Grafenrheinfeld nuclear power plant explained

Grafenrheinfeld nuclear power plant
Name Official:Kernkraftwerk Grafenrheinfeld
Country:Germany
Location:Grafenrheinfeld
Coordinates:49.9841°N 10.1847°W
Owner:PreussenElektra
Operator:PreussenElektra
Status:Demolished
Construction Began:January 1, 1975
Commissioned:December 21, 1981
Np Reactor Type:PWR
Np Reactor Supplier:Siemens
Ps Cooling Source:River Main
Ps Cooling Towers:2
Ps Units Manu Model:Siemens
Ps Units Operational:1 x 1,345 MW
Ps Electrical Capacity:1,345
Ps Annual Generation:9,425
Ps Electrical Cap Fac:80.0%
Website: Plant's site on E.ON's site

The Grafenrheinfeld nuclear power plant (German: Kernkraftwerk Grafenrheinfeld, KKG) is a now-offline electricity-generating facility near Grafenrheinfeld, south of Schweinfurt at the river Main. The plant operated from 1981 to June 28, 2015, when it was taken offline as part of the phase out policy for nuclear power in Germany. As a result of the plant's closure, Germany has relied heavily on coal and natural gas, primarily from Russia, to generate electricity.[1]

Construction and history

Construction took place between 1974 and 1981, which cost around 2.5 billion DM. The reactor, a German third-generation pressurized water reactor with an electrical net power output of 1,345 megawatts, achieved first criticality on December 9, 1981.

The plant is managed by PreussenElektra GmbH. The two 143m (469feet) tall cooling towers were visible from far away. As with almost all other nuclear plants, temporary storage facilities for spent nuclear fuel are present on site. There is an information center at the power station.

Under the phase out policy for nuclear power in Germany, the plant was scheduled to shut down on 31 December 2015. Citing economical reasons, E.ON declared intent to shut down the plant earlier, originally at end of May 2015.[2] [3]

Since its closure the plant was inoperative, and on 16th August 2024 the cooling towers were demolished using explosives. The demolition was delayed momentarily by a pro-nuclear protestor who had climbed ten meters up a power pole within the blast radius.[4]

Plant taken offline

The Grafenrheinfeld plant was taken offline on June 28, six months before scheduled to close on December 3, 2015 as part of Germany's ongoing policy to shut all nuclear power plants down in the country by 2022.[5] [6] The plant owners decided it was uneconomic to continue operation as planned.[7]

In the media

In the anti-nuclear teen novel Die Wolke (1987), the power plant undergoes a meltdown.

Notes and References

  1. News: Connolly . Kate . 2022-07-08 . Germany to reactivate coal power plants as Russia curbs gas flow . en-GB . The Guardian . 2023-05-24 . 0261-3077.
  2. Web site: Die gesuchte Seite ist leider nicht verfügbar (Fehlernummer 500). Tagesschau.de. 2016-07-16.
  3. Web site: E.ON preparing for Grafenrheinfeld nuclear plant's May closure | Energy & Oil | Reuters . https://web.archive.org/web/20150316083119/http://af.reuters.com/article/energyOilNews/idAFL5N0W81W620150306 . dead . 2015-03-16 . Af.reuters.com . 2015-03-06 . 2016-07-16.
  4. Web site: mdr.de . Kühltürme des AKW Grafenrheinfeld verspätet gesprengt MDR.DE . 2024-08-16 . www.mdr.de . de.
  5. Web site: Germany's oldest remaining nuclear plant shuts down - Lowell Sun Online . Lowellsun.com . 2016-07-16 . 2015-08-06 . https://web.archive.org/web/20150806000837/http://www.lowellsun.com/ci_28396790/germanys-oldest-remaining-nuclear-plant-shuts-down . dead .
  6. Web site: Germany's oldest remaining nuclear plant shuts down | Technology News . US News . 2015-06-28 . 2016-07-16.
  7. Web site: Grafenrheinfeld ends electricity production - World Nuclear News.