Gavins Point Dam | |
Location Map: | USA Midwest#USA |
Location Map Caption: | Location of Gavins Point Dam in the Midwestern United States. |
Coordinates: | 42.8494°N -97.482°W |
Country: | United States |
Location: | Cedar County, Nebraska and Yankton County, South Dakota. |
Status: | O |
Cost: | $51 million |
Owner: | U.S. Army Corps of Engineers, Omaha District |
Dam Type: | Embankment, rolled-earth and chalk-fill |
Dam Height: | 740NaN0 |
Dam Length: | 87000NaN0 |
Dam Width Crest: | 350NaN0 |
Dam Width Base: | 8500NaN0 |
Dam Volume: | 70000000NaN0 |
Dam Crosses: | Missouri River |
Res Name: | Lewis and Clark Lake |
Res Capacity Total: | 4920000NaN0 |
Res Catchment: | 2794800NaN0 |
Res Surface: | 31400acres |
Res Elevation: | 1,210 feet msl |
Res Max Depth: | 450NaN0 |
Res Max Length: | 250NaN0 |
Plant Operator: | U.S. Army Corps of Engineers (Operator); Western Area Power Administration (marketer) |
Plant Commission: | 1957 |
Plant Turbines: | 3 x 44 MW |
Plant Capacity: | 132 MW |
Plant Annual Gen: | 727 million KWh[1] |
Website: | U.S. Army Corps of Engineers, Gavins Point Project |
Gavins Point Dam is a 1.9miles embankment rolled-earth and chalk-fill dam which spans the Missouri River and impounds Lewis and Clark Lake. The dam joins Cedar County, Nebraska with Yankton County, South Dakota a distance of 811.1 river miles (1,305 km) upstream of St. Louis, Missouri, where the river joins the Mississippi River. The dam and hydroelectric power plant were constructed as the Gavins Point Project from 1952 to 1957 by the United States Army Corps of Engineers as part of the Pick-Sloan Plan. The dam is located approximately 4 miles (6.4 km) west or upstream of Yankton, South Dakota.
Gavins Point Dam was constructed as a part of the Pick–Sloan Missouri Basin Program, authorized by the Flood Control Act of 1944 by Congress. The dam is named after Gavins Point, a bluff along the northern bank of the Missouri River named for an early settler, now within the western end of Lewis & Clark Recreation Area, which was to be the original location of construction of the dam. The location was moved and construction began further downstream along Calumet Bluff because this location offered a shorter span distance and less fill material needed for dam construction, although the project kept the original name. The dam operations work in conjunction with the other Pick-Sloan Program Dams to assist with conservation, control, and use of water resources in the Missouri River Basin. The intended beneficial uses of these water resources include flood control, aids to navigation, irrigation, supplemental water supply, power generation, municipal and industrial water supplies, stream-pollution abatement, sediment control, preservation and enhancement of fish and wildlife, and creation of recreation opportunities. Gavins Point is the most downstream dam on the Missouri River, being 811.1 river miles upstream of St. Louis where the river meets the Mississippi River. The next dam upstream is Fort Randall Dam.[2]
During the 2011 Missouri River Flood, the dam released a record water flow of 160,200 cfs, topping the previous record of 70,000 cfs in 1997. During the 2011 flood, the debris damaged the dam and a significant portion of rocks were dislodged from its upstream side. The U.S. Army Corps of Engineers soon began repairs to the dam and its spillway gates. Pressure sensors were also installed in concrete portion of the dam.[3] [4]
The dam has a hydroelectric power plant with three generators, each having a nameplate capacity of 44,099 kW, for a total of 132.297 MW.[5] The hydroelectric power plant provides enough electricity to supply 68,000 homes. Power generated is sold through the Western Area Power Administration.
See main article: Lewis and Clark LakeGavins Point Dam creates Lewis and Clark Lake, a popular regional tourist destination for water-based recreational opportunities including boating and fishing, along with camping, hiking, and hunting opportunities managed by the State of South Dakota, State of Nebraska, and the U.S. Army Corps of Engineers. The lake is significantly impacted by sedimentation and siltation issues, diminishing the overall water surface area, water storage capacity, and recreational opportunities. Sediment carried by the Missouri River and Niobrara River is slowed and trapped within the reservoir due to the dam impounding and thus stopping the natural river flow. Studies show approximately 5.1 million tons of sediment are deposited in the lake each year, which contributes to the lake's increasing size of delta area on the western portions of the lake. Approximately 60% of the sediment comes from the Nebraska Sandhills via the Niobrara River. As of 2016, approximately 30% of the lake's overall surface area has diminished due to sedimentation deposits, and some figures project by 2045 approximately 50% of the lake will be diminished due to sedimentation deposits. Presently, there is no plan or solution to remove or slow the progression of the siltation within the lake.[6]