Energy in Uganda explained

Burning of renewable resources provides approximately 90 percent of the energy in Uganda,[1] though the government is attempting to become energy self-sufficient.[2] While much of the hydroelectric potential of the country is untapped, the government decision to expedite the creation of domestic petroleum capacity coupled with the discovery of large petroleum reserves holds the promise of a significant change in Uganda's status as an energy-importing country.[3]

Background

In the 1980s, charcoal and fuel wood met more than 95 percent of Uganda's energy needs.[4] In 2005 and 2006, low water levels of Lake Victoria, the main source of the country's electricity generation potential, led to a generation shortage and an energy crisis.[5] [6] As a result, the country experienced frequent and prolonged blackouts.[4] [5] [7] As of June 2016, according to the Uganda Bureau of Statistics, about twenty percent of Ugandans had access to electricity.[8] As of February 2015 and according to the Uganda Electricity Regulatory Authority, Uganda's installed electricity capacity was 810 megawatts, with peak demand of 509.4 megawatts so that "the incidence of load shedding due to shortage in supply is now close to zero."[9], according to Irene Muloni, the Uganda Minister of Energy, the country's generation capacity had increased to 950 megawatts.[10] Uganda expects to have a generating capacity of at least 1,900 megawatts by the end of 2019, as forecast by the Uganda Ministry of Energy and Mineral Development.[10] In March 2018, the World Bank Group estimated that about 26 percent of Uganda's population had access to grid-electricity at that time.[11] In March 2019, the United States Department of Commerce estimated that 55 percent of Uganda's urban population and about 10 percent of the country's rural population has access to grid electricity then.[12] As of April 2019, generation capacity was 1,167 megawatts, with peak demand of about 625 megawatts and approximately 25 percent national electrification rate. At that time, an estimated 1,000 new customers were requesting grid power connection on a daily basis, with over 1.3 million existing Umeme connections.[13] As of October 2019, the Uganda Ministry of Energy and Mineral Development estimated that 28 percent of Uganda's population had access to electricity.[14]  In September 2019, Uganda signed an Inter-Governmental Agreement (IGA) with Russia to build capacity to exploit nuclear technology for energy, medical and other peaceful purposes.[15]

As of March 2022, the national electricity sources were as illustrated in the table below:[16]

Sources of Electricity in Uganda as of March 2022! Rank !!Source!!Quantity (MW) !!Percentage of Total
1 Hydroelectricity1,072.9 79.7
2 Bagasse Co-generation 111.7 8.2
3 101.1 7.5
4 60.9 4.6
5 Wind 0 0.0
6 Geothermal 0 0.0
7 Nuclear 0 0.0
8 Other 0 0.0
Total1,346.6 100.0

In December 2023, PML Daily, a Ugandan online publication reported that at that time, the national generation capacity was 1,346 megawatts, with a national electrification rate of 42 percent, which was expanding at an average rate of 3 percent annually.[17] The national peak demand for February 2023 was reported as 863 MW.[18] As of December 2023, national generation capacity was approximately 1,350 megawatts, with maximum demand of 988 MW, of which 868 MW was national consumption and 120 MW was export demand.[19]

Greenhouse gas targets

Uganda aims to lower its greenhouse gas emissions by enacting measures in its energy, forestry and wetland sectors.[20] Uganda's greenhouse gas emissions per capita is 1.39 tons carbon dioxide, one of the lowest in the world. The country aims to reduce its carbon emissions by 22 percent by 2030.

Hydroelectricity

The country's hydropower potential is an estimated 2,200 megawatts.[21]

Poor maintenance during the politically unstable 1980s resulted in a drop in production at the Owen Falls Dam (now Nalubaale Power Station), at the mouth of the White Nile, from 635.5 million kilowatt-hours in 1986 to 609.9 million kilowatt-hours in 1987, with six of ten generators broken by the end of 1988.[22] The 200 megawatt Kiira Hydroelectric Power Station, built adjacent to the Nalubaale Power Station, raised total production capacity to 380 megawatts.[23]

Between 2007 and 2012, the 250 megawatt Bujagali Hydroelectric Power Station was constructed as a public-private project, at a cost of approximately US$862 million. The consortium that owns the station includes the Aga Khan Fund for Economic Development, SN Power (a subsidiary of the Norwegian Investment Fund for Developing Countries), and the government of Uganda. Bujagali Energy Limited is a special-vehicle company created to run the power station on behalf of the shareholders.[24]

