Highways in Poland explained

Controlled-access highways in Poland are part of the national roads network and they are divided into motorways and expressways. Both types of highways feature grade-separated interchanges with all other roads, emergency lanes, feeder lanes, wildlife crossings and dedicated roadside rest areas. Motorways differ from expressways in their technical parameters like designated speed, permitted road curvature, lane widths or minimal distances between interchanges. Moreover, expressways might have single-carriageway sections in case of low traffic densities (as of 2024, such sections constitute 3.5% of the highway network).

The development of modern highways began in the 1970s, but proceeded very slowly under the communist rule and for the first years afterwards – between 1970 and 2000 only the total of 434 km of highways were constructed (5% of the planned network).[1] Further 1050 km (13% of the network) were opened from 2001 to 2010, followed by 2773 km (34% of the network) constructed between 2011 and 2020.[2] It is planned to open about 3000 km (about 37%) in the 2020s, while the last 10% would be completed after 2030.

, there are 5142.5 km[3] of motorways and expressways in operation (62% of the intended network), while contracts for construction of further 1246 km[4] (15% of the network) are ongoing.

Except for the single-carriageway expressways, both types of highways fulfill the definition of a motorway as characterized by OECD, WRA or Vienna Convention. Speed limits in Poland are 140 km/h on motorways and 120 km/h on expressways (100 km/h in case of single-carriageway expressway sections). Some motorway stretches are tolled.

Technical parameters

  1. Expressways are designated for lower speed than motorways. For example, the road curvature can be higher and the lanes are usually narrower (3.5m vs 3.75m). Emergency lanes can also be narrower (2.5m vs 3m) and in exceptional situations expressways might not have them at all.
  2. Expressways can have a single carriageway on sections with low traffic density.
  3. Motorways can have interchanges only with main roads and the distance between interchanges is typically not less than 15 km (or 5 km near major cities), while expressways typically have more frequent interchanges. In exceptional situations, expressways might not have dedicated feeder lanes on interchanges.

Formally, expressways are also allowed to admit a one-level junction with a minor public road in exceptional cases,[5] however in 2020 the last such remaining junction in Poland was reconstructed into a two-level interchange.[6] [7] [8]

Speed limits

Maximum speed (km/h)
Vehicle Motorway 2-lane expressway 1-lane expressway
Private car, motorbike, van up to 3.5t (does not apply if towing trailer)140120100
Bus meeting additional technical requirements100
Bus; a vehicle over 3.5t or towing trailer or carrying dangerous materials80
Vehicle having equipment more than 1.5m forward of the driver's seat60
Motorbike (including towing trailer) carrying a child up to 7 years-old40
Not allowed on motorways: pedestrians, bikes, mopeds, agricultural vehicles. Minimal speed on motorways is 40 km/h unless there are any extraordinary circumstances (e.g., snow, ice, or a car broken down). It is forbidden to stop except extraordinary situations, or travel backwards. Towing is not allowed on motorways, but is permitted on expressways.

List of motorways and expressways

In 2004, the government published a document defining the planned highway network of length about .[9] Notable changes introduced in later amendments include re-routing S8 and adding S61 instead (a change related to the Rospuda Valley conflict),[10] introducing S16, S52 and A/S50,[11] as well as extending S5,[12] S8[13] and S10.[14] [15] [11]

The planned network consists of 16 major highways (over 200 km of intended length): A1, S3, S5, S7, S11, S17, S19, S61 running north to south and A2/S2, A4, S6/A6, S8/A8, S10, S12, S16, S74 running west to east, as well as 9 shorter highways:[16] [17] [18] [19] [20]


1) Highways and major sections completed
SignRouteLocationTotal lengthExistingYears of opening
Gdańsk (S6) - Grudziądz (S5) - Toruń (S10) - - - - 566.6 km566.6 km100%

Main section:
- S3 - Poznań - -
489.7 km 454.9 km
34.8 km  
100%mainly

Main section:
Szczecin (A6) - - A2 - Zielona Góra - Legnica (A4) -
368.7 km368.7 km
of which 3 km near the Czech border remain closed until
100%2010 – 2024
- - - Opole - - - - - 669 km669 km
100%1983 – 2016
Main section:
-
340.3 km340.3 km100%2012 – 2022

Main section:
Wrocław (A4) - Łódź (A1) - Piotrków T. - Warsaw -
548.2 km 525.5 km
22.7 km  
100%2008 – 2019
Łódź
40.2 km40.2 km
100%2012 – 2023
Main section:
Warsaw (A2) – Lublin (S12/S19)
150 km150 km100%2013 – 2020
76.5 km76.5 km
100%2006, 2022/2023
52.2 km
single carriageway
50%2008
Olsztyn (S16) – Olsztynek (S7)20.3 km20.3 km100%2012, 2019
Warsaw4.8 km4.8 km100%2013
Upper Silesia5.9 km5.9 km100%1985

