Africa. The power station is under development by a joint venture company called Sustineri Energy, co-owned by Kibo Energy, an Irish IPP and Industrial Green Energy Solutions (IGES) of South Africa. The energy generated here will be sold directly to a developer of industrial parks, based in Gauteng, South Africa, under a 10-year power purchase agreement (PPA) between the parties.[1] [2]

Location

The power station would be located in Gauteng Industrial Park, in Gauteng Province, where both Johannesburg, the country's business centre and Pretoria, South Africa's capital city are located.[1] [2]

Overview

The power station is being developed to supply baseline electricity to a developer of industrial parks in Gauteng Province, South Arica. The process involves the incineration of selected plastic waste at above 400C in the absence of oxygen, in a process called pyrolysis. This produces synthetic gas (syngas) and heat. The syngas is used to drive generators to produce electricity and the heat is sold to other industries in the industrial park.[1] [2] [3]

It is anticipated that in 24 to 26 months, business will have picked up to warrant the expansion of the power station, tripling its output to 8 megawatts.[1] [2] [3]

Developers

The owners/developers of this energy infrastructure have formed a joint venture company, named Sustineri Energy, which will own, design, finance, develop, build, operate and maintain this power station. The table below illustrates the shareholding in Sustineri Energy.[1]

Shareholding In Sustineri Energy! Rank !! IPP/Developer !! Domicile !!% Ownership !!Notes
1 Kibo Energy Plc 65.0
2 Industrial Green Energy Solutions Pty 35.0

Construction and timeline

The construction of the power station is budgeted at ZAR:180 million (approx. US$12 million). Construction is expected to start in the second half of 2022 and last about 12 to 14 months. The engineering, procurement and construction (EPC) contract was awarded to Lesedi of South Africa. The same company was also selected as the "operations and management contractor".[1] [2]

See also

External links

Notes and References

  1. Web site: Engineering News South Africa . Kibo to build plastics-to-syngas plant in Gauteng industrial park . 14 February 2022 . Marleny Arnoldi . 4 March 2021 . Bedfordview, Johannesburg, South Africa.
  2. Web site: Afrik21.africa . South Africa: Kibo to generate electricity from plastics in Gauteng . 16 February 2022 . Inès Magoum . 4 March 2022 . Paris, France.
  3. Web site: Africanreview.com . Kibo Energy signs 10-year clean energy PPA on South Africa waste to energy project . 23 February 2022 . African Review . 4 February 2022 . London, United Kingdom.