In October 2013, construction of the 183 megawatt Isimba Power Station began, approximately 40km (30miles) downstream of Bujagali, at a budgeted cost of approximately US$590 million, as a public enterprise with funding from the Export-Import Bank of China. Commissioning was planned during the second half of 2018.[25] [26] However, construction was completed in January 2019,[27] and commercial operations began in March 2019.[28]

Also in 2013, work on the 600 megawatt Karuma Power Station commenced at a budgeted cost of about US$2 billion, including US$250 million to build the high-voltage transmission lines to evacuate the generated power. Completion was planned for late 2018.[29] However, a more realistic completion date is in late 2019 or early 2020.[30]

, about six operational mini-hydropower plants are connected to the national electricity grid, supplying about 65 megawatts. These include Nyagak I (3.5 megawatts), Kabalega (9 megawatts), Kanungu (6.6 megawatts), Bugoye (13 megawatts), Mubuku I (5 megawatts), Mubuku III (10 megawatts), and Mpanga (18 megawatts).[31]

Thermal power

Two heavy fuel oil thermal power stations exist in the country.

Namanve Power Station is a 50 megawatt plant formerly owned by Jacobsen Electricity Company (Uganda) Limited, a wholly owned subsidiary of Jacobsen Elektro, an independent Norwegian power production company. The plant cost US$92 million (€66 million) to build in 2008.[32] The power station reverted to Uganda Electricity Generation Company Limited in February 2022.[33] [34]

Tororo Power Station is an 89 megawatt heavy fuel-oil powered plant owned by Electro-Maxx Limited, a Ugandan company and a subsidiary of the Simba Group of Companies, owned by Ugandan industrialist Patrick Bitature. This plant is licensed to sell up to 50 megawatts to the national electricity grid.[35]

Namanve and Tororo are used as stand-by power sources to avoid load-shedding when hydropower generation fails to meet demand.[36]

Five sugar manufacturers in Uganda have total cogeneration capacity of about 110 megawatts, of which about 50 percent is available for sale to the national grid. The cogeneration power plants and their generation capacities include Kakira Power Station (52 megawatts), Kinyara Power Station (40 megawatts), Lugazi Power Station (14 megawatts), Kaliro Power Station (12 megawatts) and Mayuge Thermal Power Station (1.6 megawatts).[37] [38]

Oil and natural gas

Uganda is highly vulnerable to oil price shocks as it imports almost all of its of oil (2013 figure). The oil comes through the Kenyan port of Mombasa.[39]

The governments of Kenya, Uganda, and Rwanda are jointly developing the Kenya–Uganda–Rwanda Petroleum Products Pipeline to carry refined petroleum products from Mombasa through Nairobi to Eldoret, all in Kenya. From Eldoret, the pipeline will continue through Malaba to Kampala in Uganda, continuing on to Kigali in Rwanda. The feasibility study for the Eldoret to Kampala pipeline extension was awarded to an international firm in 1997. The study was completed in 1998 and the report submitted the following year. The separate feasibility study for the Kampala to Kigali extension was awarded to the East African Community in September 2011. The governments of Kenya, Uganda, and Rwanda accepted the findings of the studies. The construction contract was initially awarded, in 2007, to Tamoil, a company owned by the Government of Libya. That contract was voided in 2012 after the company failed to implement the project., fourteen companies had submitted bids to construct the pipeline extension from Kenya to Rwanda. Construction was expected to begin in 2014, with a 32-month construction time-frame. Commissioning was expected in 2016.[40]

In 2006, Uganda confirmed the existence of commercially viable petroleum reserves in the Western Rift Valley around Lake Albert. In June 2006, Hardman Resources of Australia discovered oil sands at Waranga 1, Waranga 2, and Mputa. President Yoweri Museveni announced that he expected production of 6000oilbbl/d to 10000oilbbl/d by 2009.[41]

