IC3 Convention Center explained

IEC Convention Center of Cebu [1]
Former Names:International Eucharistic Congress Pavilion
Alternate Names:IC3 Convention Center
Status:Complete
Building Type:Convention center
Location:23 Minore Park, Pope John Paul II Avenue corner Cardinal Rosales Avenue, Brgy. Luz, Cebu City, Philippines[2]
Owner:Archdiocese of Cebu
Coordinates:10.3217°N 123.9083°W
Start Date:2014
Completion Date:2015
Renovation Date:2016
Floor Count:2
Grounds Area:2.5ha
Main Contractor:Duros Development Corporation
Architect:Carlos Pio Zafra
Seating Capacity:10,000 (2017)
Parking:225 slots (2017)
References:[3]

The IEC Convention Center of Cebu or the IC3 Convention Center (formerly the International Eucharistic Congress Pavilion) is a convention center within the grounds of the 23 Minore Park development along Pope John Paul II Avenue in Barangay Luz, Cebu City, Philippines.[4] [2] The convention center was built in order to host the 2016 International Eucharistic Congress held in the city.

The facility is owned by the Archdiocese of Cebu and is managed by Regent Property International.

History

Background and prior plans

With Cebu City due to host the International Eucharistic Congress (IEC) in 2016, the Archdiocese of Cebu sought a venue for the congress.

It was planned that a venue would be built out of the unfinished shell of a privately owned commercial building behind ParkMall in Mandaue which is also near to the Cebu International Convention Center. However, such plans were scrapped in favor of building a venue within the seminary compound of the Archdiocese so that the facility, which will be used for other events of the local church after the IEC, will be more accessible to the archdiocese's constituents.[5]

Construction

The groundbreaking for the IEC Pavilion was done on February 15, 2014,[6] which was attended by Archdiocese of Cebu officials as well as local government officials.[5] Construction commenced in July 2014[7] and the building was topped off on July 15, 2015.[4]

The secretariat building is 95 percent complete while the plenary hall is 69 percent done by July 2015. Overall the facility is 82.8 percent done with September 2015 as the target month of completion by this time.[4]

By November 2015, the structure was 97 percent complete with structural and architectural aspects already complete and only finishing works to be done.[7]

The IEC Pavilion's construction costed around .

Turnover

Duros Development Corporation, the contractors of the IEC Pavilion, turned over the facility to the Archdiocese of Cebu on November 21, 2015. The following day, on November 22, 2015, which also happens to be the Feast of Christ the King, the IEC Pavilion was opened to the public. The facility was consecrated to Christ the King in a ceremony attended by 7,000 people.[8]

Turnover and inauguration

In October 2016, Regent Property International a firm linked to Duros Construction Inc. formally took over the management of the venue.[9]

The former IEC Pavilion was redeveloped into a full-fledged convention center. On December 15, 2016, Duros Land inaugurated the venue as the "IEC Convention Center of Cebu" or the "IC3 Convention Center"[10] The St. John XXII Minore Seminary where the convention center stood was made into a development by Duros Land known as the 23 Minore Park.[11] The redevelopment of the seminary which was completed by December 2016 into the 23 Minore Park took about six months.[10]

The Archdiocese of Cebu the owners of the property has allowed Duros Land on handling the venue's operation for the next 25 years.[1]

Events

The IC3 Convention Center was built as the IEC Pavilion, meant as the primary venue of the 2016 International Eucharistic Congress.

After the congress, the center has hosted many religious activities organized mainly by its owner, the Archdiocese of Cebu. On May 18, 2017, ALA Boxing Promotions announced that the center will host Pinoy Pride 41, a boxing event headlined by Thai boxer Komgrich Nantapech and Donnie Nietes.[12]

Other use

During the COVID-19 pandemic a 130-bed capacity quarantine facility for mild and moderate COVID-19 patients was set up in the convention center.[13]

Architecture and design

The IC3 Convention Center was constructed by property developer, Duros Development Corporation which also financed the project for usufructuary rights for 25 years over the facility.[14] Among the people involved in the construction of the project is architect Carlos Pio Zafra and project-in-charge Engineer Adonis Gabutin.[14] [7] [15] Rizal Camangyan Jr. is also reported to be involved as a construction manager.[7]

