Hongping Pumped Storage Power Station | |
Coordinates: | 29.0664°N 115.3184°W |
Country: | China |
Location: | Hongping, Jing'an County, Jiangxi Province |
Status: | UC |
Construction Began: | 2010 |
Opening: | 2014-2017 (Phase 1) |
Operator: | Jiangxi Hongping Pumped Storage Ltd. |
Res Name: | Hongping Upper |
Res Capacity Total: | 27060000m2, 6300000m2 (active) |
Lower Res Name: | Hongping Lower |
Lower Res Capacity Total: | 54140000m2, 35470000m2 (active) |
Plant Pumpgenerators: | 4 x 300 MW Francis pump turbines |
Plant Hydraulic Head: | 528m (1,732feet) |
Plant Capacity: | 1,200 MW |
Plant Annual Gen: | 1,700 GW·h (planned) |
The Hongping Pumped Storage Power Station is a 1,200 MW pumped-storage hydroelectric power station located at about 11km (07miles) northwest of Hongping in Jing'an County of Jiangxi Province, China. It was the first pumped-storage hydroelectric power station constructed in Jiangxi.
It is operated by Jiangxi Hongping Pumped Storage Ltd.[1]
The project was split into two phases, with first phase resulting in 1,200MW of installed capacity. Construction on the project's first phase began in June 2010. The first generator was commissioned in June 2014 and by December 2016, all the four 300MW generators were commissioned, marking the end of the first phase.[2]
In 2021, a feasibility study on the second phase of the project was begun.[3] The study completed in November 2022 and the second phase project, which plans to add an additional total capacity of 1,800 MW to the power station, was deemed feasible. [4] When fully operational, the power station will have an installed capacity of 3,000 MW.
The lower reservoir is created by a 77.5m (254.3feet) tall and 181.25m (594.65feet) long roller-compacted concrete gravity dam on the Hebei River. It can withhold up to 54140000m2 of water, of which 35470000m2 can be pumped to the upper reservoir. The upper reservoir is created by a 44m (144feet) tall and 107m (351feet) long concrete gravity dam. It can withhold up to 27060000m2 of water, of which 6300000m2 can be used for power production. Water from the upper reservoir is sent to the underground power station down near the lower reservoir through two 1318.2- long headrace/penstock pipes. The power station contains four 300 MW Francis pump turbines. The difference in elevation between the upper and lower reservoir affords a hydraulic head (water drop) of 5280NaN0.[5]