In July 2007, Heritage Oil, one of several companies prospecting around Lake Albert, raised its estimate for the Kingfisher well (block 3A) in Hoima District, Bunyoro sub-region, stating that they thought it was bigger than 600Moilbbl of crude. Heritage's partner, London-based Tullow Oil, which had bought Hardman Resources, was more guarded, but stated their confidence that the Albertine Basin as a whole contained over one billion barrels. The Kingfisher-1 well flowed 13893oilbbl/d of 30-32 API oil.[42]

This news came on the heels of Tullow's 11 July 2007 report that the Nzizi 2 appraisal well confirmed the presence of 14Mcuft per day of natural gas. Heritage in a report to its partners talked of Ugandan reserves of 2.4Goilbbl worth $7 billion as the "most exciting new play in sub-Saharan Africa in the past decade."[42] However, development will require a 750miles pipeline to the coast, which will need $80 oil to justify.[43] Relations between Uganda and the neighboring Democratic Republic of the Congo (DRC) have been tense since the discovery of oil, as both countries seek to clarify the border delineation on the lake in their favor, in particular the ownership of small Rukwanzi Island. Ugandan foreign minister Sam Kutesa made an emergency visit to Kinshasa in an attempt to smooth tensions.[44]

The Economist magazine, noting that the DRC has assigned exploration blocks on its side of the border, proposed that the situation should sort itself amicably: Uganda needs a stable and secure border in order to attract foreign investment developing the oil reserves, while the cost of transporting the oil to the DRC's sole port at Matadi is so prohibitive that the Congolese government is nearly obliged to seek pipeline access through Uganda.[44]

After an initial period of disagreement between the Government of Uganda and the petroleum exploration companies, the two sides agreed in April 2013 to simultaneously build a crude oil pipeline to the Kenyan coast (Uganda–Kenya Crude Oil Pipeline) and an oil refinery in Uganda (Uganda Oil Refinery).[45]

In February 2015, the Ugandan government selected the consortium led by Russia's RT Global Resources as the winning bidder, to construct the refinery. The government was expected to begin in-depth negotiations with the winning bidder for a binding agreement to construct the refinery. The negotiations were expected to last about 60 days. If the parties failed to agree on terms, the government planned to negotiate with the losing bidder, the consortium led by SK Energy of South Korea, to construct the refinery.[46] When those talks broke down in July 2016,[47] Uganda began talks with the reserve bidder, the consortium led by SK Engineering & Construction of South Korea.[48]

In August 2017, negotiations with the consortium led by SK Engineering & Construction also broke down.[49] Negotiations were then started with a new consortium led by Guangzhou Dongsong Energy Group, a Chinese company. Those talks collapsed in June 2017 when CPECC, the main contractor in the consortium, pulled out of the talks.[50]

In August 2017, Albertine Graben Refinery Consortium, a new consortium led by General Electric (GE) of the United States agreed to build the US$4 billion refinery. GE is to own 60 percent, while the government of Uganda and other investors take up the remaining 40 percent. Total SA, has pledged to take up a 10 percent stake in the refinery.[49]

In December 2017, Irene Muloni, Uganda's Energy Minister announced that the country planned to join the Organization of the Petroleum Exporting Countries (OPEC), by 2020, when first oil is expected.[51]

Solar energy

The solar energy resource potential is an estimated 5.1 kilowatt-hours per square meter.[52]

To diversify the national energy pool, the Electricity Regulatory Authority in December 2014 licensed two solar power stations, each with capacity to generate 10 megawatts. The stations, Tororo Solar Power Station and Soroti Solar Power Station, were expected to come online no later than December 2015.[53] In December 2016, Soroti Solar Power Station was completed and connected to the national grid.[54] Tororo Solar Power Station was also brought online in October 2017.[55] In January 2019, Kabulasoke Solar Power Station, a 20 megawatt development by a private IPP was commissioned and connected to the national grid.[56] Mayuge Solar Power Station, another 10 megawatts IPP project, that cost USh 41 billion (approx. US$11.3 million), to build, came online in June 2019, bringing total grid-connected solar energy to 50 megawatts nationally.[57]

Power sales to neighboring countries

As of May 2024, Kenya was in discussions with Uganda to establish a power purchase agreement, where Uganda would commit to sell electric power to her eastern neighbor at a fixed price, on a long-term basis. At that time, Uganda had about 350 MW in excess installed generation, with another 600 MW (Karuma Hydroelectric Power Station) expected to come online in the next 6 months.[58]

