HVDC Leyte–Luzon explained

HVDC Leyte–Luzon
Country:Philippines
Province:Leyte
Sorsogon
Camarines Sur
Coordinates:11.0886°N 124.6392°W
11.3933°N 124.9844°W
12.5669°N 124.2747°W
12.6539°N 124.1161°W
13.6111°N 123.2386°W
Start:Leyte
Through:San Juanico Strait
Finish:Luzon
Owner:National Power Corporation (August 10, 1998 – March 1, 2003)
National Transmission Corporation (March 1, 2003–present)
Operator:National Power Corporation (August 10, 1998 – March 1, 2003)
National Transmission Corporation (March 1, 2003 – January 15, 2009)
National Grid Corporation of the Philippines (January 15, 2009–present)
Cable Manufacturer:ABB Group
Cable Installer:ABB Group
Substation Manufacturer:ABB Group
Substation Installer:ABB Group
Current Type:HVDC
Length:451
Capacity:440 MW
Dc Voltage:350 kV
Poles No:1

HVDC Leyte–Luzon is a high-voltage direct current transmission link in the Philippines between geothermal power plants on the islands of Leyte and Luzon.

Abbreviated as 8LI1NAG-ORMOC, 8LI1NAG-ORMOC HVDC [1] (with "HVDC" at end) and known as Ormoc-Naga HVDC transmission line.

History

The feasibility study of the transmission project was conducted by the Japan International Cooperation Agency in 1981.[2] The project financing was approved by World Bank in June 1994, co-financed also by the Japan Export-Import Bank.[3] The HVDC Leyte–Luzon went in service on August 10, 1998. It is operated by the privately owned National Grid Corporation of the Philippines (NGCP) since January 15, 2009, and previously by government-owned companies National Transmission Corporation (TransCo) and National Power Corporation (NAPOCOR). It was owned previously by NAPOCOR from August 10, 1998, to March 1, 2003, and is owned currently by TransCo since March 1, 2003.

Technical description

The transmission line is an triple-bundle power line and bipolar HVDC.

Capacity of the Leyte-Luzon is a 440 MW.[4] [5] It is implemented as monopolar line for a voltage of 350 kV, feeding the power grid in the Manila region. In addition to overall connection of grids, HVDC was chosen to enable supply of bulk geothermal power, and to stabilize the alternating current network in Manila region.[6] The interconnector was manufactured by the ABB Group in cooperation with Marubeni Corporation.

The length of submarine cable is 21km (13miles) and the total length of overhead lines is 430km (270miles).[6] [5]

The crossing of San Juanico Strait is realized as overhead crossing with a tower on an island in the strait.

By time in construction of the 1st tower ((8LI1NAG-ORMOC HVDC)0001) was erected and it is now commonly the first HVDC tower in the Philippines.

Route

The HVDC Leyte–Luzon begins at Ormoc converter station (Leyte) and ends at Naga converter station (Camarines Sur).[7] It consists three sections:

The grounding electrodes are situated at Albuera at 10.9003°N 124.7067°W and near Calabanga at 13.7331°N 123.2414°W . They are connected with the converter stations by 25 respectively 15-kilometre-long overhead lines. These lines are 69kV DC.

External links

Notes and References

  1. News: s . s . Jan 25, 2024 . Attachment 1 2023 GOMP Revision 3 Bar Chart Schedules-2024-01-25-1639-37 . . 44.
  2. Report on Feasibility Study on Leyte Power Transmission Project . . I . 3 . February 1982 . 2021-05-01.
  3. Ownership, Financing and Licensing of Geothermal Projects in the Philippines . Dolor . Francis M. . Workshop for Decision Makers on Geothermal Projects in Central America . San Salvador, El Salvador . 9–12 . November 26 – December 2, 2006 . 2021-05-01.
  4. Book: HVDC Submarine Power Cables in the World . Ardelean . Mircea . Minnebo . Philip . JRC Technical Reports . . 66 . 2015 . 978-92-79-52785-2.
  5. Web site: Leyte - Luzon . Hitachi ABB Power Grids . 2021-05-01.
  6. High Voltage Direct Current (HVDC) Transmission Systems . Rudervall . Roberto . Charpentier . J.P. . Sharma . Raghuveer . Energy Week . Washington, D.C. . March 7–8, 2000 . 2021-05-01.
  7. Book: HVDC Transmission: Power Conversion Applications in Power Systems . 398–399 . Chan-Ki Kim . Vijay K. Sood . Gil-Soo Jang . Seong-Joo Lim . Seok-Jin Lee . 2009 . 9780470822968 . Wiley.