Kakrapar Atomic Power Station Explained

Kakrapar Atomic Power Station
Country:India
Coordinates:21.2386°N 73.35°W
Operator:Nuclear Power Corporation of India
Status:Operational
Construction Began:1984
Commissioned:6 May 1993
Np Reactors:4
Np Reactor Type:
Np Reactor Supplier:NPCIL/BARC
Ps Cooling Source:Ukai Dam, Tapti River
Ps Units Operational:2 × 220 MW
2 × 700 MW
Ps Electrical Capacity:1840
Ps Annual Generation:1354
Ps Electrical Cap Fac:38.25% (5 year global average of 2 older units)

Kakrapar Atomic Power Station is a nuclear power station in India, which lies in the proximity of Mandvi, Surat and Tapi river in the state of Gujarat.

Phase I

Phase I consist two 220 MW pressurised water reactor with heavy water as moderator (PHWR). KAPS-1 went critical on 3 September 1992 and began commercial electricity production a few months later on 6 May 1993. KAPS-2 went critical on 8 January 1995 and began commercial production on 1 September 1995. In January 2003, CANDU Owners Group (COG) declared KAPS as the best performing pressurised heavy water reactor.[1]

KAPS-2 was shut down after a coolant channel leak in July 2015 and a similar issue forced the shutdown of KAPS-1 in March 2016. After a replacement of coolant channels and feeder tubes, KAPS-2 attained criticality in September 2018. Maintenance on KAPS-1 was completed ahead of schedule and was brought to operation on 19 May 2019.

The construction costs were originally estimated to be ₹382.52 crore; the plant was finally finished at a price of ₹1,335 crore.

Phase II

In 2007 the First Manmohan Singh ministry approved outline plans to build two Indian-designed IPHWR-700 reactors, with two sister reactors a little later at Rajasthan Atomic Power Station. In 2009 approval was confirmed, and site preparation was completed by August 2010. The first concrete for Kakrapar 3 and 4 was in November 2010 and March 2011 respectively with operation originally expected by early and late 2018 respectively.[2] [3]

The project over-ran largely due to tuning of the IPHWR-700 design and slow delivery of supplies.[2]

Unit 3 achieved the first criticality on 22 July 2020. It was connected to the grid on 10 January 2021.[4] This unit began commercial operation on 30 June 2023.[5] Unit 3 achieved operations at full load on 31 August 2023.[6]

Unit 4 commissioning is under progress. Hot functional testing was scheduled around June 2023 and criticality was initially planned around September 2023. The Initial Fuel Loading (IFL) commenced on 20 October 2023 after permission was granted by the Atomic Energy Regulatory Board.[7] Unit 4 achieved first criticality on 17 December 2023.[8] The reactor was connected to the grid on 20 February 2024.[9] Unit 4 started commercial operation from 31 March, 2024.[10]

Units

PhaseUnit
No.
ReactorStatusCapacity in MWeConstruction startFirst criticalityGrid ConnectionCommercial operationClosureNotes
Type Model Net Gross
I 1 202 220 1 December 1984 3 September 1992 24 November 1992 6 May 1993 [11]
2 202 220 1 April 1985 8 January 1995 4 March 1995 1 September 1995 [12]
II 3 630 700 22 November 2010 22 July 2020 10 January 2021 30 June 2023 [13]
4 630 700 22 November 2010 17 December 2023 20 February 2024 31 March 2024 [14]

Incidents

See also

External links

Notes and References

  1. News: Kurian. Vinson. Indian N-reactors set new global benchmark. The Hindu Business Line. 26 March 2003. 16 February 2017.
  2. News: Bright prospects for India's future fleet . Nuclear Engineering International . 16 August 2017 . 23 July 2020.
  3. News: Kakrapar 3 achieves first criticality . World Nuclear News . 22 July 2020 . 23 July 2020.
  4. Web site: Unit 3 of Kakrapar nuclear plant synchronised to grid. Live Mint. 10 January 2021. 18 January 2021.
  5. News: 2023-07-04 . India's Kakrapar 3 begins commercial operation . World Nuclear News . 2023-07-25.
  6. News: Gujarat: 'India Achieves Another Milestone' As First Indigenous 700 MW Nuclear Plant Starts Operations At 100%. Free Press Journal. 2023-08-31.
  7. News: 2023-10-21 . NPCIL starts loading fuel in home-built 700 MW n-power plant at Kakrapar. ET EnergyWorld . 2023-10-21.
  8. News: 2023-12-17. Kakrapar-4 nuclear reactor attains criticality. The Hindu. 2023-12-17.
  9. Web site: Kakrapar-4 Reactor Connected To Grid As Nation Pushes For Major Expansion Of Nuclear Power. Kamen. Kraev. NucNews. 2024-02-24.
  10. Web site: MAJOR ACHIEVEMENTS OF NPCIL IN MARCH 2024. NPCIL. 2024-04-16.
  11. Web site: Nuclear Power Reactor Details - KAKRAPAR-1 . 23 Nov 2010 . Power Reactor Information System . International Atomic Energy Agency (IAEA) . 2010-11-23 .
  12. Web site: Nuclear Power Reactor Details - KAKRAPAR-2 . 23 Nov 2010 . PRIS . (IAEA) . 2010-11-23 .
  13. News: 2023-06-30 . India's first domestically built 700 MW nuclear reactor starts commercial operations in Gujarat . The Economic Times . 2023-06-30 . 0013-0389.
  14. News: Varadhan . Sudarshan . 31 May 2022 . KAPS 4 attains criticality . en . Pib .
  15. Web site: Shutdown of Unit-1 of KAPS Nuclear Power Plant following an incident leakage from Coolant System . . S. . Harikumar . 2016-03-11 . 2017-02-16.
  16. News: More than 100 hours later, Kakrapar nuclear leak not fixed. 16 March 2016. 18 April 2016. Rediff.com.
  17. News: Kakrapar Nuclear Reactors to Get New Coolant Channels . News18 . Indo-Asian News Service . 1 February 2017.
  18. News: Fernandes . Snehal . A year after KAPS-1 heavy water leak, corrosion spots found: AERB . Hindustan Times . 19 March 2017 . en.
  19. News: Balan . Premal . Ahmedabad: No power from Kakrapar plant for at least a year . The Times of India . 11 March 2017.
  20. Web site: KAPS-1 connected to grid. NPCIL. 24 May 2019.