Karlsruhe–Basel high-speed railway explained

Karlsruhe–Basel high-speed railway
Native Name:Ausbau- und Neubaustrecke Karlsruhe–Basel
Native Name Lang:de
Start:Karlsruhe Hbf
End:Basel Bad Bf
Linenumber:
  • 4280 (high-speed line)
  • 4000 (original line)
Routenumber:702
Linelength Km:182
Speed:250abbr=onNaNabbr=on
Tracks:2 continuous
Electrification:15 kV/16.7 Hz AC overhead catenary
Locale:Baden-Württemberg, Germany

The Karlsruhe–Basel high-speed railway (Ausbau- und Neubaustrecke Karlsruhe–Basel, literally "Upgraded and new line Karlsruhe–Basel") is a new line being built on the route of the Mannheim–Karlsruhe–Basel railway (Rhine Valley Railway). As a result of the project, the railway through the Rhine Valley is being upgraded to four continuous tracks and its operational efficiency will be increased as a result of the segregation of the various transport flows. The travel time for passenger services between Karlsruhe and Basel is to be shortened by 31 minutes. The project forms part of the RotterdamGenoa corridor and part of it is also part of the Main line for Europe (Magistrale für Europa in German and Magistrale européenne in French; ParisBudapest). In September 2010, it was forecast to be completed in 2020.

Large parts of the line runs next to the existing Rhine Valley Railway. The planning of the line has been carried out progressively since the mid-1980s and the first section of the line between Rastatt Süd and Offenburg, was placed in operation in 1993. While several sections have been opened others are under construction or not started. The main components of the projects include the Rastatt Tunnel, the Katzenberg Tunnel and a western bypass of Freiburg for freight.

The date of the completion of the overall project is uncertain.[1] The Federal Government considers a completion by 2030 possible. Planning services for sections 7.2. to 7.4 have been procured on the basis that it will be completed by the end of 2042.[2]

The planned total cost is €6.172 billion (as of April 2013). Until the end of 2014, €2.27 billion had been spent on it. Deutsche Bahn estimated the total cost in 2015 as being €7.1 billion.[3]

Route

Between Karlsruhe and Offenburg, the route runs closely parallel with the existing Rhine Valley Railway. Between Offenburg and Buggingen (south of Freiburg), it will run next to the A 5 as a new bypass of Freiburg. This section, which is designed to be operated at, is to be used in future by freight trains. A dense population and a reduction in the impact of freight transport were the key reasons for choosing this option. The existing line in this area, running from Offenburg through Freiburg to Buggingen, is to be upgraded for a running speeds of and will be used by all or almost all passenger trains.[4]

In Buggingen, south of Freiburg, the freight bypass and the Rhine Valley Railway will meet up again and run in parallel to Schliengen. Between Schliengen and Eimeldingen the new line runs through the Katzenberg Tunnel, which with a length of 9.4 kilometres is the largest single structure in this section. The tunnel shortens the route for passenger trains, avoiding the winding route along a bank in this area. Later the passenger and freight tracks will run parallel to the Basel rail node.

The line between Rastatt Süd and Offenburg can be operated at . The newly built sections between Buggingen and Basel can also be traversed at this speed. The planned freight bypass of Freiburg is designed for . According to the federal government, although the speeds could have been increased to on some disconnected sections, this would not have had significant travel time benefits. The projected speed of, as opposed to the achieved on recent new lines, results from planning carried out in the 1980s. Between Rastatt station and Rastatt-Niederbühl the line continues to be double-track. This is to be resolved by the construction of the Rastatt Tunnel. The remaining section between Offenburg and Freiburg and further south is still being planned.

The 7 km-long Offenburg Tunnel is to be built under the city of Offenburg, which has 60,000 inhabitants. The German parliament approved the construction and financing of the tunnel on 28 January 2016.[5]

History

Background

In the 20th century, there were demands for a new railway line to stimulate the central and southern Upper Rhine economically and to allow additional traffic to run.

A study in 1964 for the executive board of Deutsche Bundesbahn proposed the straightening of the line—particularly in Rastatt and Offenburg—to achieve significant travel time savings.[6]

A program of upgrades for the Deutsche Bundesbahn network (Ausbauprogramm für das Netz der Deutschen Bundesbahn) that was submitted in 1970 provided for the construction of some 50 kilometre of new line by 1985 to relieve the most heavily used section between Rastatt and Offenburg. The route would branch off the existing Karlsruhe–Ettlingen West–Rastatt line near Muggensturm and bypass Rastatt to the east and Achern to the west. The new line would rejoin the existing line north of Offenburg. The town of Rastatt would have been connected to the new line by a shuttle service.[7] The new section between the Rastatt area and Offenburg was allocated the second highest level of priority of the plan and was therefore targeted to be completed by 1985. The construction of the sections between Mannheim and Karlsruhe and between Offenburg and Basel would have been completed after 1985.[8]

While planning in the first half of the 1970s still provided for an almost direct new line between Karlsruhe and Basel with a large loading gauge (for the transport of trucks in enclosed high-speed wagons), it was updated in the second half of the 1970s.[9] In mid-July 1979, Deutsche Bundesbahn plans announced that the route would no longer consist of a completely new line. Instead, the new line would to a large extent be placed next to the existing line.[10]

In 1990, around 320 trains ran on the existing line on each weekday (total of both directions). In 1992, the existing line between Offenburg and Basel carried approximately 130 trains per day in each direction. The line was considered overloaded, particularly towards Basel, which was calculated as having a capacity of around 110 trains per day.[11] The Federal Transport Infrastructure Plan (Bundesverkehrswegeplan) 1992 forecast an increase in the number of trains south of Offenburg from 133 trains (as of 1992) to 190 trains per day and direction.

