Kaligandaki A Hydroelectric Power Station Explained

Kaligandaki A Dam
Name Official:Kaligandaki A Hydroelectric Power Station
Location Map:Nepal
Coordinates:27.9791°N 83.5805°W
Country:Nepal
Location:Mirmi, Syangja
Purpose:Power
Status:O
Construction Began:1997
Opening:2002
Cost:US$354.8 million (50 billion Nepali Rupees)
Owner:Nepal Electricity Authority
Dam Type:Concrete gravity
Dam Crosses:Gandaki River
Dam Height:44m (144feet)
Spillway Type:Radial gated
Res Capacity Total:7700000m2
Res Surface:7.618km2
Plant Name:Kaligandaki A Hydroelectric Power Station
Plant Coordinates:27.9309°N 83.6151°W
Plant Operator:Nepal Electricity Authority
Plant Commission:2002
Plant Type:R
Plant Hydraulic Head:115m (377feet)
Plant Capacity:144 MW
Plant Annual Gen:860 GWh

Kaligandaki A Hydroelectric Power Station is situated near Mirmi of Syangja District about 300 km to the west of Kathmandu and 100 km from Pokhara in the same direction in Nepal. The hydropower project is also the biggest hydropower project of Nepal. The dam and headworks are situated on the Gandaki River at the confluence of the Andhikhola whereas the power house is located downstream, around a bend in the river, in Beltari (About 7 km towards the South-East of Mirmi).[1] [2] A 5.9km (03.7miles) long headrace tunnel connects the reservoir to the power station which contains three 48 MW Francis turbine-generators. Owner and operator of the power plant is Nepal Electricity Authority.

It is a run-of-river type of project and currently is the largest power plant of any kind in Nepal with an installed capacity of 144 MW. Construction started in the year 1997 and was completed in the year 2002. The three turbine & generators Toshiba Make were commissioned in March, April and May 2002. It was constructed primarily to curb the ever increasing energy demand at that time and eliminate loadshedding prevalent due to the imbalance in demand and supply of energy. It was constructed with the financial aid of the Asian Development Bank with total costs reaching US$354.8 million (50 billion NPR (approx)).[3]

Hydrology and Sediments

The Kali Gandaki River originates in the high Himalayas carrying high sediment load. The river generates a suspended sediment load of 43 Mt/yr, of which around 25 per cent consists of sand. This sand has a high concentration of highly abrasive angular quartz. About 95 per cent of this suspended sediment load is delivered during the monsoon, between late May and late September and is large enough to completely fill the reservoir in a single monsoon season.

Data on discharge, suspended sand concentration in the river, and on the flow diverted into the turbines is shown in figure 3. The suspended sand concentration in the river and delivered to the turbines suddenly spikes in early June. This corresponds to the date that the reservoir level is lowered, thereby mobilising sand. The sand concentration drops again when the reservoir level is brought back up to its impounding level, reducing both the flow velocity through the reservoir and the rate of sand transport. This sluicing procedure has nearly stabilised reservoir capacity, producing a sediment balance across the reservoir. [4]

Transmission line

The power generated by the three turbines is evacuated to the central grid via a 132kV single circuit, a 66km (41miles) long transmission line to Pokhara, and a 44km (27miles) double circuit transmission line to Butwal. The electricity is sent to Lekhnath Municipality and Butwal (known as Butwal-1 and Butwal-2). A sub-station has been constructed in Lekhnath Municipality, Kaski district and the existing Jogikuti substation in Butwal has been upgraded.[5]

See also

Notes and References

  1. Web site: Nepal: Kali Gandaki "A" Hydroelectric Project. adb.org. 25 March 2014.
  2. Web site: Kali Gandaki 'A' Hydropower Station. erg.com.np. 25 March 2014. 25 March 2014. https://web.archive.org/web/20140325173838/http://www.erg.com.np/kali_hydropower.php. dead.
  3. Web site: April 2004. Project Completion Report on the Kali Gandaki "A" Hydroelectric Project (Loan 1452-Nep[Sf]) in Nepal ]. Asian Development Bank. 1 March 2015.
  4. Web site: International Hydropower Association. www.hydropower.org.
  5. Web site: Kali Gandaki 'A' Hydroelectric Project in Environmental Perspectives. aecen.org. 25 March 2014. 25 March 2014. https://web.archive.org/web/20140325174033/http://www.aecen.org/sites/default/files/nepal_eia_article_kaligandaki_hydroelectricinenviperspective.pdf. dead.