Kawanda–Birembo High Voltage Power Line Explained

Kawanda–Birembo High Voltage Power Line
Country:Uganda and Rwanda
Coordinates:-0.5905°N 30.4302°W
Direction:North to South
Start:Kawanda, Uganda
Through:Masaka, Mbarara, Mirama Hills
Owner:Government of Uganda & Government of Rwanda
Partners:African Development Bank
Operator:Uganda Electricity Transmission Company Limited & Rwanda Energy Group Limited
Contractors:Multiple
Construction:2014
Expected:2019
Current Type:AC
Length:420
Ac Voltage:220kV
Circuits No:2

Kawanda–Birembo High Voltage Power Line is a high voltage electricity power line, under construction,[1] connecting the high voltage substation at Kawanda, in Uganda to another high voltage substation at Birembo, in Rwanda.[2]

Location

The 220 kilovolt power line starts at the Uganda Electricity Transmission Company Limited power station at Kawanda, Wakiso District, in Uganda's Central Region, approximately 15.5km (09.6miles), by road, north of Kampala, the capital and largest city of Uganda. From here, the line travels to the southwestern Ugandan city of Masaka, a straight-line distance of about 121km (75miles). From Masaka, the power line continues west to the city of Mbarara, a straight distance of approximately 130km (80miles). From Mbarara the power line travels in a general southerly direction to the town of Mirama Hills, a distance of about 66km (41miles).[2] From a substation in the Mirama Hills/Kagitumba neighborhood, the power line continues in a southwesterly direction to end at a substation in Birembo, Kinyinya Sector, Gasabo District, Rwanda,[3] in the northern suburbs of Kigali, the capital and largest city of Rwanda, a straight-line distance of about 110km (70miles).

Overview

This power transmission line connects the electricity grid of Uganda to that of neighboring Rwanda. It is in line with the Nile Equatorial Lakes Subsidiary Action Program, Interconnection of Electric Grids Project, led by Regional Manager, Grania Rubomboras.[4] The power line is being developed in tandem with Karuma Hydroelectric Power Station, whose capacity output of 600MW is expected to be consumed locally and the balance sold regionally, with Rwanda, Burundi and the Democratic Republic of the Congo as potential customers.[5]

Construction in Uganda

The project on the Uganda side is divided into three sections:(a) the Kawanda–Masaka section, measuring about 137km (85miles)[6] (b) the Masaka–Mbarara section, measuring about 130km (80miles) and (c) the Mbarara–Mirama Hills section, measuring about 66km (41miles). The Kawanda–Masaka section was constructed at a budgeted cost of US$153.20 million, of which the World Bank lent US$120 million. Completion was expected in January 2019.[6] However, in July 2018, the Daily Monitor reported that the 220kV line had been commissioned.[7] [8]

The Masaka–Mbarara section was budgeted at €50 million, to be borrowed from the European Union Africa Infrastructure Fund. Work is expected to start in the fourth quarter of 2017 and is expected to conclude in 2019.[9] In March 2018, The Uganda Independent reported that the Ugandan government borrowed €37.1 million from the French Development Agency and another €35 million from the German Development Bank to finance the Masaka-Mbarara section of this transmission line.[1] The Mbarara–Mirama Hills section was completed in 2015.[10]

Construction in Rwanda

The Mirama Hills/Kagitumba–Birembo section measures approximately 100km (100miles). The Mbarara–Birembo section measures about 166km (103miles).[11] As reported by the EastAfrican in May 2015, this 220kV network already exists.[12] Rwanda is also in the process of building a 220kV substation in Birembo.[13]

Recent developments

At a later date, the entire Kawanda–Birembo High Voltage Power Line is expected to be upgraded to 400kV.[14] In May 2018, the Ugandan government borrowed €37.1 million (about US$44.2 million), from the French Development Agency, to upgrade the 135km (84miles), between the cities of Masaka and Mbarara to 400kV.[15] In November 2020, the New Vision newspaper reported that the German Development Bank (KfW) had partially co-funded the upgrade of the Masaka–Mbarara section to 400kV.[16]