Planning

As a result of intermodal economic and business analysis carried out by the Federal Ministry of Transport, the “(Karlsruhe–) Rastatt–Offenburg–Basel railway” was added the Federal Transport Infrastructure Plan 1980 (BVWP 1980).[12] As part of the Stufe I (“level I”) of the BVWP 1980, the first work would have been a new double-track line between Rastatt and Offenburg to be built by 1990 for DM 960 million.[12] [13] In addition, the plan provided for an upgrade to three-tracks between Offenburg and Basel with improvements to the track. A total of DM 2.5 billion (1978 prices) would have been invested in the project.[9] The Federal Transport Infrastructure Plan 1980 also provided for an additional track between Offenburg and Basel in the period after 1990 as part of Stufe II (“level II”).[14] At the end of 1980, the planners envisaged initiating the first planning approval procedure in 1981. A planning group for the upgraded and new line was established in Karlsruhe in 1981. The regional planning approval procedure for the Karlsruhe–Basel section was carried out during 1983 and 1984.

In the mid-1980s, the section between Offenburg and Rastatt was particularly congested. Around 290 trains ran daily through this bottleneck and more on peak days. The then Deutsche Bundesbahn described traffic on the section as exceeding capacity by 30 percent. Traffic was expected to increase to 350 trains per day by the end of the century. It was intended at that time that a 70 km-long new railway line would be built between Durmersheim and Offenburg parallel to the existing line designed for operations at 250 km/h, an upgraded line would be built between Offenburg and Schliengen for operations at 200 km/h (this would have included measures for maximising capacity), an approximately 20 kilometer-long new line would be built between Schliengen and Basel and a planning study would be undertaken for a third track south of Offenburg. The project would have cost 2.3 billion DM and have been completed in 1995. The cost–benefit analysis for the Federal Transport Infrastructure Plan showed a benefit-cost ratio of 5.4 for the overall Karlsruhe–Basel project.[15]

Preparations for the land use and planning approval process began in 1984. The first regional planning process, for the Karlsruhe–Offenburg section, was successfully concluded in the autumn of 1984.[16] Detailed planning commenced immediately and an initial planning approval process for the Achern area was opened in 1985. It was intended that the upgrade project, under which almost 80 percent of the route would have been made operable at 200 km/h, would be finalised if possible by 1994.[17]

In February 1988, the regional planning approval process was commenced for the Schliengen–Basel section.[18]

The Federal Transport Infrastructure Plan 1985 provided for four tracks between Karlsruhe and Offenburg. In the section continuing to Basel the capacity of the two existing tracks would be upgraded and an option for a third track would be considered. Between Offenburg and Schliengen, the line could be upgraded for 200 km/h with relatively little work.[19] The section with projects listed as "urgent requirements" in the BVWP 1985 included the so-called 1. Stufe der ABS/NBS Karlsruhe – Offenburg – Basel ("level 1 of the Karlsruhe–Offenburg–Basel upgraded and new line") with an investment cost of DM 1,678 million. The section covering planning provided DM 532 million for a second stage.[20]

Due to the proposed new and upgraded rail links through the Alps (between Switzerland and Italy and between Austria and Italy), planning for the Karlsruhe–Basel section was checked for adequate capacity around 1989.[21] Although the upgrading of the existing line to enable operations over two tracks at was not listed in the Federal Transport Infrastructure Plan 1985, this specification had already been adopted in the planning. Deutsche Bundesbahn took over the planning in 1989. It developed three groups of options that could be combined for the section between Freiburg and Basel: along the Rhine Valley Railway, along the autobahn and bypass routes. The 1990 planning studies produced forecasts of costs, depending on the option, of around DM four billion, plus or minus 15 percent. Considerations of passenger traffic bypassing Freiburg with a route that was about 7.5 kilometers shorter and would serve the city with a station at the intersection with the Freiburg–Colmar railway at Hochdorf have since been discarded. This bypass of Freiburg would instead serve only freight trains and special trains bypassing Freiburg.

In the second half of 1993, a continuous four-track upgrade of the Rhine Valley Railway was an element of the draft Federal Transport Infrastructure Plan 1992. In addition to Switzerland's decision to implement NRLA, the building of the Betuweroute in the Netherlands, Austria’s introduction of a ban on driving trucks at night on 1 December 1989 and the introduction of the European Union’s internal market on 1 January 1993, the wish to improve rail passenger services was a major reason for its adoption.[22] Construction of a third track on the section was discarded due to insufficient capacity and operational difficulties.

In mid 1986, DB calculated that if construction began in the following year, the project could be completed in 1994. A new line would be built between Rastatt and Offenburg and on the remaining section to Basel the maximum speed would be raised to at least 200 km/h (with occasional line improvements).[23]

The board of Deutsche Bundesbahn authorised the upgrade in December 1986. On 1 January 1987, it approved the construction of the Karlsruhe–Offenburg section.[24] On 21 January 1987, the Federal Transport Minister Werner Dollinger, in agreement with the Minister of Finance, responded to a request of the then Deutsche Bundesbahn and approved funding to build the line as part of the Federal Transport Infrastructure Plan 1985 under section 14.3c of the Bundesbahn Act (Bundesbahngesetz). The costs were then estimated at about DM 2.3 billion; the construction would commence in 1987, although the planning approval process had not yet started. When completed, the travel time between Hamburg and Basel would be reduced by two hours to five and a half hours. The maximum speed between Karlsruhe and Offenburg would be 250 km/h.[25] The existing Rhine Valley Railway would be upgraded between Karlsruhe and Offenburg for continuous operations as 160 km/h.

In December 1987, the first planning approval (for section 4) was finalised. In the same month the first pile was driven for a new bridge over the Acher. Three sections were considered for planning approval in early 1990.