See also

External links

Notes and References

  1. Web site: 20MW of solar energy to be added to national grid. Samuel Sanya. Alfred Wandera. 31 March 2015. 25 November 2015. Kampala. New Vision.
  2. Web site: 14 May 2015 . Uganda's Renewable Energy Investment Guide 2012 . 2012 . Irene . Muloni . Embassy of The Netherlands In Uganda . 4 March 2016 . https://web.archive.org/web/20160304120436/http://uganda.nlembassy.org/binaries/content/assets/postenweb/u/uganda/embassy-of-the-kingdom-of-the-netherlands-in-kampala/import/development-cooperation/renewable-energy-investment-guide.pdf . dead .
  3. Web site: The Oil for Development Programme In Uganda . Julie Magnihild Grøtnæs . Trond Kvarsvik . Ingvild Bergskaug . Svein Erik Heglund . 2 July 2014 . 31 May 2015 . Norwegian Agency for Development Cooperation.
  4. Encyclopedia: Energy Profile of Uganda . 15 July 2009 . Peter . Saundry . 31 May 2015 . dead . https://web.archive.org/web/20150609043403/http://www.eoearth.org/view/article/152538/ . 9 June 2015 . The Encyclopedia of Earth.
  5. Web site: 9 October 2012 . Strategic plan to increase power supply pays dividends . 1 June 2015 . Kasita . . Kampala.
  6. Web site: 26 September 2005 . RWI. USDA: Low water levels observed on Lake Victoria . Reliefweb.int (RWI) . 1 June 2015.
  7. Web site: 1 June 2015 . . 14 October 2011 . Uganda's power outages spark scrutiny, criticism . Ioannis . Gatsiounis.
  8. Web site: 16 June 2016 . German firm avails Shs80b for new power connections . Kampala . 16 June 2016 . Nelson . Wesonga . . 12 January 2017 . https://web.archive.org/web/20170112082555/http://www.monitor.co.ug/Business/Markets/German-firm-avails-Shs80b-power-connections/-/688606/3251206/-/e7qhe7z/-/index.html . dead .
  9. Web site: February 2015 . 12 August 2015 . Investing in the electricity sector in Uganda . Norton Rose Fulbright (NRFC) . NRFC . 15 August 2015 . https://web.archive.org/web/20150815065220/http://www.nortonrosefulbright.com/knowledge/publications/126133/investing-in-the-electricity-sector-in-uganda . dead .
  10. Web site: 13 March 2018 . 13 September 2017 . Cecilia Okoth . Home National Uganda to double electricity capacity by 2019 . . Kampala.
  11. 2 June 2018 . 8 March 2018 . IFC and MIGA Boards Support Bujagali Refinancing Package to Reduce Ugandan Electricity Costs . Washington, DC . . 23 February 2020 . https://web.archive.org/web/20200223205930/https://ifcextapps.ifc.org/ifcext/pressroom/IFCPressRoom.nsf/0/7C6FB1872C371C118525824A007D3E80 . dead .
  12. Web site: Uganda Country Commercial Guide: Energy . 30 March 2019 . . 29 June 2019 . Washington, DC.
  13. Web site: . 9 April 2019 . 9 April 2019 . Barriers to free electricity connections . Ismail Musa Ladu . Kampala.
  14. Web site: Government Drafts Road Map For Universal Access To Clean Energy . . 24 October 2019 . 24 October 2019 . The Independent . Kampala.
  15. 2008. Uganda planning to build nuclear power plants. Physics Today. 10.1063/pt.5.022166. 1945-0699.
  16. Web site: Uganda Electricity Installed Capacity As of March 2022 . . 16 March 2022 . Electricity Regulatory Authority . 27 April 2022 . Kampala, Uganda.
  17. Web site: PML Daily . ATIDI partners with Dubai-based AMEA Power on 20 MW Ituka West Nile Uganda Limited Solar Project . 13 December 2023 . Nelson, Mandela . 16 December 2023 . Kampala, Uganda.
  18. Web site: ERA lowers electricity end-user tariffs . . 12 April 2023 . Geofrey Serugo . 10 April 2024 . Kampala, Uganda.
