Kaiwera Downs Wind Farm Explained

Kaiwera Downs Wind Farm
Country:New Zealand
Location:Gore
Coordinates:-46.2414°N 169.0558°W
Cost:115m (stage 1)
Owner:Mercury Energy
Wind Farm Type:Onshore
Wind Hub Height:77m
Wind Rotor Diameter:136m
Ps Site Elevation:400m – 460m
Ps Units Operational:10 x 4.3MW
Ps Units Manu Model:V136-4.2 MW in 4.3 MW operating mode
Ps Units Planned:155 MW
Ps Annual Generation:148 GWh (Stage 1)
Construction Began:October 2022
Commissioned:November 2023

The Kaiwera Downs Wind Farm is a wind farm in the Southland region of New Zealand. It is consented to have a maximum capacity of 240MW and use up to 83 turbines.[1] Originally proposed by Trustpower, it is now owned and operated by Mercury Energy. The 10 turbine, 43MW stage 1 of the project was opened in November 2023.[2]

The New Zealand Ministry for Culture and Heritage gives a translation of "hot food" for Kaiwera.[3]

Location and Resource

The wind farm is located about 15 kilometres south-east of Gore, within an area of 2568ha.[4] Access to the site from the port at Bluff is "considered excellent".

The prevailing south-west/ westerly winds blow with an average wind speed of 8.7 – 8.9 m/s.

Construction

The project received resource consent in June 2008.[5] In September 2018 Tilt said that the development was waiting for favourable market conditions.[6] In June 2021 Tilt announced the project was being acquired by Mercury Energy.[7] In June 2022 Mercury began talks with the local community over the wind farm.[8]

Stage 1

Installation of an initial ten turbines totalling 43MW of generation is expected to start in October 2022.[9] [10] [11] Earthworks began in the first week of October 2022.[12] A sod-turning ceremony was held in November 2022.[13] As of February 2023, Mercury say they expect all turbines to be operational by October 2023.[14] The first turbines arrived in April 2023, and were transported to the site during May and June.[15] As of July 2023, two of ten turbines had been erected, and the wind farm was expected to be complete by October.[16] As of mid October 8 of 10 turbines are operational and stage 1 of the project is on track to be completed by the end of October. The wind farm was officially opened on 20 November.[2] [17]

Stage 2

Mercury is building stage 2 of the project starting in June 2024 with first generation coming on stream by mid-2026 and completion by mid-2027. They are building an additional 155MW of capacity. [18] In June 2023 they received approval to amend their resource consent.[19] This change reduces the total number of turbines for the project from 83 to 66 but allows the remaining turbines to be built with an additional 20 meters of height, a maximum blade tip height of 165m. Mercury say this will help reduce stress on the blades and increase their lifespan.

Construction of stage 2 began in July 2024.[20]

Transmission

Power from Stage 1 is exported via a new 18km (11miles) 33,000-volt line to Transpower's Gore substation.[21]

Power from Stage 2 will be exported via a short new 220Kv transmission line connecting to Transpower’s North Makarewa to Three Mile Hill Line.[22]

See also

External links

Notes and References

  1. Web site: Wind farm carbon savings 'could be worth 25m' . The Southland Times . Sonia Gerken . 2008-04-04 . 2008-09-24.
  2. Web site: Mercury opens Kaiwera Downs wind farm near Gore . Stuff . 21 November 2023 . 21 November 2023.
  3. Web site: 1000 Māori place names. New Zealand Ministry for Culture and Heritage. 6 August 2019.
  4. Web site: Kaiwera Downs Wind Farm. Tilt Renewables. 24 June 2018.
  5. Web site: Appeals lodged against wind farm . Otago Daily Times . Glenn Conway . 2008-07-05 . 2008-09-24.
  6. Web site: Kaiwera Downs wind farm still on the horizon . Rachael Kelly . Stuff . 26 September 2018 . 17 June 2021.
  7. Web site: Kaiwera Downs windfarm project still viable in Southland . Stuff . Rachael Kelly . 11 June 2021 . 17 June 2021.
  8. Web site: Talks ramp up around Kaiwera Downs wind farm near Gore . Logan Savory . Stuff . 22 June 2022 . 27 June 2022.
  9. Web site: Construction on new wind farm near Gore will begin in October . Stuff . Geraden Cann . 13 September 2022 . 13 September 2022.
  10. Web site: Wind farm 'something we will have to learn to live with' . Otago Daily Times . 14 September 2022. 14 September 2022.
  11. Web site: Mercury NZ commits to $115m wind farm near Gore . New Zealand Herald . 14 September 2022.
  12. Web site: Earthworks begin at Mercury Energy's $115m Kaiwera wind farm . Stuff . Rachael Kelly . 4 October 2022 . 20 October 2022.
  13. Web site: Southland has an exciting future in wind generation . Stuff . Rachael Kelly . 3 November 2022 . 3 November 2022.
  14. Web site: 2023 Interim Report by Mercury - Issuu . 2023-02-23 . issuu.com . 21 February 2023 . en.
  15. Web site: Big job transporting turbine parts to Kaiwera Downs . Stuff . 2 May 2023 . 4 May 2023.
  16. Web site: Two turbines up, eight to go at Mercury's new wind farm . Stuff . Rachael Kelly . 19 July 2023 . 20 July 2023.
  17. Web site: Mercury Energy champions renewable growth as it switches on Kaiwera Downs wind farm . New Zealand Herald . 21 November 2023 . 22 November 2023.
  18. Web site: NZX, New Zealand's Exchange . 2024-06-06 . www.nzx.com.
  19. Web site: Kelly . Rachael . 2023-08-21 . More turbines a possibility for Kaiwera Downs wind farm . 2023-10-15 . Stuff . en.
  20. Web site: Expansion of Mercury’s Kaiwera Downs wind farm launched . Stuff . Rachael Kelly . 26 July 2024 . 26 July 2024.
  21. Book: Kaiwera Downs Wind Farm Newsletter February 2023.
  22. Web site: 18 July 2023 . Gore District Council Consent Variation Decision for Kaiwera Downs Wind Farm . https://web.archive.org/web/20240510101454/https://www.goredc.govt.nz/repository/libraries/id:2buwl3j7c17q9srz9ase/hierarchy/Properties/Documents/Planning%20%26%20Resource%20Consents/2023%20Planning%20Consent%20Decisions/July%202023/2023-07%20Kaiwera%20Downs%20Wind%20Farm%20Variation.pdf#expand . 2024-05-10.