In 1988, it was planned to leave the section between Offenburg and Basel as double track, but to upgrade it for maximum efficiency and a top speed of 200 km/h. A long-term option would be kept open to upgrade it for three-tracks.[26] In 1990, Deutsche Bundesbahn was already examining a continuous four-track upgrade.[27] When the Swiss parliament took the decision in 1991 to adopt the NRLA project, it also assumed that the line south of Offenburg would be rebuilt with four continuous tracks.[28]

On 6 September 1996,[29] an agreement was signed in Lugano between the head of the Federal Department of Transport and Energy of Switzerland and the Minister of Transport of the Federal Republic of Germany to secure the performance of the approach line to the new railway through the Swiss Alps. The progress of work in Germany and Switzerland is regularly reported to a German-Swiss steering committee.[30]

No federal funds for the upgrading of the track were provided between 1998 and 2003. At first, the land-use and planning approval process continued.[31] In the autumn of 1999, it was announced that, because of budgetary constraints, the quadruplication between Offenburg and Basel would not be implemented for the time being. All measures not yet begun were postponed and a new needs assessment and evaluation would be carried out. According to the previous assessment an upgrade of the existing line, including equipping it with CIR-ELKE (a now-superseded form of computerised operations and control of railways developed by Deutsche Bundesbahn in the 1990s) would only become necessary with the full utilisation of the new Alpine crossing. The section of line north of Offenburg would not be affected by the austerity measures.[32] At the end of June 2000, DB Netz was studying the needs of for Offenburg-Niederschopfheim, Schliengen-Eilmeldingen and Haltingen Weil am Rhein sections.[33]

DB and SBB announced at the end of 2002 they would re-examine the Bypass Hochrhein ("High Rhine bypass") feasibility study carried out at the end of 1993 to identify opportunities for capacity expansion in the Basel area.[34] With the introduction of the planning approval procedure for section 7.3 on 3 July 2007, construction approval was sought for all sections between Offenburg and Weil am Rhein. On 4 March 2013, the project advisory board unanimously selected the so-called Bürgertrasse ("citizens’ route") through the Markgräflerland as well as the implementation of additional measures to control noise on the freight train bypass of Freiburg.

Between Karlsruhe and Basel, the estimated travel time reduction for passenger services would be 31 minutes. The scheduled travel time would be 69 minutes. Regional services along the line would also be improved.[35]

In 2009, a project advisory board was established with representatives of the federal and the state department of transport, district administrators, local politicians and citizens' groups.[36]

After five years of discussion, the Projektbeirat Rheintalbahn (“Rhine Valley Railway Project Advisory Group”) held its tenth and final meeting on 26 June 2015.[37] Changes to the existing plan amounted to €2 billion in excess of the legal requirements for noise abatement.[38] It agreed to the construction of the Offenburg Tunnel, a double-track freight line between Offenburg and Riegel, additional noise protection between Hügelsheim and Auggen and an at-grade design for the rail junction at Hügelsheim.[39]

Construction

On 12 December 1987, work began on the construction of two additional tracks on the Rastatt–Offenburg section in Achern station in the presence of the then Chancellery Minister Wolfgang Schäuble. Work began in the Bühl/Ottersweier area in December 1988.[40]

Earthworks, including the track base, were completed at the end of 2006 over a length of over 7.5 kilometres for the new line between Karlsruhe and Rastatt, which was built together with the parallel construction of a new section of federal highway 36. It branches from the old Rhine Railway at the Bashaide block post near Durmersheim and runs to the approximate beginning of a future trough structure on the approach to the Rastatt Tunnel south of Ötigheim. The road and railway tracks are built below natural ground level.

Commissioning

The first nine-kilometre section between Bühl and Achern was taken into operation in March 1993. The southbound track was opened to scheduled traffic on 7 March and the northern track was opened on 28 March. Following the transfer of the traffic from the old tracks—with an unchanged speed of 160 km/h—the original route was rebuilt with new tracks.[41] [42]

The section between Buhl and Offenburg was taken into operation in June 2001. In mid-2003, the entire project was expected to be completed in 2012.[43]

After nine years of construction and the investment of approximately €260 million, the 20 km-long section between Rastatt Süd and Buhl went into operation at the timetable change on 12 December 2004. Four new stations (Baden-Baden Haueneberstein, Baden-Baden Rebland, Sinzheim and Sinzheim Nord) were opened on the new section and a new Karlsruhe Stadtbahn service (S4) was established between Baden-Baden and Achern. Thus, a total of 43 km of the new line had been completed. The total investment at that time amounted to €1.2 billion.[44]

The Katzenberg Tunnel was put into operation in December 2012.

In July 2015, the responsibility for the project was transferred from DB ProjektBau to DB Netz.[45]

Outlook

At least the southerly Katzenberg Tunnel section adjoining Basel has been put into operation in time for the opening of the Gotthard Base Tunnel in 2016.[46] According to the federal government, the piece-by-piece upgrade of the Rhine Valley Railway will provide sufficient capacity for the growth of traffic on the line when it is needed. According to the Federal Ministry of Transport, progress favours the completion by 2022 of the upgrade to four tracks with the exception of the 40-kilometre section between Offenburg and Riegel/Kenzingen. That would mean that four-fifths of the project had been realised.

A forecast for the Federal Transport Infrastructure Plan indicates that 38 pairs of trains in long-distance traffic will run on the Offenburg–Basel section each day. In freight transport, 137 daily trains are expected to run from north to south and 147 trains from south to north. In the section between Buggingen and Basel, 138 trains are expected to run from north to south and 148 trains from south to north. The German government expects the most heavily congested section of the Rhine Valley Railway to carry 335 trains per day in 2025. A forecast for 2030 should be included when the Federal Transport Infrastructure Plan 2015 is presented.[47]

In December 2013, Deutsche Bahn announced its intention to call for tenders for a number of construction projects in the planning approval sections 9.0 to 9.3 for a total of around €200 million.[48]

The Federal Government considers the substantial completion of the project by 2030 is possible if two core requirements, the Offenburg Tunnel and the section next to Autobahn 5 around Freiburg, are omitted.

Karlsruhe–Rastatt section

According to the planning status of 2007, section 1 between Karlsruhe and Rastatt should have been completed by 2011. The federal government proposed in 2007 to significantly increase the annual investment assuming the receipt of planning approvals.[49] No funding for individual sections of the project had been allocated as of October 2010.[50] The estimated total project cost in April 2010 was €5.734 billion.

Due to financial constraints, construction in the Rastatt area was not yet in sight in 2010. Work focused due to limited budgetary resources on the section in southern Baden. At the beginning of 2009, it was decided to revise the decade-old planning for the Rastatt Tunnel and to begin construction in early 2011. This was intended to be funded from the economic stimulus package II. Because of the high financial requirements and the long duration of the project, it was later separated from the stimulus package.