2) Highways in development
SignRouteLocationTotal lengthExistingConstruction commencedOf which under active constructionScheduled years of opening[21] TenderIn predesign
Katowice Airport (A1) - Mysłowice (A4) - Bielsko-Biała (S52) - 144 km
59%
(64.9%)
4.8 km
+ 3.7 km single carriageway
2025
+ 0.5 km 1st carriageway
(65.3%)+ 0.5 km
(reconstruction of the interchange in Dąbrowa Górnicza, 1 lane per direction is open to traffic)
2024
(+ 39.5 km)
dual carriageway road
(94.1%)+ 39.5 km
(new route)
+ 27 km
(new route)
2025, 2026
Eastern section:
168.2 km35.1 km20.9%100.8 km2024, 2025, 2029?32.3 km
Northern section:
85.4 km50.9 km
+ 5.4 km 1st carriageway
62.8%29.1 km
+ 5.4 km 2nd carriageway
2024/2025

402.4 km 28.1 km  
228.4 km
+ 9.4 km 1st carriageway
64.9%136.5 km
+ 9.4 km 2nd carriageway
2025
Gdańsk (A1) - Elbląg (S22) - Olsztynek (S51) - approx. 709 km82.7%
<
-- 334 km -->45 km
(are open to traffic on the whole length of the reconstruction site)
2025, 2027,  2032? (reconstruction
(+ 58 km)
(100%)
Warsaw - Radom (S12) - Kielce (S74) - Kraków (A4)
91.6% <-- 281.7 km -->23.6 km
2024, 2025
Kraków (A4) - Rabka-Zdrój - 34.6%<-- 91.8 km -->2030?, 2032?, 2038?
(+ 25 km)
(62%)
Eastern section:
Lublin (S17/S19) - Chełm -
103.7 km29.2 km28.2%68.8 km14 km2025, 2027,
2030?
5.7 km

Via Carpatia
- Białystok (S8) - Lublin (S12/S17)572.5 km18.5 km
1st carriageway
2.9% <--317.8 km-->229.9 km
2nd carriageway<
--13.7 on A2-Lublin, 4.8 north of Bialystok-->87.8 km
2nd carriageway
2025, 2026,
2027, 2028?
69.4 km
<
--40.2 km: DŚU overruled-->
141.7 km

94.8%
(100%)
<
--158 km-->16.3 km
2nd carriageway
2026
Rzeszów (A4) – 11.4 km11.8% <-- 96.6 km-->80 km42.6 km2025, 2026, 2027
5.2 km

part 2
Kraków-Balice (A4) – Kraków‑Mistrzejowice (S7)Kraków
18.3 km5.8 km31.4%12.5 km2024

Via Baltica
Ostrów Mazowiecka (S8) - Łomża - Ełk (S16) - Suwałki - 210.7 km197.8 km93.9%12.9 km2024/2025

3) Highways partially in development
SignRouteLocationTotal lengthExistingConstruction commencedOf which under active constructionTender completeIn predesignPlanned [22]
Southern extension:
Wrocław (A8) - Kłodzko -
approx. 127.4 km5.1 km4%32.5 km36.3 kmapprox. 53.5 km2027, 2033
Main section:
- Bydgoszcz (S5) -
297 km
+ 17.5 km
1st carriageway
19.8%40 km
+ 10.9 km 2nd carriageway
112 km37.8 km2030
+ 39.5 km
- 556.5 km154.4 km
+ 10.5 km
1st carriageway
28.7%92.1 km
+ 4.2 km 2nd carriageway
25 km77 km2030

+ 6.3 km 2nd c/w
Eastern section:
Lublin (S12/S19) - Zamość -
126 km9.6 km
+ 2 km 1st carriageway
8.4%47.7 km44.3 km22.3 km2029
+ 2 km 2nd c/w
Sulejów (S12) - Kielce (S7) - Sandomierz - Nisko (S19)207 km6.7 km3.2%108.6 km9.7 km92 km2032