  19. Web site: 6 May 2024 . Uganda Electricity Maximum Demand . Electricity Regulatory Authority (ERA) . ERA . 22 May 2024 . Kampala, Uganda.
  20. Web site: Nandelenga. Rachel. 2015-10-16 . Uganda Targets 22% emission cuts to achieve low-carbon growth . UNDP in Uganda. en . 2020-07-05.
  21. Web site: June 2018. Uganda International Hydropower Association. 2020-07-05. International Hydropower Association.
  22. Web site: Uganda Energy During the 1980s . U.S. Library of Congress. 14 May 2015. 1989. Countrystudies.us.
  23. Web site: 14 May 2015 . UEGCL . Profile of Kiira Hydroelectric Power Station . Uganda Electricity Generation Company Limited (UEGCL) . dead . https://web.archive.org/web/20150523012001/http://www.uegcl.com/kiira-Power.html . 23 May 2015 .
  24. Web site: 24 August 2018 . Govt earns Shs300 billion from Bujagali buyout deal . . 5 January 2020 . Christine Kasemiire . Kampala.
  25. Web site: Uganda Kicks Off Construction of Isimba Plant . 5 October 2013 . 14 May 2015 . Joint Report . . Nairobi . 25 July 2015 . https://web.archive.org/web/20150725014118/http://www.theeastafrican.co.ke/business/Uganda-kicks-off-construction-of-Isimba-plant-/-/2560/2019694/-/afn4o5z/-/index.html . dead .
  26. Web site: Parliament Okays UShs1.4 Trillion Loan for Isimba Hydropower Deal . Yasiin Mugerwa . Nelson Wesonga . . Kampala . 14 May 2015. 15 March 2015.
  27. Web site: Uganda: CWE Commissions 183.2 MW Isimba Hydroelectric Dam . Afrik21 . 1 April 2019 . 21 March 2019 . Jean Marie Takouleu . Paris, France.
  28. Web site: . Uganda adds 183MW to national grid, but will consumers gain? . 21 March 2019 . 1 April 2019 . Julius . Barigaba . Nairobi.
  29. Web site: Parliament Okays US$1.435 Billion Loan for Karuma. 14 May 2015 . 25 March 2015 . Nelson . Wesonga . . Kampala.
  30. Web site: . Karuma: Government to incur more costs as completion delays . 8 December 2018 . 1 April 2019 . Tobbias Jolly Owiny . Kampala.
  31. Web site: Kamwenge Gets USh60 Billion Power Project . 15 May 2015 . 14 February 2011 . Ronald . Kalyango . New Vision (Kampala) . dead . https://web.archive.org/web/20150522104648/http://www.newvision.co.ug/D/8/220/746561 . 22 May 2015 .
  32. Web site: . 6 November 2008 . Namanve plant reduces load-shedding . Sylvia Juuko . https://web.archive.org/web/20120914160503/http://www.newvision.co.ug/D/8/12/658314 . 11 August 2022 . 14 September 2012 . Archived from the original on 14 September 2012.
  33. Web site: Govt takes over Namanve Thermal Power plant . . 13 September 2021 . Stephen Otage . 11 August 2022 . Kampala, Uganda.
  34. Web site: . 24 February 2022 . Stephen Otage . Govt suggests it will not renew Eskom's contract . 11 August 2022 . Kampala, Uganda.
  35. Web site: 5 September 2017. Ministry of Energy and Mineral Development Celebrating the Annual Manifest Week, From 12th to 19th May, 2017 . Uganda Media Centre . Ministry of Energy and Mineral Development . Kampala. 12 May 2017 . dead . https://web.archive.org/web/20170518120728/http://mediacentre.go.ug/press-release/ministry-energy-and-mineral-development-celebrating-annual-manifesto-week-12th-19th . 2017-05-18. Ministry of Energy and Mineral Development (Uganda) .
  36. Web site: 22 January 2014. Uganda Radio Network. Heavy Fuel Electricity Could Return In 2014 As Demand Hits 12 Percent. 15 May 2015. Mark Keith. Muhumuza.