On 24 August 2012, Federal Ministry of Transport, Construction and Urban Development and Deutsche Bahn completed a financial agreement providing €693 million for the most northerly section of the project. It covered the 16 km-long northern section of the line, including the 4.27 km-long Rastatt Tunnel.[51]

Offenburg–Katzenberg Tunnel section

A new line carrying mostly freight will be built from Offenburg to Buggingen, which is located in the middle between Freiburg and Basel. It will start a bit north of Offenburg and use a tunnel to underpass Offenburg. It will run on a separate route west of the current line. The existing line between Offenburg and Buggingen will be enhanced for speeds of 250 or 200 km/h on the existing tracks. Some sections will be expanded to quadruple track. Between Buggingen and the Katzenberg Tunnel the line will be expanded to quadruple track, with two tracks being capable of 250 km/h. The same applies between the Katzenberg Tunnel and Basel. Due to reordering of different trains some shorter sections will have six tracks.[52] South of Offenburg station there is a sharp curve with a radius of 300 to 400 metres with a speed limited to 80 km/h. Deutsche Bahn had investigated the possibility of building the now planned freight train tunnel in Offenburg. First, a route had to be determined and then exploratory drillings were made. Also a route running parallel with the Autobahn between Offenburg and Riegel was examined. The costs of both studies, totalling €1.3 million, were shared equally between the DB and the state of Baden-Württemberg. The additional costs have now been determined, depending on the option, to be €450–780 million. The Federal Ministry of Transport requested that the state of Baden-Württemberg meet half of these costs. The state rejected this demand.[53] According to Deutsche Bahn there is no consensus on a route running parallel with the Autobahn.[54] According to press reports, the additional cost of this option (compared to the route next to the current line as originally proposed) amounts to €300 million.[55]

Contracts for the construction work on the planning approval sections 9.0 to 9.2 were expected to be awarded at the end of 2012. The value of the contracts was estimated at €200 million.[56]

A number of citizens' initiatives, which have combined as the Interessengemeinschaft Bahnprotest an Ober- und Hoch-Rhein (“community of interest of the railway protest of the Upper and High Rhine”; abbreviated IG BOHR), which have been referred to as Baden 21, presented an alternative approach; 172,000 signatures were collected in support of this.[57] The cumulative costs of the proposed measures on the budget presented by Deutsche Bahn were estimated to be over €900 million.

On 5 March 2012, the project advisory board, agreed to the so-called Bürgertrasse ("citizens route") including a freight bypass of Freiburg between Kenzingen and Buggingen as well as changes at Müllheim (displacement of the Buggingen junction to the south) to be realised by 2020. The related costs of €250 million in excess of the statutory requirements for noise and landscape protection (the 5 dB allowance normally given to railway projects in Germany compared to road projects was disregarded for this section), will be shared equally by the federal government and the state of Baden-Württemberg. €84 million of these costs will be incurred on the bypass of Freiburg and €166 million on the remaining route.[58]

On 4 March 2013, the project advisory board called on Deutsche Bahn to abandon planning for the originally planned aboveground route. Deutsche Bahn announced plans to implement this recommendation as soon as funding was secured for such a tunnel.

Progress on project sections

The project is divided into nine sections and 21 planning approval sections (in accordance with the municipal and district boundaries):

Costs and financing

In 2013, Deutsche Bahn estimated that the cost of the project would be €6.172 billion in April 2013 prices. €2.27 billion had been spent on it up to the end of 2014. DB’s estimate had increased to €7.1 billion in mid-2015.

The costs were estimated in mid-2012 as amounting to €5.7 billion, plus a little more than €1 billion for planning costs.[91] According to the Federal Government in January 2013, the future resource requirements would amount to about €3.66 billion. Of these, around €1.23 billion is attributable to sections that are ready for construction or under construction, that is planning approval sections 1, 9.0b, 9.1, 9.2 and 9.3.[92]

At the end of 2007, the total cost was expected to be around €4.5 billion. Approximately €4.2 billion of which would come from the federal government, about €250 million from Deutsche Bahn’s own funds and about €50 million through construction grants from third parties such as the European Union. By mid-2005 about €1.6 billion had already been spent. The project was included in the Federal Transport Infrastructure Plan 2003 as a “priority need”. The bulk of the financing was provided by the federal government. €108 million was invested in 2006.[93]

In the spring of 2005, the federal government announced an additional €500 million for railway projects by 2008, including upgrades and new construction.[94] In 2008, €75.4 million was spent on the project. Previously incurred costs added up to €1,789 million.[95] In 2010, €99.71 million was invested, giving an estimated cumulated cost of €5.743 billion.[96] The estimated total cost had risen to €6.172 billion in 2012.[97] By mid-2010 about €1.8 billion had been invested in the project.

Deutsche Bahn justified the cost increase over the estimated cost of 2003 (€4.5 billion) as an acceptable variation from the nominal value of the construction cost at the planned completion (around €580 million), changes in specification due to changed policies and adjustments as a result of the planning approval process (approximately €520 million) and additional construction work between Rastatt and Offenburg (about €100 million). €1.3 billion was spent on the completed section between Rastatt Süd and Offenburg.

In mid-September 2010, the financing agreement was signed for sections 9.2 and 9.3, with a total length of 8.5 km, for a total of almost €400 million (covering planning and construction costs).[98] According to the federal government, financing had also been secured for section 9.3 (Badischer Bahnhof). This was awaiting approval by the Swiss authorities in October 2011.[99]

Part of the project's finances came from a fund of around €1 billion that had been set aside to be invested from 2012 to 2015 for additions to the rail network. These funds, in turn, came in part from the dividend that has been paid by Deutsche Bahn to the Federal Government since 2011.[100]

In 2010, about €56 million was invested in the project; in 2011, about €94 million; in 2012, about €88 million; in 2013, about €69 million; and in 2014, about €74 million (preliminary estimate). In 2012 and 2013, the European Union contributed with a total of €33.7 million.[101] During the current funding period to 2015, the EU is likely to participate with almost €90 million in finance. This would correspond to about ten percent of project costs during this period. €350 million have been earmarked by 2020.[102]