4) Planned highways
SignRouteLocationTotal lengthExistingConstruction commencedOf which under active constructionTender completeIn predesignPlanned
Eastern extension:
approx. 104.3 km14.3 km13.7%approx. 90 km2033
Western extension:
Bolków (S3) – Świdnica – S8
approx. 50 km0 km0%approx. 50 km2031
Western extension:
Szczecin
50.8 km0 km0%1.5 km49.3 km2031
Eastern section:
-
approx. 120 km0 km0%2033
Western section:
- Radom (S7) - Lublin (S17)
185 km16.4 km
+ 6.0 km
1st carriageway
10.7%29.1 km133.5 km
+ 6.0 km 2nd c/w
2032
Olsztyn (S51) - Ełk (S61) - approx. 245 km46.2 km

1st carriageway
23%8.7 km
+ 20.1 km 2nd carriageway
11 km77.5 km2037
+ approx. 81.5 km
Marki (S8) – Lubelska (A2/S2)Warsaw
17.3 km3.5 km20.2%13.8 km2032

Warsaw
(2nd ring road)
approx. 265 km0 km0%
<
-- S50 length excluding the part that is planned to be joint with S10 !-->2036
- 98 km37 km37.8%61 km2032
In total
Highway typePlanned lengthExistingConstruction commencedOf which under active constructionTenderPredesign completeIn predesignNo progress
approx. 1853 km88.83%100.8 km100.8 kmapprox.
132.3 km
approx. 3102.1 km
+ 177.6 km
1st carriageway
52.22%945.8 km

502 km

317.1 km1.5 kmapprox.
1562.1 km

2nd carriageway
Totalapprox. 4955.1 km

1st carriageway
61.54%1046.6 km

602.8 km

317.1 km1.5 kmapprox.
1694.4 km

2nd carriageway

2nd carriageway

As of 2024, the operational sections of highways utilize the following cross-sections:

All single-carriageway expressways are constructed with allocated space for a possible upgrade to dual-carriageway and all bridges above such highways are prepared to accommodate the second carriageway. Most of those sections are planned to be widened to full profile by 2033, the exceptions being S1 (near the Slovak border) and S22 (near the border with Kaliningrad Oblast) where widening is currently not expected.[20]

Tolls

Since 2023, almost all highways are free for vehicles up to 3.5 tons of permissible maximum weight[23] [24] (for a passenger car with a trailer, the joint permissible maximum weight of the car and the trailer must not exceed 3.5 tons[25]). On some sections, the old infrastructure for toll collection is still in place.

The privately-owned sections of A2 and A4 are tolled. In the closed system, there are toll stations on every interchange both entering and exiting the tolled section; the driver receives a ticket upon entering the motorway and pays on the exit, with the price dependent on the distance driven. In the open system, two toll stations are located at the ends of the section; a person driving the whole distance pays at both gates, while a person entering or leaving the motorway mid-section pays only at one gate. The following sections are tolled:

Vehicles over 3.5 tons and buses

Using e-Toll is obligatory for buses as well as all vehicles with maximum permissible weight exceeding 3.5 tons (including the trailer) while driving on the Polish roads (not just the highways). More details can be found on the e-Toll website.[28]

Traffic volumes

Traffic volumes in Poland note rapid increase since the fall of communism in 1989: the annual average daily traffic recorded in 2020 amounts to over 360% of the average traffic recorded in 1990.[29] [30] With the increasing traffic, the length of overburdened single-carriageway national roads[31] had also been steadily increasing until reaching the maximum of 1389 km in 2010.[32] Due to the large number of highway sections opened between 2010 and 2020, in that decade the length of overburdened roads has fallen down for the first time in history, from 1389 km in 2010 to 1121 km in 2020.[30]

The latest general measurement was conducted in 2020, although some measurement days were moved to 2021 due to the COVID-19 pandemic which would have caused the results from 2020 to be unreliable.[33] The following highways recorded the highest volumes:[34]

Most busy highways in Poland (absolute numbers)
NoSectionNotes
1S8 in Warsaw (partially joint with S7)198'000
Highest AADT on sections with 3 lanes per direction: 179k.
S8 in Warsaw serves both the transit and local traffic, and long jams form on it during rush hours.
S2, Warsaw southern bypass
(partially joint with S7 and S8)
114'000 From 3 to 5 lanes per direction.
2S86113'000S86 serves mainly local traffic between Sosnowiec and Katowice and is not part of Poland's transit network. 3 lanes per direction.
3A4 in Katowice105'000A4 serves both the transit traffic (2 lanes per direction) and local traffic (2 lanes per direction).
Most busy highways in Poland (per number of lanes)
NoSectionNotes
1S8 in Warsaw (partially joint with S7)S8 in Warsaw serves both the transit and local traffic, and long jams form on it during rush hours.
2S6, Gdańsk, Sopot and Gdynia bypass93'000 / 2x2 lanesSome decrease in traffic on S6 is expected after Tricity Outer Bypass (S7) is opened in mid 2025.
3A4, Kraków western bypass85'000 / 2x2 lanesSome decrease in traffic on A4 is expected after Kraków north-eastern bypass (S7/S52) is opened in mid 2025. Widening to 3 lanes per direction is planned in the future (after 2030).

