Isinya–Singida High Voltage Power Line Explained

Isinya–Singida High Voltage Power Line
Country:Kenya and Tanzania
Coordinates:-1.995°N 36.8°W
Direction:North to South
Start:Isinya, Kenya
Finish:Singida, Tanzania
Owner:Government of Kenya & Government of Tanzania
Partners:African Development Bank
Operator:Kenya Electricity Transmission Company & Tanzania Electric Supply Company
Contractors:North China Power Engineering Company Limited
Expected:2024
Current Type:AC
Length Mi:315.5
Ac Voltage:400kV
Circuits No:2

The Isinya–Singida High Voltage Power Line is a high voltage electricity power line, under construction, connecting the high voltage substation at Isinya, Kenya to another high voltage substation at Singida, Tanzania.[1]

Location

The power line starts at Isinya, in Kajiado County, about 58km (36miles) south of Nairobi, and runs in a southerly direction for approximately 109km (68miles) to the border with Tanzania at Namanga.

At Namanga the power line crosses into Tanzania and follows a southerly direction to Arusha, a distance of about 110km (70miles) from Namanga. From Arusha the line travels in a south-westerly direction for about 325km (202miles) to end at Singida. According to the African Development Bank, 93.1km (57.8miles) of the line are located in Kenya and 414.5km (257.6miles) are located in Tanzania, for total length of 507.6km (315.4miles).

Overview

As far back as 2015, Kenya, Tanzania and Zambia began to explore the amount of electricity that can be moved along high voltage power lines linking the three countries. The objective was to exchange electricity between the Eastern Africa Power Pool to which both Kenya and Tanzania belong, and the Southern African Power Pool to which Tanzania ad Zambia belong. Each country would build and maintain the infrastructure within its borders.[2] Kenya and Tanzania sought a joint consultant to advise on the project.[3] A joint Environmental and Social Impact Assessment (ESIA) in both countries was carried out in 2014, funded by the African Development Bank (AfDB).

Construction in Kenya

In October 2017, Ketraco, the Kenyan electricity transportation monopoly awarded the construction contract for a 400kV substation at Isinya and the 96km (60miles) 400kV high tension line from Isinya to Namanga, to North China Power Engineering Company Limited (NCPE).[4] The work will be jointly financed by Kenyan government at US$4.25 million and the AfDB which will offer US$22.42 million in loans. Construction was expected to take 22 months.

In 2023, the development was met with construction delays related to compensation of landowners and lack of sufficient capital to do so.[5] In January 2024, Business Daily Africa reported that completion of construction was expected in 2024.[6] In March 2024, The EastAfrican reported that construction was completed but testing and calibration was ongoing with test completion planned for the end of April 2024.[7]

Construction in Tanzania

The work in Tanzania involves the construction of approximately 415km (258miles) of double circuit high tension power lines, from Namanga, through Arusha to Singida, a 400kV substation in Arusha and another 400kV substation in Singida. The work is budgeted at US$258.82 million.[8]

The section between Singida and Babati was contracted to Kalpataru Power Transmission Limited of India. The Babati to Arusha section was contracted to Bouygues Energies & Services of France. Kenya is expected to establish a 400kV connection to Ethiopia, while Tanzania is expected to establish a similar 400kV connection to Zambia. This will enable seamless power sales between the four countries.[9]

Other considerations

In May 2024, as Kenya and Tanzania were hurrying to complete this power transmission line, the EastAfrican reported that the 400kV transmission line between Tanzania and Zambia is under construction and is scheduled for completion in November 2025. At that time Eastern Africa Power Pool countries will be able to trade power with the countries of the Southern Africa Power Pool.[10]

See also

External links

-1.995°N 36.8°W

Notes and References

  1. Web site: Multinational Kenya–Tanzania Power Interconnection Project: Country : Kenya and Tanzania: Project Number : P-Z1- FA0-052 . July 2014 . 19 October 2016 . . Asfaw S; Kulemeka N . etal . Abidjan, Ivory Coast.
  2. Web site: . Reuters . Zambia, Tanzania, Kenya to assess power output on high-voltage power line . https://web.archive.org/web/20190403145918/https://af.reuters.com/article/topNews/idAFKCN0SD1Q020151019 . dead . 3 April 2019 . 19 October 2015 . 19 October 2016 . New York City.
  3. Web site: Kenya, Tanzania seek consultant for cross-border power lines . . Nairobi . 19 October 2016 . 9 February 2015.
  4. Web site: 18 October 2016 . Chinese firm to build KSh2.6 billion power line to Tanzania . 19 October 2016 . Neville . Otuki . Nairobi . Business Daily Africa.
  5. Web site: Completion of Kenya-Tanzania Power Interconnection Project to delay . Pumps-Africa . 5 April 2023 . Anita Anyango . 31 January 2024 . Nairobi, Kenya.
  6. Web site: . AfDB wants Kenya, Dar electricity deals finalised . John Mutua . 31 January 2024 . 31 January 2024 . Nairobi, Kenya.
  7. Web site: . 25 March 2024 . Kenya misses target to commission over 500km power line to Tanzania . 25 March 2024 . Nairobi, Kenya.
  8. Web site: 19 October 2016 . Work on Kenya-Tanzania powerline set to begin . Nairobi . . 18 October 2016 . Anyanzwa . James.
  9. Web site: Tanzania-Kenya joint power project kicks into high gear . 9 February 2019 . . Bob Karashani . 11 February 2019 . Nairobi, Kenya.
  10. Web site: 1 May 2024 . Power line linking Kenya to southern Africa set for 2025 . . Brian Ambani . 1 May 2024 . Nairobi, Kenya.