Jinping-II Dam | |
Name Official: | Jinping-II Hydropower Station |
Dam Crosses: | Yalong River |
Location: | Yanyuan County and Muli Tibetan Autonomous County, Sichuan, China |
Dam Length: | 162m (531feet) |
Dam Height: | 37m (121feet) |
Construction Began: | 2007 |
Opening: | 2014 |
Status: | O |
Purpose: | Power |
Owner: | Yalong River Hydropower Development Company, Ltd. |
Operator: | MWREP |
Res Name: | Jinping-II Reservoir |
Res Capacity Total: | 14280000m2 |
Res Capacity Active: | 5020000m2 |
Res Catchment: | 102663km2 |
Plant Turbines: | 8 × 600 MW Francis-type |
Plant Capacity: | 4,800 MW |
Plant Hydraulic Head: | 310m (1,020feet) |
Plant Commission: | 2012–2014 |
Location Map: | China Sichuan#China |
Coordinates: | 28.2483°N 101.6444°W |
Plant Name: | Jinping-II Hydropower Station |
Plant Coordinates: | 28.1381°N 101.792°W |
The Jinping-II Dam, also known as the Jinping-II Hydropower Station, is a gravity dam on the Jinping Bend of the Yalong River (Yalong Jiang) in Sichuan, China. Construction on the project began in 2007 and it was complete in 2014. Its hydroelectric power station has a 4,800 MW installed capacity.
While Jinping-I relies on a conventional tall dam and large reservoir to supply water, Jinping-II uses a much smaller dam, located 7.5 km downstream of Jinping-I, to divert water into four 16.6 km long headrace tunnels. These tunnels connect to a downstream point on the same river at a much lower elevation, providing a 310m (1,020feet) head of water[1] without flooding a large area of land.
Harnessing hydropower on the Jinping Bend of the Yalong River has been in planning for decades. The river makes a hairpin bend 150 km long around the Jinping Mountains, but the downstream part of the river on the opposite side of the mountain is separated by only 16 km. In that distance, there is an elevation drop of 310 m, creating an excellent situation for hydroelectricity production. Two projects were planned for the bend, the Jinping I and Jinping II with a combined capacity of 8,400 MW. Planning for the projects began in the 1960s under the former Sichuan and Shanghai design institutes along with the Ministry of Water Resources and Electric Power. They produced the "Reinvestigation Report on The Yalong River bend (Jinping)". In July 1965, the Jinping Hydropower Engineering Headquarters was set up and designs for the Jinping 1 and Jinping 2 would progress with the East China Investigation and Design Institute .[2]
Construction on the Jinping-II started on January 30, 2007.[3] The dam's first generator was commissioned in December 2012, the second in January 2013.[4] The fifth generator went online in May 2014 and the seventh in October 2014.[5] [6] Jinping-I was fully commissioned by July 2014 and the eighth and final generator for Jinping-II was commissioned on 26 November 2014.[7]
A 37 m tall, 162 m long sluice dam on the west-side of the Jinping bend diverts water into four 16.6 km long headrace tunnels towards the power station. At the power station, the water turns eight 600 MW Francis turbines with a total capacity of 4800 MW before being discharged back into the river.
About 30% of the power from the Jinping dams is used locally, and 70% will be sent to eastern China via ±800 kV bipolar HVDC transmission lines.
In addition to the four headrace tunnels, two roadway tunnels (A and B) were constructed with a diameter of, and a drainage tunnel in diameter. These were all constructed by drilling and blasting, as were headrace tunnels #2 and #4, with a diameter of . Headrace tunnels #1 and #3, with a diameter of, were excavated by tunnel boring machine.[8]