The other highest and lowest recorded AADT values were:

CategorySectionNotes
Most busy regular national roads in Poland
Note: Measurements are not performed on national roads within the borders of major cities
Most busy dual-carriageway national roadDK7 north of Warsaw63'000 New parallel route of S7 is planned to be opened in the future (around 2032).
DK44 west of Kraków36'000Widening to 2 lanes per direction is planned in the future (after 2030).[35]
within the planned highway networkDK19 north of Lublin28'500S19 is under construction, expected to be opened in mid-2026.
Least busy highways in Poland
Least busy single-carriageway highwayS22 near 800The results cannot be considered fully reliable, because the measurement has been conducted while major restrictions in entering European Union via its external border were in force because of the COVID-19 pandemic.
Least busy dual-carriageway highwayA4 near 1'800
Least busy highway excluding near-border sections3'900 – 6'400

Substandard highways

Motorways and expressways constructed before 1999 do not have to fulfill technical parameters listed in the ordinance. As of 2024, one notable case of a substandard highway remains:

Notable historical cases are:

History

Before World War II

The first plans of creation of a national highway network in Poland were conceived in the interwar period:

Plans

The main promoter of this concept was Professor Melchior Wladyslaw Nestorowicz of the Warsaw University of Technology, who organized three Road Congresses, during which a group of specialists discussed the creation of the network. On March 5, 1939, in the trade magazine Drogowiec, Professor Nestorowicz proposed a very ambitious plan for the construction of almost 5,000 kilometres of category I and II roads, based on similar programmes in Germany and Italy.[38] Nestorowicz sketched a map of the future system with the following routes:

First class roads would, according to the plans, consist of the following motorways (totalling some :

Second class roads would consist of the following motorways, totalling another :

In 1934, Nazi Germany started the construction of their motorway system, parts of which today form A18 and A4 to Wrocław (Breslau), as well as A6 (Szczecin bypass) and S22 (parts of the planned motorway to Königsberg). About half of them were constructed as single-carriageway with the intention of adding a second carriageway in later years. However, after 1938, warfare expenses meant little money would be invested into any infrastructure and only one 9 km single-carriageway piece west of Gliwice (now A4) was constructed.

SignageSectionLengthStart of constructionOpeningNotes
Krzyżowa – Krzywa
Krzywa – Wrocław
Wrocław – Brzeg (Owczary)Southern carriageway only
Ujazd (Nogowczyce) – Łany
Łany – Kleszczów (Gliwice)
– Szczecin-Zachód
– IłowaSouthern carriageway only
IłowaGolnice
Elbląg – GrzechotkiWestern carriageway only
Total
of which single carriageway
Note: Signage of the roads at the time of opening was different.

In Poland, a 28 km stretch between Warlubie and Osiek (now DW214) was constructed in 1937 – 1939 in the motorway standard of the time (today not considered a highway) with a concrete surface, which was designed by Italian engineer Piero Puricelli. The motorway was planned to reach Gdynia, but the outbreak of the Second World War halted the plans.

1945 – 1972

The Potsdam conference defined the borders for communist Poland, which were very different from the pre-1939 ones. It received the so-called Regained Territories from the former Third Reich with the aforementioned motorway sections (some of them with first carriageway only). Most of the motorway bridges were destroyed by the warfare, but only a few were repaired or rebuilt in the first post-war years. The bridge over Ina river was reconstructed in 1972, and those on S22 only between 1996 and 2003.

Apart from the bridges, almost all the motorways were left in the same condition as they were in 1945 until the mid-1990s. The only road left from Nazi times that was completed by the People's Republic of Poland was a one-carriageway small section between Łęczyca and Lisowo (15 km of what is now DW142), which was built on the previous works of Nazis.