External links

Notes and References

  1. Bericht über die Projektfortschritte beim Ausbau der grenzüberschreitenden Schienenverkehrsachsen – printed matter . 118/357 . 2 . Records of the Bundestag . 28 May 2015 . de. 25 April 2016.
  2. Deutschland-Karlsruhe: Technische Planungsleistungen für Verkehrsanlagen: 2016/S 017-026671 . 26 January 2016 . Tenders Electronic Daily . 6 May 2016. de.
  3. News: Grün-Rot gibt Bahn mehr Geld . . 142 . 24 June 2015 . 5 . de.
  4. Joachim Nied . Bernd Dassler . Thomas Ziege . Neu- und Ausbau der Strecke Karlsruhe – Basel – aktueller Planungsstand und Bauablauf . Eisenbahntechnische Rundschau . 56 . 9. 2007. 0013-2845 . 506–512 . de.
  5. Web site: Bürger feiern Bundestagsbeschluss zum Bahnausbau: Tunnelfinanzierung ist gesichert! . https://web.archive.org/web/20160204214418/http://www.offenburg.de/html/aktuell/aktuell_u.html?artikel=5878 . dead . 4 February 2016 . City of Offenburg . 28 January 2016 . de . 6 May 2016 .
  6. Book: Gruppe für Allgemeine Studien der Deutschen Bundesbahn . Schnellfahrstrecke für die Hauptverkehrsströme im Bundesbahn-Netz . 7. de. (study completed in September 1964)
  7. Paul Werner . Ausbau und Ergänzung des Streckennetzes der Deutschen Bundesbahn . Eisenbahntechnische Rundschau . 1. 1971 . 16–20 . de.
  8. Paul Werner . Die Aufgaben der Planungsabteilung im Rahmen der ZTL . Die Bundesbahn . 45 . 1971 . 19/20 . 0007-5876 . 987–994 . de.
  9. Jürgen Grübmeier . Georg Fischer . Die Ausbaustrecken der Deutschen Bundesbahn . Die Bundesbahn . 57 . 10 . 1981 . 0007-5876. 781–788 . de.
  10. Book: Werner Hagstotz . Betroffenheit und kollektives Handeln im ländlichen Raum . Verlag Haag+Herchen . Frankfurt am Main . 1981 . 3-88129-475-9 . 271 . de.
  11. Walter Vögele . Wolfgang Ruppelt . Siegfried Lorenz . Planung und Realisierung der Pilotstrecke für CIR-ELKE . Die Deutsche Bahn . 0007-5876 . 68 . 7 . 1992 . 763–767. de.
  12. NBS/ABS (Karlsruhe–)Rastatt–Offenburg–Basel . Die Bundesbahn . 12 . 1980 . 0007-5876 . 853 f . de.
  13. Bundesverkehrswegeplan 1980 mit höheren Bahn-Investitionen . Die Bundesbahn . 12 . 1979 . 859–862 . 0007-5876. de.
  14. Christian Woelker . Bundesverkehrswegeplan '80: Die Schiene holt auf . Wolfgang Vaerst . Peter Koch . Jahrbuch des Eisenbahnwesens. 31 . Hestra-Verlag . Darmstadt . 1980 . 0075-2479 . 3-7771-0160-5. 30–36 . de.
  15. Book: Projektgruppe NBS Karlsruhe der Bahnbauzentrale . Die Ausbau- und Neubaustrecke Karlsruhe–Basel . Leporello . Karlsruhe. 1987. de. (10 A4 pages)
  16. "Grünes Licht" für ersten Abschnitt des Streckenausbauprojekts Karlsruhe–Basel . Eisenbahntechnische Rundschau . 33 . 12 . December 1984 . 878 . de.
  17. Jürgen Grübmeier . Helmut Wegel . Bundesverkehrswegeplan 1985 . Eisenbahntechnische Rundschau . 1/2 . 1986 . 45–55 . 0013-2845 . de .
  18. Jahresrückblick 1988 . Die Bundesbahn . 1. 1989 . 63 . de .
  19. Ernst Krittian . Die Ausbau- und Neubaustrecke Karlsruhe–Base . Die Bundesbahn . 63 . 1987 . 10 . 0007-5876 . 911–916 . de.
  20. Wilhelm Linkerhägner . Bundesverkehrswegeplanung '85 . Die Bundesbahn . 0007-5876 . 66 . 10 . 1990 . 933–936 . de.
  21. Neubau- und Ausbaustrecken. Die Bundesbahn . 0007-5876 . 66. 1 . 1990 . 82–87 . de.
  22. Rüdiger Harmuth. ABS/NBS Karlsruhe–Basel. Die Bundesbahn . 69 . 1993 . 9–10 . 0007-5876 . 627–636 . de.
  23. Neu- und Ausbaustrecken – Investition in die Zukunft . DB Kundenbrief . 8 . 1986 . 122–124 . de.
  24. Book: Der Bundesminister für Verkehr . Bundesverkehrswegeplan 1985 - Stand der Realisierung . Anlage zum Sachstandsbericht Bundesverkehrswegeplan 1985 und Gesamtdeutscher Verkehrswegeplan . Bonn . 2 October 1990 . 41 . de.
  25. Bau der ABS/NBS Karlsruhe–Basel genehmigt . Eisenbahntechnische Rundschau . 36 . 1/2 . 1987 . 102 . de.
  26. Jahresrückblick 1988 . Die Bundesbahn . 65 . 1 . 1989 . 0007-5876 . 63 . de.
  27. Wilhelm Linkerhäger . Bundesverkehrswegeplanung '85 . Die Bundesbahn . 66 . 1990 . 10 . 0007-5876 . 933–936 . de.
  28. Book: Eugen Reinhard . Verkehr . 40 Jahre Baden-Württemberg. Aufbau und Gestaltung 1952–1992 . Konrad Theiss Verlag . Stuttgart. 1992 . 3-8062-1018-7 . 413–478 . de.
  29. Web site: Vereinbarung zwischen dem Vorsteher des Eidgenössischen Verkehrs- und Energiewirtschaftsdepartements1 und dem Bundesminister für Verkehr der Bundesrepublik Deutschland zur Sicherung der Leistungsfähigkeit des Zulaufes zur neuen Eisenbahn-Alpentransversale (NEAT) in der Schweiz . Swiss Government . de.