During the groundbreaking ceremony of the IC3 Convention Center as the IEC Pavilion, IEC secretary Msgr. Dennis Villarojo explains that the structure is dubbed as a "Pavilion" because the venue would not be convention center with high-end amenities. He described the would-be structure as "simple" and would provide delegates of the congress in 2016 "a comfortable and decent venue". He insists that the IEC Pavilion would not be a high-end facility describing the then to be built venue as "a roofed structure with walls, floors and will be air-conditioned,[16]

Zafra, the architect of the IEC Pavilion said he was instructed that the design of the building is to be "simple". Camangyan noted that Cebu Auxiliary Bishop Dennis Villarojo called for "low maintenance building" specifying that there would be no finishes to be done on the floor so that it can be cleaned using a mop.[7] Likewise the walls and ceiling were bare and unadorned. The facility was also to be designed to be earthquake-resistant withstanding strong earthquakes such as the magnitude 7.2 Bohol-Cebu earthquake of 2013.[16]

Facilities

As the IEC Pavilion, the venue had a plenary hall, a secretariat building, a chapel, a media center, and holding rooms for bishops and priests. The pavilion had three levels[16]

As the IC3 Convention Center, the venue has 10,000 seating capacity. The IC3 has three convention halls and a function room. Hall A has a capacity of 3,000 people, Hall B can accommodate 5,000 people, and Hall C can seat 2,000 people.[9]

The second level of the convention center which can be used for wedding events and medium-scale conferences can seat about 500 people.[1] The facility also hosts a holding room for performers and breakout rooms for small-scale gatherings. The grand hallway of the convention center is dubbed as the Ganghaan Walk where photos of the 2016 International Eucharistic Congress are exhibited.[17]

For the facility's parking space, there are 255 slots available.[17]

Notes and References

  1. News: Galolo . Jeandie . IEC Convention Center of Cebu seats 10,000 . . December 15, 2016 . May 18, 2017 .
  2. Web site: Contact Us! . ic3.com.ph . August 30, 2020.
  3. News: Mondoñero. Laureen. LOOK: What's inside the IEC Pavilion. February 2, 2016. Sun Star Cebu. November 20, 2015.
  4. News: Quintas. Kristine. IEC Pavilion done by September. February 2, 2016. The Freeman. July 16, 2015.
  5. News: Mayol. Ador Vincent. Groundbreaking held for P380-M Eucharistic Pavilion. February 2, 2016. Cebu Daily News. February 16, 2014.
  6. News: IEC Pavilion Groundbreaking. 2 February 2016. Dulos Land Properties. 2014. https://web.archive.org/web/20160207150950/http://www.durosland.com/iec-pavillon-groundbreaking/. February 7, 2016. dead.
  7. News: Mondoñero. Laureen. IEC Pavilion now 97% complete. February 2, 2016. Sun Star. November 19, 2015.
  8. News: EC Pavilion consecrated to Christ the King. https://web.archive.org/web/20170510071146/http://www.cbcpnews.com/cbcpnews/?p=68303. usurped. May 10, 2017. 2 February 2016. CBCP News. 23 November 2015.
  9. News: Vestil. Justin. IEC ‘has left lasting legacy for Cebuanos’. May 19, 2017. Sun Star Cebu. January 22, 2017.
  10. News: 23 Minore Park opens, unveils IC3 . Cebu Daily News . February 7, 2017 . May 18, 2017 .
  11. News: Villaester . Maurice Jitty . Duros Land launches 23 Minore Park . Cebu Daily News . December 14, 2016 . May 18, 2017 .
  12. Web site: New Cebu City venue for Pinoy Pride 41 . fightnews.com . May 18, 2017 . May 18, 2017 .
  13. News: Abatayo . Rosalie . Bayanihan Cebu opens COVID-19 center in IC3 . June 12, 2020 . Cebu Daily News . May 26, 2020.
  14. News: Locsin. Joel. Cebu pavilion for int'l catholic congress 50% done, to be completed by September. February 2, 2016. GMA News. March 15, 2015.
  15. Web site: IEC 2016 Committee Visits Pavilion Site. International Eucharistic Congress-Cebu. February 2, 2016. January 5, 2015.
  16. News: Quintas. Kristine. Palaubsanon. Mitchelle. Bets urged: Respect IEC. February 2, 2016. The Freeman. November 20, 2015.
  17. Web site: Facilities. IC3 Convention Center. May 19, 2017.