  37. Web site: 24 July 2015 . Kenya Joins Big Investors In Renewable Energy As East Africa Plays Catch-Up . Special Correspondent . . Nairobi . 24 July 2015 . 2 January 2020 . https://web.archive.org/web/20200102055808/https://www.theeastafrican.co.ke/news/East-Africa-an-emerging-renewable-energy-hub-/-/2558/2806036/-/item/3/-/y5h3frz/-/index.html . dead .
  38. Web site: 15 May 2015 . 30 May 2014 . ERA . Application for A License for The Establishment of A 11.9MW Bagasse Co-Generation Power Plant In Kaliro District . Electricity Regulatory Authority (ERA) . dead . https://web.archive.org/web/20140811121527/http://www.era.or.ug/index.php/2013-10-23-18-03-21/2013-10-23-18-12-48/notices/324-application-for-a-license-for-the-establishment-of-a-11-9mw-bagasse-co-generation-power-plant-in-kaliro-district . 11 August 2014 .
  39. Web site: The World Factbook: Uganda - Energy: Petroleum Products. 24 April 2015. 15 May 2015. CIA.
  40. Web site: Kenya-Uganda Oil Pipeline, Kenya . 2012 . Hydrocarbons-technology.com (HCTC) . 15 May 2015 . HCTC.
  41. Web site: Uganda Becomes Oil Producer . Afrol . 9 October 2006 . 15 May 2015 . Afrol.com.
  42. Web site: More oil, gas found . Edris Kisambira . . 16 July 2007 . dead . https://web.archive.org/web/20070928164531/http://www.busiweek.com/index.php?option=com_content&task=view&id=3720&Itemid=9 . 2007-09-28.
  43. Web site: Africa's Potential To Sate World's Oil Demand Dims. The Wall Street Journal. 22 October 2008 . 15 May 2015 . Fritsch . Peter.
  44. Web site: 15 May 2015. 23 August 2007. Congo And Uganda: Do You Want To Share Or To Fight? - The Question Posed By The Oil Find In Lake Albert. From Print Edition. The Economist.
  45. Web site: Uganda Reaches Deal On Refinery, Pipeline. 15 May 2015. Bariyo. Nicholas. The Wall Street Journal. 15 April 2013.
  46. Web site: Uganda Picks Russia's RT Global Resources To Build Refinery . 15 May 2015 . 17 February 2015. Biryabarema . Elias . . London.
  47. Web site: 1 December 2017 . . 1 July 2016 . Russian firm pulls out of Uganda's $4 billion oil refinery . Frederic . Musisi . Nairobi.
  48. Web site: 1 July 2016 . . 1 December 2017 . Biryabarema . Elias . Uganda switches bidder in talks over long-delayed $2.5 billion refinery. https://web.archive.org/web/20160702141320/http://af.reuters.com/article/investingNews/idAFKCN0ZH4XT . dead . 2 July 2016 .
  49. Web site: 7 August 2017. Uganda says agrees terms with consortium to build oil refinery . Biryabarema . Elias . . 1 December 2017.
  50. Web site: 7 August 2017 . Uganda: Chinese Quit Museveni's Refinery Deal. 31 July 2017 . . Haggai . Matsiko . Kampala.
  51. Web site: . Uganda requests to join OPEC . 4 December 2017 . 4 December 2017 . Kampala . Frederic . Musisi.
  52. Web site: Alhaji. 2020-03-29. Four solar and wind farms to be developed in Uganda. 2020-07-05. Construction Review Online. en-US.
  53. Web site: 15 May 2015 . 10 December 2014. Four Firms To Build 20 MW Solar Power Plants In Uganda . Biryabarema. Reuters.com. Elias.
  54. Web site: Uganda's first 10MW solar plant comes online . . 13 December 2016 . Asiimwe . Dicta . 1 May 2017 . Nairobi.
  55. Web site: 10 MW EU funded Tororo Solar Power Plant opens . 1 December 2017 . 16 October 2017 . EEEU . Eeas.Eupora.eu (EEEU).
  56. Web site: Solar power capacity to hit 50MW . 10 January 2019 . . 15 January 2019 . Sadat Mbogo . and Misairi Thembo Kahungu . Kampala.
  57. Web site: Mayuge gets Shs41b solar plant . . 8 June 2019 . Philip Wafula . 17 February 2020 . Kampala.
  58. Web site: . 24 May 2024 . Kenya seeks Uganda power purchase deal . John Mutua . 24 May 2024 . Nairobi, Kenya.