Plans

At the post-war year there were very ambitious plans to make a motorway network for the whole Poland. For example, engineer Eugeniusz Buszma has published his propositions to the network in the magazine "Drogowiec" (1946, issue 1):

  1. East – West (SłubiceWarsawBiałystok) – 680 km
  2. North – South (Gdynia – Warsaw – Balkans) – 650 km
  3. Silesia – Baltic I (GdańskŁódźKatowice) – 460 km
  4. Pomeranian (Gdańsk – Szczecin) – 280 km
  5. Silesian (Wrocław – Katowice – Kraków) – 190 km
  6. Mazurian (Kaliningrad – ElblągMalbork) – 20 km
  7. Silesia – Baltic II (Bydgoszcz – Wrocław) – 260 km
  8. Łódź – Wrocław – (Prague) – 310 km
  9. Katowice – (Vienna) – 60 km
  10. Poznań – Szczecin – 200 km
  11. RadomLublin – (Lviv) – 220 km

In total, the mileage, according to the proposal, would total more than .

After the addition of the sections built by the Third Reich the total network length had to be approx. 3700 km. In 1963 the Motorization Council at the Council of Ministers had presented the similar plan plus the motorways: Warsaw-Kraków-Zakopane, Kraków-Przemyśl, Warsaw-Bydgoszcz-Koszalin, Poznań-Koszalin i Warsaw-Terespol (approx. 1250 km).

Despite announcing such pompous plans, no motorway was opened in the meantime.

In the 1970s

Only in the 1970s did any works start.

Plans

In 1972 it was planned to build:

The plans were expanded in 1976 by the following sections:

In 1973 – 1976, "Gierkówka" dual carriageway from Warsaw to Katowice was built. Originally planned as a motorway, it was in the end constructed by adding another carriageway to the existing road, hence going through many villages and crossing with local roads. The part from Piotrków Trybunalski to Częstochowa (78 km) was constructed on a new route in a motorway alignment, but nonetheless the majority of the crossings between the highway and the other roads were constructed as one-level intersections with no viaducts or overpasses.

Highway sections opened in the 1970s
SignageSectionLengthStart of constructionOpening
Piotrków Trybunalski – Częstochowa
substandard (multiple at-grade intersections), constructed on motorway alignment, not signed as a highway
Tri-city bypass (eastern carriageway)
substandard (two at-grade intersections, then reconstructed when adding a second carriageway in the 1980s)
Szczecin-Rzęśnica (end of post-German A6 motorway) – Goleniów
substandard (two at-grade intersections)
Total
of which single carriageway

In the 1980s

Near the end of the 1970s the first construction of motorways started and continued to the next decade. The roads opened in the 1980s were the first motorways and expressways which generally meet the contemporary standards (at least with respect to their more important attributes), although in multiple cases the poor quality of their construction forced major renovations to be performed as soon as within the first 20 years of operation.[39] [40]

The major routes planned as motorways were A1, A2 and A4, while other main routes were planned as expressways. The implementation of these plans, however, came at a very slow pace: throughout the 1980s, only an average of of highways in the whole country were being opened per year.


average: 20.5 km / year
SignageSectionLengthStart of constructionOpeningNotes
Reconstructed 2019 – 2021
Września - KoninRenovated 2002 – 2003
Jaworzno - Kraków (Balice I)Renovated 1999 – 2000
Kraków bypass
Dąbrowa Górnicza - Tychy
Tri-city bypass (to Straszyn)Second carriageway
Kielce bypassFirst carriageway
Katowice - SosnowiecFirst completely done expressway
Total of which single carriageway

In the 1990s

In the III Republic of Poland, planned S3 was promoted to motorway A3 (the decision was later reversed) and a plan was introduced (also later reversed) of constructing motorway A8 Łódź – Wrocław – Bolków (now S8/A8/S5). Szczecin bypass (A6) and section Olszyna – Krzywa (then named A12, now A4/A18) were promoted to motorways, even though at that time the majority of their lengths was in bad shape, laid with the original concrete surface from the 1930s with no significant works having been performed on any of them throughout the whole communist period.


average: 15 km / year
SignageSectionLengthStart of constructionOpeningNotes
Katowice - Jaworzno (Mysłowice - Jaworzno)Northern carriageway was opened on
(in Katowice)?
Kraków bypass (section Tyniec - ul.Kąpielowa) (to Skawina)
A4 had a crossroad with ul. Kąpielowa till 2002, when the bridge was built over it.
- Zgorzelec
Krzyżowa - Krzywa?Renovated
- PodjuchyRenovated
Olszyna - Królów?Northern carriageway added
Golnice - KrzyżowaRenovated both carriageways
- Cieszyn-East
Sulechów - Zielona GóraWestern carriageway only
Świecie bypassSingle carriageway; dual carriageway near the interchanges
Miłomłyn bypassEastern carriageway only
Radzymin bypass
Total of which reconstructed, single carriageway

In the 2000s

As of the beginning of 2000, the vast majority of national and international traffic routes were served by regular national roads with at-grade intersections and pedestrian crossings, most of them leading through the centres of cities, towns and villages, and most of them single carriageway. Only the following number of highways was present:

Before Poland received the EU membership

At the beginning of the 21st century, the tempo of highway construction started to increase. The main focus was on the west-east motorways A4 and A2. In 2002, a long-awaited renovation of the A4 from Krzywa to Wrocław (93 km) has started, which included laying new high quality surface in place of the Nazi German concrete slabs, reconstruction of all the pre-WWII bridges on the motorway and renovation of the viaducts above the motorway.

