Huntington Beach Energy Project | |
Name Official: | Huntington Beach Energy Project |
Country: | United States |
Location: | Huntington Beach, California |
Status: | O |
Construction Began: | Units 1-4: 1958 Unit 5: June 2017 |
Commissioned: | Units 1-4: 1967 Unit 5: February 4, 2020 |
Decommissioned: | Units 1: December 31, 2019 [1] Unit 2: December 31, 2020 (expected) Unit 3: ? Unit 4: ? |
Owner: | AES Corporation |
Operator: | AES Corporation |
Th Fuel Primary: | Natural gas |
Ps Combined Cycle: | Yes |
Ps Cooling Source: | Unit 2: Pacific Ocean Unit 5: Atmosphere |
Ps Units Operational: | 1 x 225 MW CCGT 1 x 644 MW CCGT |
Ps Units Planned: | 1 x 200 MW SCGT |
Ps Units Decommissioned: | 1 x 225 MW CCGT 2 x ? MW |
Ps Electrical Capacity: | 869 MW |
The Huntington Beach Energy Project (HBEP), formerly AES Huntington Beach, is a natural gas-fired power station located in Huntington Beach, California.
The facility was constructed between 1958 and 1969 on a 53adj=midNaNadj=mid.[2] Total station capacity was 1,000,000 kilowatts. It originally consisted of two 215 MW General Electric cross compound 3600/1800 RPM steam turbines (HP/LP turbines). Main steam pressure was 2400 PSI, main steam temperature was 1050 DEG F and reheat temperature was 1000 DEG F. The generators were hydrogen cooled, rated at 128,000 KVA. The boilers were Babcock and Wilcox natural circulation (drum boilers), rated at 1,560,000 LB/HR. The boilers could be fired with natural gas or fuel oil. Units 1 and 2 were completed in 1958. Unit 3 was a General Electric cross compound 3600/1800 RPM at 1050/1000 DEG F, with a 215 MW steam turbine. Unit 4 was a Westinghouse, cross compound 3600/1800 rpm, 1050/1000 DEG F 225MW. The boilers were Babcox and Wilcox Universal Pressure Boilers (called once thru) rated at 1,638,000 LB/HR. All four units were cooled using water sourced from the Pacific Ocean. Unit 5 was completed in 1969 and was a gas peaking unit, rated at 121 MW at 90 deg F. It consisted of 8 Pratt & Whitney GG4a-2 gas turbines exhausting into 4 Worthington expanders 2 stage turbines and 1 Westinghouse generator, 3 phase hydrogen cooled rated at 162,500 KVA, 16,000 volts 3600 rpm. Unit 1 was decommissioned on December 31, 2019, while Units 3 and 4 were decommissioned at an unknown date. Unit 2 is the only original unit still in operation.[1]
In June 2017, AES began construction of a 644 MW combined cycle gas turbine (Unit 5) that is visually smaller and is air-cooled.[3] Unit 5 was commissioned on February 4, 2020. An additional 200 MW simple cycle gas turbine is proposed for the site should additional capacity be necessary.[4] [5]