  30. Response by the Federal Government to the minor questions from deputies Winfried Hermann, Alexander Bonde, Kerstin Andreae and other members and the Alliance '90/The Greens parliamentary group—printed matter 17/933 . Parliament of Germany. Printed Matter . 17. 1306 . 6 April 2010 . de. 9 May 2016 .
  31. Ausbau-Probleme . Eisenbahn-Revue International . 4 . 1998 . 1421-2811 . 116 . de.
  32. Kein viergleisiger Ausbau am Oberrhein . Eisenbahn-Revue International . 10 . Year book . 1999 . 1421-2811 . 394 . de.
  33. Aktuelles in Kürze. Eisenbahn-Revue International . 8–9 . 2000 . 1421-2811 . 340 . de.
  34. Bypass Hochrhein. Eisenbahn-Revue International . 1. 2003 . 1421-2811. 32 f . de.
  35. Book: DB ProjektBau . Infrastrukturprojekte 2010. Bauen bei der Deutschen Bahn . Eurailpress-Verlag . Hamburg. 2010 . 978-3-7771-0414-0 . 50 f . de.
  36. Ministry for Transport and Infrastructure. Projektbeirat stimmt weiteren Schritten beim Ausbau der Rheintalbahn zu . 4 March 2013. 10 May 2015 . de.
  37. News: Kostenpoker um Rheintalbahn . Esslinger Zeitung . 24 June 2015 . 5 . de .
  38. News: Michael Petersen . Lärmschutz für alle an der Rheintalbahn . . 145 . 26 June 2015 . 10 May 2015 . de.
  39. News: Wolfgang Voigt . Durchbruch bei der Rheintalbahn . Badische Neueste Nachrichten . 27 June 2015 . de .
  40. Rainer Scheuermann . Richard Bitterling . Neubau-/Ausbaustrecke Karlsruhe–Base . Die Bundesbahn . 66 . 1990 . 8 . 0007-5876 . 793–800 . de.
  41. Erster Abschnitt der Neubaustrecke Karlsruhe–Basel fertig . Eisenbahntechnische Rundschau . 42 . 5 . 1993 . 361. de.
  42. Erster Abschnitt der Neubaustrecke Karlsruhe–Basel fertig . Die Deutsche Bahn. 4 . 1993. 347. de.
  43. Ausbau Karlsruhe – Basel . . 10. 2003. 1421-2811. 461. de.
  44. Rastatt – Offenburg vierspurig . Eisenbahn-Revue International . 1. 2005. 1421-2811. 28. de.
  45. DB Netz AG . Editorial . Karlsruhe–Basel Im Fokus . 2 . 2015 . 1 . 10 May 2016 . de . https://web.archive.org/web/20160305103042/http://www.karlsruhe-basel.de/Newsletter.html?file=files%2Fnewsletter%2FNewsletter_2_2015.pdf . 5 March 2016 . dead .
  46. News: Michael Baas . Ein Tunnel, der Maßstäbe setzt . . Lörrach regional. 5 July 2012 . 33 . de.
  47. Answer of the Federal Government to minor questions from deputies Matthias Gastel, Kerstin Andreae, Stephan Kühn (Dresden) and other members and the Alliance '90/The Greens parliamentary group—printed matter 18/4878. Parliament of Germany. Printed Matter . 18. 5037. 28 May 2015. 2–4 . de. 9 May 2016 .
  48. Deutschland-Frankfurt am Main: Bauarbeiten für Eisenbahnlinien, document 2013/S 238-413024 . 7 December 2013 . Tenders Electronic Daily . 10 May 2016. de.
  49. Answer of the Federal Government to minor questions from deputies Winfried Hermann, Alexander Bonde, Kerstin Andreae and other members and the Alliance '90/The Greens parliamentary group. Parliament of Germany. Printed Matter . 16. 5037. 16 April 2007. 2–4 . de. 10 May 2016 .
  50. DB Mobility Logistics. Ministerpräsident Mappus und DB-Chef Grube: "Investitionen in Bahn-Projekte stärken Infrastruktur in Baden-Württemberg". 18 October 2010 . de.
  51. Federal Ministry of Transport, Construction and Urban Development. Bund stellt Finanzmittel für den Rastatter Tunnel bereit. https://archive.today/20130111123014/http://www.bmvbs.de/SharedDocs/DE/Pressemitteilungen/2012/173-ramsauer-rastatter-tunnel.html. dead. 11 January 2013. 173/2012. 24 August 2012. de. 10 May 2016.
  52. https://karl.brodowsky.com/2016/06/16/neubaustrecke-karlsruhe-basel/ Neubaustrecke Karlsruhe–Basel (German)
  53. Die Deutsche Bahn muss im Rheintal neu planen . . 5 . 2013 . 228–229 . 1421-2811. de.
  54. DB ProjektBau GmbH . Schritt für Schritt voran . Karlsruhe–Basel Im Fokus . 2 . 2012 . 1 f . de . 10 May 2016 . dead . https://web.archive.org/web/20160305041008/http://www.karlsruhe-basel.de/Newsletter.html?file=files%2Fnewsletter%2FNewsletter_2_2012.pdf . 5 March 2016 .
  55. News: Michael Petersen . Mehr Geld für die Rheintalbahn . . 132 . 12 June 2015 . 6 . de . 10 May 2016.
  56. D-Karlsruhe: Bauarbeiten für Eisenbahnlinien: document 2011/S 67-109317 . 6 April 2011 . Tenders Electronic Daily . de.
  57. DB ProjektBau GmbH . Bahnchef bereist Rheintalbahn . Karlsruhe–Basel Im Fokus . 3 . 2010 . 1 f . de . 10 May 2016 . dead . https://web.archive.org/web/20160305122013/http://www.karlsruhe-basel.de/Newsletter.html?file=files%2Fnewsletter%2FNewsletter_3_2010.pdf . 5 March 2016 .
  58. News: Bernhard Walker . Für den Verkehrsminister ein "wichtiger Durchbruch" . . 55 . 6 March 2012 . de.
  59. Bernd Dassler . Joachim Nied . ABS/NBS Karlsruhe – Basel, Planung und Realisierung im Streckenabschnitt. Eisenbahntechnische Rundschau . 12. 2012 . 10–15. de.