This is also the period when Poland started introducing motorway tolls, first in 2000 for the A4 section between Mysłowice and Kraków.


average: 57 km / year
SignageSectionLengthStart of constructionOpeningNotes
Poznań Komorniki - Września
Wrocław (Bielany) - (to Brzeg)
(to Opole-East)
(to Kleszczów)
Chorzów - Katowice Mikołowska
Kraków bypass (section ul.Kąpielowa - Wieliczka)
Śmigiel bypass?First carriageway
Straszyn - RusocinSecond carriageway
Białobrzegi bypass
Ostrów Mazowiecka bypass
Total of which single carriageway

Poland in European Union

1 May 2004 was a crucial day for the history of motorway construction and that is when the length of highway constructions increased the most. One of the major advantages of signing the European Union access document was that Poland could get access to large funds for co-financing the construction of new roads and upgrades of the existing road infrastructure.

These years, the existing scattered pieces of highways began to converge into the basis of the future network:

A large number of expressway bypasses of towns were also constructed at this time. On many of them, only one carriageway was built, with the allocated space prepared for easy construction of the second carriageway later.


average: 151 km / year
SignageSectionLengthStart of constructionOpeningNotes
Sośnica - Żory
2007
Nowy Tomyśl - Poznań Komorniki
Konin - Łódź (Stryków)
Krzywa - Wrocław (Bielany)–2006
(in sections)
Renovated both carriageways
Gliwice (Sośnica) - Chorzów Batory
Gliwice bypass (Kleszczów - Sośnica)
Zgorzelec - Krzyżowa
Wieliczka - Targowisko
Szczecin Klucz - Szczecin KijewoRenovated both carriageways
Olszyna - GolniceConstructed the northern carriageway alongside the pre-WWII southern carriageway
- Zwardoń - Milówka2002 - 20072004 - 2010
then signed S69
Żywiec - Przybędza20052007
Pyrzowice airport - Podwarpie20052006Single carriageway
SzczecinGorzów Wielkopolski
Single carriageway
Międzyrzecz bypass
Nowa Sól bypass
Szubin bypassSingle carriageway
Słupsk bypassSingle carriageway; dual carriageway near the interchanges
Jędrzejów bypassPartially (2.7 km) single carriageway
Nowy Dwór Gdański bypass
Elbląg bypass
Grójec bypass
Białobrzegi - Jedlińsk
Myślenice - Lubień
Kielce bypass (northern part)
Płońsk bypass
SkurówBiałobrzegi
Kraków eastern bypass (first fragment)
Oleśnica bypass
Wyszków bypass
Wyszków - Radzymin
Wrocław - Kobierzyce
Toruń bypass (fragment)Single carriageway
Kobylanka bypassPartially (7 km) single carriageway
Stargard bypass
Bydgoszcz bypass (fragment)
Wyrzysk bypassSingle carriageway
Poznań - Kórnik
Ostrów Wlkp. bypass (northern part)Single carriageway
Piaski bypass
Puławy bypassPartially (8.7 km) single carriageway
BarczewoBiskupiecSingle carriageway
Garwolin bypass
Międzyrzec Podlaski bypassSingle carriageway
Elbląg - Grzechotki / Kaliningrad OblastSingle carriageway; constructed in place of a partially destroyed motorway from the 1930s
Cieszyn - Bielsko-Biała (Komorowice)2002 - 20052005 - 2007
Then signed S1
Total of which single carriageway, reconstructed

2011 – 2015

In the five years from 2011 to 2015, 1563 kilometers of motorways and expressways got opened – about as much as in the whole prior history of highway construction combined. The main focus was on developing connections between Poland's largest cities, especially those serving as host venues of UEFA Euro 2012, as well as on extending A4 towards Ukraine.

YearLengthNotes
2011
2012Of which were opened before Euro 2012 championship
2013
2014
2015
TotalOf which first carriageway, second carriageway

The sections opened in 2011 – 2015 belonged to the following highways:

2016 – 2020

After the peak of investments before Euro 2012, very few new contracts for road construction have been signed in 2012 and 2013. This resulted in a small number of sections getting opened in 2015 and 2016, large share of which were the last delayed fragments originally scheduled for a Euro 2012 opening. In particular:

Since 2014, the number of signed contracts has risen again, resulting in the number of road openings having risen again since 2017.

