Jamshoro Power Station Explained

Jamshoro Thermal Power Station
Name Official:TPS Jamshoro
Location Map Caption:Location of Jamshoro Power Station in Pakistan
Coordinates:25.4722°N 68.2661°W
Country:Pakistan
Status:O
Commissioned:Unit 1: January 1990
Unit 2: December 1989
Unit 3: June 1990
Unit 4: January 1991
Unit 5: 2023 (projected)
Unit 6: 2029 (projected)
Cost:Unit 5-6: US$1.5 billion
Owner:Government of Pakistan
Operator:WAPDA
Th Fuel Primary:Unit 1: Furnace Oil
Unit 2-4: Gas/Furnace Oil
Unit 5-6: Coal
Ps Cooling Source:Indus River
Ps Units Operational:1 x 250 MW
3 x 210 MW[1]
Ps Units Manu Model:Unit 1: Mitsui Engineering & Shipbuilding
Unit 2-4: Harbin
Unit 5-6: Siemens-Harbin JV
Ps Units Uc:2 x 660 MW
Ps Electrical Capacity:880 MW (operational)
2,200 MW (planned)

Jamshoro Thermal Power Station also known by other names such as GENCO-I, and TPS Jamshoro is a gas / furnace oil and coal based thermal power plant with a total installed capacity of 880 MW located in Jamshoro near Hyderabad, Sindh in Pakistan. It is operated by the Jamshoro Power Company. The first phase of the project was commissioned between 1989 and 1991. It consists of one 250 MW unit and three 210 MW units.[2] [3] The power station is undergoing a planned expansion with additional 2 x 660 MW coal fired units. One 660 MW unit has been constructed and is ready for commissioning. Site preparation of second 660 MW unit is in progress with an expected commissioning date of July 2029.[4]

In February 2014, the Asian Development Bank agreed to loan $900m to the government of Pakistan for a project to install 2 x 660MW supercritical coal-fired power plant at Jamshoro.[5] The Islamic Development Bank (IDB) approved $220m for the Jamshoro Coal Power generation project. The Asian Development Bank had already approved $900m for the project, whereas $380m was to be contributed by the government to meet the overall estimated project cost of $1.5 billion.

The new 2 x 660 MW units will be supercritical coal-fired power plants. Unit 5 of 660 MW will be using an 80/20 blend of imported sub-bituminous coal (80%) and domestic lignite (20%) from Thar coalfield. Unit 6 will be based on 100% domestic lignite.[6]

See also

External links

Notes and References

  1. Web site: State of Industry Report 2022 . 2023-07-26 . nepra.org.pk.
  2. Web site: State of Industry Report 2022 . 2023-07-26 . nepra.org.pk.
  3. Web site: Oil- and Gas-Fired Plants in Pakistan . Power Plants Around The World . 10 July 2013 . 19 March 2014 . dead . http://arquivo.pt/wayback/20090718093535/http://www.industcards.com/st-other-pakistan.htm . 18 July 2009 .
    - Web site: WAPDA Jamshoro Thermal Power Station . Global Energy Observatory . 23 March 2014 . 19 March 2014 . https://web.archive.org/web/20140319175534/http://globalenergyobservatory.org/form.php?pid=3722 . dead .
  4. Web site: Jamshoro power station . 2023-07-03 . Global Energy Monitor . en.
  5. Web site: ADB Provides $900 Million for Jamshoro Power Project . Asian Development Bank . 12 February 2014 . 19 March 2014 . dead . https://web.archive.org/web/20140319134114/http://www.adb.org/news/pakistan/adb-provides-900-million-jamshoro-power-project . 19 March 2014 .
  6. Web site: adbheadhoncho . 2013-12-09 . Jamshoro Power Generation Project . 2023-07-03 . Asian Development Bank . en.