In May 2023, it was reported that there was need for a "communications booster" to be installed at the Rwanda Energy Group (REG) electricity sub-station at Shango, Rwanda to communicate effectively with the Uganda Electricity Transmission Company Limited (UETCL) electricity substation in the city of Mbarara in Uganda. It was also reported that procurement and installation of that booster had been concluded in 2023.[17]

The substation at Shango, which is located approximately 13km (08miles) north of the Birembo substation, has double circuit bays connecting to the electric grids of Rwanda, Uganda, Tanzania, Burundi and DR Congo. This allows both Rwanda and Uganda who have excess electricity to sell, to trade power between each other and to "wheel" excess power to neighboring countries through Shango.[17]

See also

External links

-0.995°N 30.3667°W

Notes and References

  1. Web site: 18 March 2018 . Uganda: Sh459 Billion Approved for New Nile Bridge, Electricity Power Line . 15 March 2018 . Kampala . . The Independent.
  2. Web site: 12 October 2017 . 29 January 2014 . UETCL . Kampala . Progress Report of Projects Under Implementation for Uganda Electricity Transmission Company Limited . Uganda Electricity Transmission Company Limited.
  3. Web site: Rwanda aims to light up 70 percent of rural homes by 2017 . https://web.archive.org/web/20160609140048/http://news.xinhuanet.com/english/2016-06/08/c_135423015.htm . dead . June 9, 2016 . 8 June 2016 . Xinhuanet.com . Xinhua . 12 October 2017.
  4. Web site: Women In Energy: Leader Immersed In Power Projects . 12 October 2017 . December 2016 . ESI Africa Magazine . 2 of 2016.
  5. Web site: 22 June 2016 . Plan to export Karuma excess power on . 12 October 2017 . . Nelson . Wesonga . Kampala.
  6. Web site: Electricity Sector Development Project . 12 October 2017 . 30 June 2011 . Washington, DC . World Bank (WB) . WB.
  7. Web site: UETCL commissions lines for power export . . 30 July 2018 . Shabibah Nakirigya . 30 July 2018 . Kampala, Uganda.
  8. Web site: UETCL Commissions Kawanda-Masaka Power Line, Guarantees Stable Power . 2018 . . 1 December 2018 . Kampala, Uganda.
  9. Web site: Masaka-Mbarara 220kV Transmission Line . 12 October 2017 . December 2016 . European Union Africa Infrastructure Fund.
  10. Web site: Joint Communiqué from the 5th Northern Corridor Integration Projects Summit . 2 May 2014 . . 12 October 2017 . Kigali, Rwanda.
  11. Web site: 12 October 2017 . Invitation for Prequalification: Construction of Uganda (Mirama) Rwanda (Birembo) 220 Kilo Volt Transmission Line And Associated Substation . African Development Bank. Abidjan . November 2011.
  12. Web site: African states to interconnect power grids . 16 May 2015 . Kennedy . Senelwa . . Nairobi . 12 October 2017.
  13. Web site: . 11 July 2014 . Rwanda plans to import power from Kenya by 2015 . Nairobi . 12 October 2017 . Esiara . Kabona.
  14. Web site: December 2014 . Building Modern World Class Infrastructure . The European Times Magazine (TETM) . TETM . 12 October 2017.
  15. Web site: AFD gives Uganda €37.1 million for power transmission line . 22 May 2018 . . Jeff Mbanga . 24 May 2018 . Kampala, Uganda.
  16. Web site: . Uganda boosts power transmission lines . 25 November 2020 . Paul Kiwuwa . 26 November 2020 . Kampala.
  17. Web site: . 17 May 2023 . Rwanda, Uganda In 400MW Energy Deal . Michel Nkurunziza . 10 April 2024 . Kigali, Rwanda . via AllAfrica.com.