YearLengthNotes
2016
2017
2018
2019
2020
TotalOf which first carriageway, second carriageway

The sections opened in 2016 – 2020 belonged to the following highways:

2021 – present

The high tempo of highway development continued in the 2020s. The main focus was on construction of new highways in the less populated eastern Poland, including the international routes Via Carpatia and Via Baltica.

YearLengthNotes
2021
2022
2023
2024Sections already opened, ongoing constructions with scheduled completion date in 2024[41]
2025Ongoing constructions with scheduled completion date in 2025
TotalOf which first carriageway, second carriageway

The sections opened, or planned to get opened, in 2021 – 2025 belong to the following highways:

Total length of highways by year

YearLength of motorways and expressways (end of the year)
1936 (then Nazi Germany) 92 km
1937 (then Nazi Germany) 104 km and 38 km first carriageway
1938–1945 (then Nazi Germany) 133 km and 135 km first carriageway (further below not considered as a motorway until addition of the second carriageway)
1939–1945 (Poland) 28km (today not considered as a highway)
1945–1976 133 km
1977 169 km
1978 169 km
1979 190 km
1980 190 km
1981 190 km
1982 190 km
1983 255 km
1984 278 km
1985 321 km
1986 327 km
1987 327 km
1988 348 km
1989 366 km
1990 381 km
1991 399 km
1992 399 km
1993 403 km
1994 405 km
1995 440 km
1996 453 km
1997 456 km
1998 490 km
1999 502 km
2000 592 km
2001 630 km
2002 639 km
2003 727 km
2004 781 km
2005 848 km
2006 1013 km
2007 1083 km
2008 1282 km
2009 1454 km
2010 1560 km
2011 1865 km
2012 2495 km
2013 2805 km
2014 3100 km
2015 3131 km
2016 3252 km
2017 3510 km
2018 3811 km
2019 4214 km
2020 4337 km
2021 4690 km
2022 4933 km
2023 5116 km
2024 5258 km (forecast)
2025 5776 km (forecast)
2026 6006 km (forecast)
2027 6180 km (forecast)
2028 approx. 6500 km (plans)
2030 approx. 7000 km (plans)
2033 approx. 8000 km (plans)
After 2035 approx. 8200 km – full network (plans)

