Kanakadurga Flyover Explained

Bridge Name:Kanakadurga Flyover
Native Name:కనకదుర్గ వారధి
Other Name:Durga Temple Flyover
Carries:6 lanes of road
Crosses:Krishna River, Prakasam Barrage
Locale:Vijayawada
Design:Beam bridge
Length:2.6km (01.6miles)
Width:23.7m (77.8feet)
Spans:47
Begin:22 November 2015
Complete:30 August 2020
Cost:₹458 Crores
Coordinates:16.5128°N 80.6039°W

The Kanakadurga Flyover (also known as Durga Temple Flyover) is a Flyover Spanning the Krishna River and Prakasam Barrage in Vijayawada, India. It is the Longest Flyover in Andhra Pradesh as of 2022 with a Length of . It was inaugurated on 16 October 2020 by Nitin Gadkari.[1]

Geography

The Kanakadurga Flyover is built around Indrakeeladri Hill on which Kanaka Durga Temple is located. It spans from Bhavanipuram near Gollapudi to PNBS. The road widening works are done up to Kanaka Durga Varadhi. This project has a total length of, of which are flyover and the remaining are road widening works. This flyover crosses Krishna River, Prakasam Barrage[2] and Buckingham Canal near Indrakeeladri hill,[3] and meets NH65[4] near PNBS.[5]

History

After Bifurcation a Flyover was Proposed by The Government of Andhra Pradesh to Control Traffic Flow Between the new State Capital Amaravati And the de facto Capital Hyderabad on the Existing 15-20 Foot Highway Around Durga temple.[6] The Construction of The Kanakadurga Flyover was Started by Soma Company of Hyderabad on 22 November 2015 and the Road Level Bridge was Completed by 2016 for Krishna Pushkaralu. The Flyover is very Difficult to Construct Due to its Plan and on The River Krishna. The Land Acquisition For this Project Cost Around 100 Crores for The shifting of Utilities like Drinking Water Pipelines along The Road. Later the Deadline was extended to March 2020, after having been previously extended in August 2017, March 2018, and August 2018. The Construction was Completed by 30th, August, 2020 .[7]

Construction

It is a six-lane highway with a width of 23.7 metres.[8] It is the third of its kind in India by using pre-stress technology. It is estimated to have cost 282.4 crores, which was later adjusted to 440 crores for inflation.[9] It has a unique and complex design with a six-lane corridor supported by a single pillar. There are two underpasses in the flyover master plan. Vertical gardening has been done on the column of this flyover along with a park for F1H2o to celebrate the 2018 F1H2o World Championship in Amaravati.[10] The district administration has decided to allow traffic through the flyover prior to its completion to prevent traffic bottlenecks and congestion.

See also

Notes and References

  1. Web site: At last, Kanaka Durga flyover opened in Vijayawada. 2020-10-18. The New Indian Express.
  2. News: Gateway project at riverfront set in motion. Staff Reporter. 2018-11-19. The Hindu. 2018-11-24. en-IN. 0971-751X.
  3. News: Private firm to maintain sanitation at Durga Ghat. The New Indian Express. 12 November 2018. 22 May 2019.
  4. News: Andhra Pradesh moving towards no-potholes roads - Times of India. The Times of India. 2018-11-24.
  5. News: Vijayawada: Alternative route for heavy vehicles to reduce city traffic. The New Indian Express. 2018-11-24.
  6. News: Motorists in for a dangerous ride on Durga flyover - Times of India. The Times of India. 2018-11-24.
  7. Web site: Durga temple flyover not before 2019: Govt. The Hans India. en. 2018-11-24.
  8. News: Kanakadurga flyover works drag on. 2018-10-27. Deccan Chronicle. 2018-11-24. en.
  9. News: Amazing Pics Of Kanaka Durga flyover. Gulte.com. 2018-11-24. en-us.
  10. News: First vertical organic garden coming up in Vijayawada. The New Indian Express. 2018-11-24.