  60. DB Netz AG . Stand der Planungen und Bauarbeiten . Karlsruhe–Basel Im Fokus . 1 . 2010 . 4 . 11 May 2016 . de . dead . https://web.archive.org/web/20141006073034/http://www.karlsruhe-basel.de/Newsletter.html?file=files%2Fnewsletter%2FNewsletter_1_2010.pdf . 6 October 2014 .
  61. Staatssekretärin Splett bei Rheintalbahn-Spatenstich in Rastatt . Baden-Württemberg Ministry for Transport and Infrastructure . 30 July 2013 . de.
  62. Johann Leonhäuser . Brücken für die ABS/NBS Karlsruhe–Basel im Abschnitt Karlsruhe–Offenburg . Die Bundesbahn . 66 . 5 . 1990 . 0007-5876 . 481–485 . de.
  63. Bernd Gruhn . Rolf Hamberger . Der Abschnitt Bühl–Offenburg der Ausbau- und Neubaustrecke Karlsruhe–Basel (ABS/NBS K/B). Die Bundesbahn. 68 . 1992. 10. 0007-5876. 1099–1102. de.
  64. Web site: DB ProjektBau . Ausbau- und Neubaustrecke Karlsruhe–Basel: Planfeststellungsabschnitt 7.1: Offenburg Süd–Hohberg . Karlsruhe . December 2008. de. (12 page brochure with state of December 2008)
  65. . Aus- und Neubau der Rheintalbahn: Erste Bewertung des Regierungspräsidiums Freiburg im Anhörungsverfahren für Offenburg: Antragstrasse der Bahn in der vorgelegten Form nicht genehmigungsfähig . 18 January 2011. de.
  66. Book: Zusammenfassung der Abwägungsentscheidung im Planfeststellungsabschnitt (PfA) 7.1 (Offenburg-Hohberg). Regierungspräsidiums Freiburg . 18 January 2011. de.
  67. DB ProjektBau GmbH . Stand der Planung im Streckenabschnitt 7.1 . Karlsruhe–Basel Im Fokus . 4 . 2012 . 5 . de . 12 May 2016 . dead . https://web.archive.org/web/20160305103112/http://www.karlsruhe-basel.de/Newsletter.html?file=files%2Fnewsletter%2FNewsletter_4_2012.pdf . 5 March 2016 .
  68. Deutschland-Frankfurt am Main: Dienstleistungen im Eisenbahnbau, document 2016/S 061-106060 . 26 March 2016 . Tenders Electronic Daily . 12 May 2016. de.
  69. Web site: DB ProjektBau. Ausbau- und Neubaustrecke Karlsruhe–Basel: Planfeststellungsabschnitt 7.2: Hohberg–Friesenheim . Karlsruhe . October 2006 . de. 12 May 2016. (12 page brochure with status of October 2006)
  70. Web site: DB ProjektBau. Ausbau- und Neubaustrecke Karlsruhe–Basel: Planfeststellungsabschnitt 7.3: Lahr–Mahlberg, Karlsruhe . December 2008. de. 12 May 2016. (12 page brochure with status of December 2008)
  71. Deutsche Bahn . Ausbau-und Neubaustrecke Karlsruhe – Basel: Planfeststellungsverfahren zwischen Lahr und Ettenheim beantragt . 12 July 2007. de.
  72. Web site: DB ProjektBau . Ausbau- und Neubaustrecke Karlsruhe–Basel: Planfeststellungsabschnitt 7.4: Ettenheim–Ringsheim–Herbolzheim . July 2006. de. 12 May 2016. (12 page brochure with status of July 2006)
  73. Web site: DB ProjektBau . Ausbau- und Neubaustrecke Karlsruhe–Basel: Planfeststellungsabschnitt 8.0: Herbolzheim–Riegel . March 2007. de. 12 May 2016. (12 page brochure with status of March 2007)
  74. Book: DB ProjektBau . Ausbau- und Neubaustrecke Karlsruhe–Basel: Planfeststellungsabschnitt 8.1: Riegel–March . October 2009. de. (12 page brochure with status of October 2009)
  75. Book: Martin Kastner . DB ProjektBau . Streckenabschnitt 8 – Umfahrung der Freiburger Bucht . Infrastrukturprojekte 2012: Bauen bei der Deutschen Bahn . Eurailpress . Hamburg . 2012 . 186–194 . 978-3-7771-0445-4 . de.
  76. DB ProjektBau GmbH . Matthias Hudaff im Interview . Karlsruhe–Basel Im Fokus . 2 . June 2014 . 3, 4 . de . 2020-02-13 . https://web.archive.org/web/20160305103132/http://www.karlsruhe-basel.de/Newsletter.html?file=files%2Fnewsletter%2FNewsletter_2_2014.pdf . 2016-03-05 . dead .
  77. Web site: DB ProjektBau . Ausbau- und Neubaustrecke Karlsruhe–Basel: Planfeststellungsabschnitt 8.2: Freiburg–Schallstadt . Karlsruhe . February 2010. de. (12 page brochure with state of February 2010)
  78. Web site: DB ProjektBau . Ausbau- und Neubaustrecke Karlsruhe–Basel: Planfeststellungsabschnitt 8.3: Bad Krozingen–Heitersheim . Karlsruhe . July 2006. de. (12-page brochure with state of July 2006)
  79. DB ProjektBau GmbH . Neuer Planfeststellungsabschnitt 8.4 . Karlsruhe–Basel Im Fokus . 4 . 2013 . 2 . de . 13 May 2016 . dead . https://web.archive.org/web/20151119035324/http://www.karlsruhe-basel.de/Newsletter.html?file=files%2Fnewsletter%2FNewsletter_4_2013.pdf . 19 November 2015 .
  80. Book: Heinz-Georg Haid . Albert Schmidt . Der Katzenbergtunnel – Historie, Planung und Bau . Der Katzenbergtunnel, Ausbau- und Neubaustrecke Karlsruhe–Basel . Eurailpress . 2012 . DB ProjektBau GmbH . 18–23 . 978-3-7771-0450-8 . Hamburg. de.