See also

External links

Notes and References

  1. Here and in the following figures, construction of 1st or 2nd carriageway is accounted as half-length for consistency of the summed results. Sections constructed by Nazi Germany are accounted for the dates of their reconstruction to modern highways.
  2. https://www.gov.pl/web/gddkia/mapa-stanu-budowy-drog4, more details: History
  3. Web site: Autostrady :: Generalna Dyrekcja Dróg Krajowych i Autostrad - Strona Główna. www.gddkia.gov.pl.
  4. Including design–build contracts; see the List of motorways and expressways for details on the phases of construction and design.
  5. The definitions and technical parameters of highways are defined in the Public Roads Act of 21 March 1985 (with later amendments): Web site: Ustawa z dnia 21 marca 1985 r. o drogach publicznych. prawo.sejm.gov.pl. and the ministry ordinance of 2 March 1999 (with later amendments).Web site: Obwieszczenie Ministra Infrastruktury i Budownictwa z dnia 23 grudnia 2015 r. w sprawie ogłoszenia jednolitego tekstu rozporządzenia Ministra Transportu i Gospodarki Morskiej w sprawie warunków technicznych, jakim powinny odpowiadać drogi publiczne i ich usytuowanie. prawo.sejm.gov.pl.
  6. Web site: S3 Miękowo - Rzęśnica :: Generalna Dyrekcja Dróg Krajowych i Autostrad - Serwis informacyjny. www.gddkia.gov.pl.
  7. Web site: Miekowo Rześnica. Miekowo Rześnica.
  8. Web site: Generalna Dyrekcja Dróg Krajowych i Autostrad - Generalna Dyrekcja Dróg Krajowych i Autostrad - Portal Gov.pl. Generalna Dyrekcja Dróg Krajowych i Autostrad.
  9. Web site: Rozporządzenie Rady Ministrów z dnia 15 maja 2004 r. w sprawie sieci autostrad i dróg ekspresowych . prawo.sejm.gov.pl.
  10. Web site: Rozporządzenie Rady Ministrów z dnia 20 października 2009 r. zmieniające rozporząsdzenie w sprawie sieci autostrad i dróg ekspresowych. prawo.sejm.gov.pl.
  11. Web site: Dziennik Ustaw 2019 r. poz. 1819. www.dziennikustaw.gov.pl.
  12. to Ostróda in 2015 and to Bolków in 2019
  13. to Kłodzko in 2019
  14. to Wołomin in 2015
  15. Web site: Zmiany w rozporządzeniu w sprawie sieci autostrad i dróg ekspresowych - Ministerstwo Infrastruktury i Budownictwa. mib.gov.pl. 2016-07-05.
  16. Web site: Zestawienie realizacji autostrad i dróg ekspresowych w Polsce . 2019-12-26.
  17. Web site: Mapa budowy dróg ekspresowych i autostrad . 2019-12-26.
  18. Web site: Map of construction of Polish highways - SISKOM & SSC . ssc.siskom.waw.pl . 2019-12-26.
  19. Web site: Map of construction of Polish highways - GDDKiA . gov.pl . 2021-07-31.
  20. Web site: Rządowy Plan Budowy Dróg do 2030 roku. www.gov.pl.
  21. Web site: List of ongoing road contracts signed by GDDKiA.
  22. https://orka.sejm.gov.pl/zapisy10.nsf/0/30E0DE27BF736B55C1258B04004BE804/%24File/0036010.pdf
  23. Web site: Toll-free travel on motorway sections managed by GDDKiA (A2 Konin-Stryków and A4 Wrocław-Sośnica) for light vehicles from 1 July 2023. . 2023-07-01 . e-TOLL . pl.
  24. Web site: Cała autostrada A1 bezpłatna dla samochodów osobowych i motocykli - Ministerstwo Infrastruktury - Portal Gov.pl .
  25. Web site: Via Toll.
  26. Web site: Autopay - Comfortable automatic payments - Autopay.
  27. Web site: Koniec stania przy bramkach. Autopay na państwowych autostradach od 1 grudnia - Autopay.
  28. Web site: Types of vehicles for which toll is collected .
  29. Web site: Archived copy . 2020-01-26 . 2021-01-27 . https://web.archive.org/web/20210127170718/https://www.gddkia.gov.pl/userfiles/articles/g/GENERALNY_POMIAR_RUCHU_2000/0.1.3.3_Raport_GPR_2000.pdf . dead .
  30. https://www.gov.pl/attachment/f49c90ff-eb1c-469c-8ab4-04bf91ac7db0
  31. The measurement analysis defines a regular single-carriageway road as overburdened if recorded average annual traffic exceeds 15'000 vehicles per day, see Web site: Archived copy . 2020-01-26 . 2021-01-27 . https://web.archive.org/web/20210127173253/https://www.gddkia.gov.pl/userfiles/articles/g/generalny-pomiar-ruchu-w-2015_15598/SYNTEZA/Synteza_GPR2015.pdf . dead.
  32. https://www.archiwum.gddkia.gov.pl/userfiles/articles/g/GENERALNY_POMIAR_RUCHU_2010/0.1.1.5_Synteza_GPR_2010.pdf
  33. Web site: Generalna Dyrekcja Dróg Krajowych i Autostrad - Generalna Dyrekcja Dróg Krajowych i Autostrad - Portal Gov.pl.
  34. Web site: Generalny Pomiar Ruchu 2020/2021 - Generalna Dyrekcja Dróg Krajowych i Autostrad - Portal Gov.pl.
  35. Web site: W kwietniu przetarg w sprawie drogi między Ruczajem a Skawiną. Co z tramwajem? . 25 July 2023 .
  36. Web site: Umowa na analizę dla rozbudowy A4 Wrocław – Krzyżowa podpisana! :: Generalna Dyrekcja Dróg Krajowych i Autostrad - Serwis informacyjny. www.gddkia.gov.pl.
  37. Web site: A6 Szczecin Dąbie - Rzęśnica :: Generalna Dyrekcja Dróg Krajowych i Autostrad - Serwis informacyjny. www.gddkia.gov.pl.
  38. Web site: Zamów domenę. domains24.pl.
  39. Web site: Historia - Autostrada Wielkopolska SA. 31 December 2021. 2 July 2019. https://web.archive.org/web/20190702112310/https://www.autostrada-a2.pl/corporate/about/history/. dead.
  40. Web site: Historia przedsięwzięcia. Stalexport Autostrada Małopolska S.A..
  41. Web site: Budowa dróg – sztafeta rozłożona na lata - Generalna Dyrekcja Dróg Krajowych i Autostrad - Portal Gov.pl .