Gisagara Thermal Power Station Explained

Gisagara Thermal Power Station
Location Map Caption:Location of the Gisagara Thermal Power Station
Coordinates:-2.2992°N 29.9539°W
Country:Rwanda
Location:Gisagara District, Southern Province
Status:UC
Construction Began:2017[1]
Commissioned:2021 (Expected)
Cost:US$350 million
Owner:Hakan Mining and Generation Industry & Trade Inc.
Operator:HQ Power Rwanda
Th Fuel Primary:Peat
Ps Electrical Capacity:80MW

Gisagara Thermal Power Station is an, peat-fired thermal power plant, under construction in Gisagara District, in the Southern Province of Rwanda.[1] [2]

Location

The power station is located in Akanyaru Village, Gisagara District, Southern Province, approximately 75km (47miles), by road, southwest of the city of Kigali, the capital and largest city in Rwanda.

Overview

A study by Ekono Inc., an American company, found that Rwanda has dry peat reserves estimated at 155 million tons, spread over 50000ha. Hakan Mining and Generation Industry & Trade Inc., a Turkish Independent Power Producer, won the rights to build an 80 MW peat power plant in Gisagara District, Southern Rwanda.[3]

In 2016, Hakan signed a power purchase agreement (PPA) with the government of Rwanda to design, finance, build, own and operate the plant using peat extracted from Akanyaru in Gisagara District. Rwanda would in turn buy the power generated and integrate it into the national electricity grid.[4]

The 80MW Gisagara Peat Power Plant will complement the 15MW Gishoma Thermal Power Station, which came online in 2017.[5] [6]

Budget and timetable

Hakan will finance the estimated US$400 million (Rwf300 billion) project. Construction began in 2017 and completion was expected in 2020.[4] Other credible sources have put the construction budget at US$350 million.[1]

In August 2020, Rwandan print media reported that overall progress of development of the power station was estimated at 96.7 percent, with completion anticipated in April 2021.[7] In January 2021 Taarifa Rwanda, an online publication, indicated that the power station was expected to come online in February 2021. The cost of the development is reported as US$350 million.[8]

Developers

The power station was developed and is currently owned by a consortium comprising (a) Hakan AS, a Turkish solid fuel company (coal, peat etc.) (b) Quantum Power, an International power company and (c) Themis, a project development company. The consortium has developed a special purpose vehicle (SPV) company, HQ Power Rwanda. The owner developers have signed a power purchase agreement to construct, operate, maintain and own the power station for 26 years from date of commissioning and to sell the electricity generated to the Rwandan electricity utility company. Ownership of the power plant will then revert to the Government of Rwanda.[8]

Funding

, the funding for this project included the following:[2]

Funding of Gisagara Thermal Power Station! Rank !!Name of Lender!!Amount Loaned (US$m)!!% of Total
1 75.0 21.43
2 35.0 10.00
3
4 Exim Bank of India
5
6
Total350.00100.00

See also

External links

Notes and References

  1. Web site: Dan . Construction of 80MW Gisagara Peat Plant In Progress . 21 May 2018 . 10 January 2018 . Ngabonziza . KTPress.rw . Kigali.
  2. Web site: Rwanda's peat to power project earns AFC global award . 12 March 2018 . 9 March 2018 . East African Business Week (EABW). EABW Reporter . Kampala.
  3. Web site: PRNewswire . Rwanda Prepares to Switch on Africa's First Peat Fired Power Plant, Reports KT Press . 24 October 2014 . KT Press . 24 February 2016 . Kigali, Rwanda.
  4. Web site: Turkish firm lands energy production deal in Rwanda . Kennedy . 24 February 2016 . 20 February 2016 . Senelwa . . Nairobi . 23 February 2016 . https://web.archive.org/web/20160223174258/http://www.theeastafrican.co.ke/business/Turkish-firm-lands-energy-production-deal-in-Rwanda-/-/2560/3085558/-/ew30b/-/index.html . dead .
  5. Web site: Jean-Pierre Bucyensenge . Gisagara peat power plant to generate 80 megawatts . 26 September 2014 . 12 March 2018 . . Kigali.
  6. Web site: Rwanda adds to energy mix with first peat-fired power plant in Africa . 21 May 2018 . 10 April 2017 . Theconversation.com . The Conversation.
  7. Web site: . 2 September 2020 . Rwanda: Electricity Production From Gisagara Peat-Fuelled Plant Begins Next Year . 6 September 2020 . Kigali . . James Karuhanga.
  8. Web site: Rwanda Completes Construction Of 80MW Peat Power Plant . Taarifa Rwanda . 2 January 2021 . Taarifa Staff Writer . 21 January 2021 . Kigali.