  81. Web site: DB ProjektBau . Ausbau- und Neubaustrecke Karlsruhe–Basel: Planfeststellungsabschnitt 9.0: Buggingen–Auggen . Karlsruhe . July 2005. de. (16 page brochure with state of July 2005)
  82. Hans-Peter Hecht . Friedrich Schaser . 'Ausbau- und Neubaustrecke Karlsruhe–Basel: Streckenabschnitt 9/Katzenbergtunnel . Eisenbahntechnische Rundschau. 55 . 2006 . 39–46 . de.
  83. Deutsche Bahn AG. 'Bahn und Bund investieren 200 Millionen Euro in den viergleisigen Ausbau der Rheintalbahn zwischen Müllheim und Auggen . 21 January 2013 . de.
  84. D-Karlsruhe: Planungsleistungen im Bauwesen: document 2013/S 101-173373 . 28 May 2013 . Tenders Electronic Daily . de.
  85. VGH: Viergleisiger Ausbau Karlsruhe – Basel zulässig . . 4. 2004 . 1421-2811 . 146 . de.
  86. Web site: DB ProjektBau . Ausbau- und Neubaustrecke Karlsruhe–Basel: Planfeststellungsabschnitt 9.2: Haltingen–Weil am Rhein . Karlsruhe . May 2006. de.
  87. Web site: Eisenbahn-Bundesamt, Außenstelle Karlsruhe/Stuttgart . Planfeststellungsbeschluss gemäß § 18 AEG für das Vorhaben Aus- und Neubaustrecke Karlsruhe – Basel Streckenabschnitt Haltingen – Weil am Rhein (Planfeststellungsabschnitt 9.2) . 1 February 2010 . https://web.archive.org/web/20160205061504/http://www.eba.bund.de/SharedDocs/Publikationen/DE/PF/Beschluesse/Baden_W/23_Rheintalbahn%209.2%20Haltingen%20-%20Weil%20am%20Rhein.pdf?__blob=publicationFile&v=1 . dead . 5 February 2016 . de . 13 May 2016 .
  88. Deutsche Bahn . Aus- und Neubaustrecke Karlsruhe - Basel: Planfeststellungsbeschluss für Haltingen - Weil am Rhein kann sofort umgesetzt werden . 11 February 2010 . de.
  89. Deutsche Bahn AG. Ausbau- und Neubaustrecke Karlsruhe-Basel; Wettbewerb zur Wiesequerung in Basel entschieden . 12 February 2014 . de.
  90. DB ProjektBau GmbH . Wettbewerb zur Wiesequerung in Basel entschieden . Karlsruhe–Basel Im Fokus . 1 . 2014 . 3 . de . 14 May 2016 . https://web.archive.org/web/20151119034926/http://www.karlsruhe-basel.de/Newsletter.html?file=files%2Fnewsletter%2FNewsletter_1_2014.pdf . 19 November 2015 . dead .
  91. DB ProjektBau GmbH . Hüter der Finanzen . Karlsruhe–Basel Im Fokus . 2 . 2012 . 5 . de . 13 May 2016 . dead . https://web.archive.org/web/20160305041008/http://www.karlsruhe-basel.de/Newsletter.html?file=files%2Fnewsletter%2FNewsletter_2_2012.pdf . 5 March 2016 .
  92. Response by the Federal Government to minor questions from deputies Kerstin Andreae, Dr. Valerie Wilms, Harald Ebner and other members and the Alliance '90/The Greens parliamentary group – printed matter 17/12007 . Parliament of Germany. Printed Matter . 17. 12007 . 22 January 2013 . de. 14 May 2016 .
  93. News: Investitionsbilanz 2006 der DB AG ' . Eurailpress . 2 January 2007 . 14 May 2016 . de . https://web.archive.org/web/20160205061523/http://www.eurailpress.de/news/wirtschaft-unternehmen/single-view/news/investitionsbilanz-2006-der-db-ag-1.html . 5 February 2016 . dead .
  94. Mehr Geld für Verkehrsprojekte . . 6. 2005 . 1421-2811 . 254 . de.
  95. Unterrichtung durch die Bundesregierung: Verkehrsinvestitionsbericht 2009. Parliament of Germany. Printed Matter . 17. 444 . 14 January 2010 . 29. de. 14 May 2016 .
  96. Unterrichtung durch die Bundesregierung: Verkehrsinvestitionsbericht für das Berichtsjahr 2010. Parliament of Germany. Printed Matter . 17. 8700 . 20 February 2010 . 99–102. de. 14 May 2016 .
  97. Parliament of Germany . Verkehrsinvestitionsbericht für das Berichtsjahr 2012 . Jahresbericht ... Des Nationalen Normenkontrollrates: Kostenbewusstsein Stärken - für eine Bessere Gesetzgebung . 18 . 580 . 18 February 2014 . 97–101 . 0722-8333 . de. 14 May 2016.
  98. Deutsche Bahn. 400 Millionen Euro für weiteren Aus- und Neubau der Bahnstrecke Karlsruhe–Basel . 15 September 2010 . de.
  99. Parliament of Germany . Response by the Federal Government to minor questions from deputies Uwe Beckmeyer, Sören Bartol, Bernhard Brinkmann (Hildesheim) and other members and the SPD—printed matter 17/7081 . Jahresbericht ... Des Nationalen Normenkontrollrates: Kostenbewusstsein Stärken - für eine Bessere Gesetzgebung . 17 . 7297 . 11 October 2011 . 5 . 0722-8333 . de. 14 May 2016.
  100. DB Mobility Logistics AG . DB begrüßt Zusage über zusätzliche Mittel für Ausbau der Schiene: Eine Milliarde extra bis 2015 . 16 March 2011. de. 14 May 2016.
  101. News: Konstantin Schwarz . EU gibt Geld für Stuttgart 21 und Strecke nach Ulm . . 16 . 21 January 2014 . 15 . de. 14 May 2016.
  102. News: Konstantin Schwarz . EU zahlt eine Milliarde für Bahnstrecke bis Ulm . . 161 . 16 July 2015 . 17 . de . 14 May 2016.