Line 5 Eglinton Explained

Line 5 Eglinton
Type:Light rail
System:Toronto subway
Status:Under construction
Locale:Toronto, Ontario, Canada
Start:
  • (phase 1, western)
  • (phase 2, western)
End: (eastern)
Stations:32
Planopen:
  • (previous target; central)[1]
  • 2030/ (west)[2]
Owner:Metrolinx
Operator:Toronto Transit Commission[3]
Depot:Eglinton Maintenance and Storage Facility
Stock:Flexity Freedom
Linelength:28km (17miles)
Electrification:[4]
Signalling:Bombardier Cityflo 650
Speed:
  • In tunnel: 80km/h
  • On surface: 60km/h
Map State:collapsed

Line 5 Eglinton (also known as the Eglinton Crosstown LRT or the Crosstown) is a light rail line that is under construction in Toronto, Ontario, Canada. Owned by Metrolinx and operated by the Toronto Transit Commission (TTC), the line will be part of the Toronto subway system as its fifth route. The line is being constructed in two phases, with two extensions approved by the Toronto government but not yet under construction.

The first phase of the 19km (12miles) line will include 25 stops along Eglinton Avenue, from Mount Dennis station mostly underground to Laird station, after which it will run predominantly at-grade within the street's median to Kennedy station, where it will connect underground with Line 2 Bloor–Danforth. This first phase has an estimated cost of ; the cost when the contract was awarded was pegged at $9.1billion, although the cost was originally estimated at $11billion. This phase is incomplete and has no scheduled opening date.

A second phase, a 9.2km (05.7miles) westward extension from Mount Dennis, will run mostly underground or elevated to Renforth station, with seven new stations. The second phase is expected to cost $4.7billion and to be completed by 2031. Construction of the westward extension to Renforth station began in July 2021.[5] [6] [7]

Two future extensions are planned: an eastern extension to the University of Toronto Scarborough[8] and a northwestern extension towards Toronto Pearson International Airport were approved by Toronto City Council in 2016.[9] The eastern extension was approved by the Toronto Transit Commission, but the extension was split into its own line in 2022.

Line 5 was conceived in 2007 during the administration of Toronto mayor David Miller as part of Transit City, a large-scale transit expansion plan. Construction of the first phase of the line began in 2011 and was originally expected to be completed in 2020, but the opening date has been revised several times.[10] Metrolinx expected the line to be substantially complete by September 2022 but then conceded it would not meet that date. After revising the opening date of the central section to 2023 and then 2024, and amid ongoing legal action against Crosslinx (the construction consortium), Metrolinx stated they believed there was no credible schedule to complete the project.[11] While the central section is estimated to be 97 percent complete, Metrolinx has chosen to refuse to provide an estimated completion date until three months before opening.[12] For budget purposes, the TTC made the assumption that Line 5 would open no earlier than September 2024.

History

See also: Eglinton West line and Transit City.

Background

The origins of Line 5 Eglinton can be traced to the 1985 Network 2011 plan conceived by the Metropolitan Toronto government as the TTC and Metro began to install the busway along Eglinton. It was to be completed by 2003. In 1986, a coalition of City of York and Etobicoke Metro councillors and the Regional Municipality of Peel persuaded Metro Council to include an Eglinton West line in a new Transit Network Plan. Work on the subway line began in 1994 and was halted following the election in 1995, which saw Mike Harris taking power and led to the cancellation of the Eglinton West line, with the existing tunnel quickly filled in.[13]

Original concept

Line 5 Eglinton was originally conceived as the Eglinton Crosstown LRT, a partially underground light rail line, announced in 2007 by Toronto mayor David Miller and TTC chair Adam Giambrone. It was part of the Transit City plan, which included the implementation of six other light rail lines across Toronto. The original version of the line would have run from Pearson Airport along Silver Dart Drive to Convair Drive. The line would have then turned southwest to a bridge over Highway 401 to reach Commerce Boulevard on the other side, where it would run south to reach Eglinton Avenue and the east end of the Mississauga Transitway. The rest of the line would run east along Eglinton Avenue, including a portion along which the proposed Eglinton West subway line would have been built. The line would then traverse the city, connecting with Line 1 Yonge–University, Line 2 Bloor–Danforth, and Line 3 Scarborough.

There were 43 stops planned for the Eglinton Crosstown LRT, 13 of which would be underground.[14] Surface stops would be spaced on average 500m (1,600feet) apart and the underground stations would be 850m (2,790feet) apart on average, as constructing numerous underground stops would be costly. The average speed would be 28km/h, compared with the existing bus routes along Eglinton that have an average speed of 16to.[15] The line would terminate at Kennedy station to the east in Scarborough where it would meet Line 2 Bloor–Danforth, the proposed Scarborough Malvern LRT and the Stouffville GO train line. The expected cost was .[16] As a result of provincial funding cuts, construction of the line was divided into two phases: phase one would end at Jane Street, and phase two would terminate as had been planned at Pearson Airport.[17]

Rob Ford–era redesigns

Miller's successor, Rob Ford, announced the cancellation of Transit City on December 1, 2010, the day he took office.[18] He proposed an alternative titled the "Eglinton–Scarborough Crosstown line", which put the 19km (12miles) line along Eglinton Avenue completely underground. The line would have then followed the route of Line 3 Scarborough, thus forming a single line continuously from Black Creek Drive to . The cost would almost double to $8.2billion and, compared to the original plan, 18 fewer stops were planned, including the elimination of the connection to Pearson Airport. Most of the additional cost would have come from putting 12 additional stations underground and for converting the Scarborough RT.

On February 8, 2012, in a special meeting, Toronto City Council, led by Karen Stintz, voted 25–18 to override Mayor Ford's modifications to the project. The vote reinstated the original proposal to only construct the portion between Laird Drive and Keele Street underground while the remainder of the line is built along the surface. On November 30, 2012, the environmental assessment was revised, such that the east tunnel portal location would be moved from east of Brentcliffe to east of Don Mills;[19] however, this was reversed in May 2013 after receiving community feedback.[20] In January 2013, city councillors from Scarborough put forward an alternative plan to proceed with the construction of the Eglinton Avenue portion of the line as planned but to exclude the Scarborough RT. In July 2013, plans for an "Eglinton-Scarborough Crosstown" line were abandoned, thereby reverting the entire line back to the plan that had been conceived under Transit City.[21] [22]

Location of tracks at Leslie Street

The environmental assessment evaluated the line running in the middle of Eglinton Avenue through the valley at Leslie Street. However, in late 2012 and early 2013, there were proposals to locate the tracks elsewhere. In 2012, Metrolinx discovered that there would be minimal cost differential between tunnelling under the West Don River at Leslie Street (the proposed location of the Sunnybrook Park stop) versus laying the track on the surface. Also, tunnelling through that section would have provided "significant improvements to construction staging, schedule and traffic impacts", according to Metrolinx.[23] [24] Thus, in December 2012, Metrolinx proposed continuing the LRT tunnel from Laird station to Science Centre station and eliminating the planned Sunnybrook Park surface stop. It did not want to build an underground station at the Sunnybrook location as it would cost $80 to $100 million (as compared to about $3 million for a surface stop). Metrolinx considered the cost of an underground station to be unjustified given its low projected ridership (650 passengers at the busiest hour). Local residents objected to the elimination of their stop,[25] and by mid-2013, Metrolinx had relented and the surface stop was restored.[23] [26]

Members of the public asked Metrolinx why it was proposing a centre-of-road alignment instead of running the tracks on the south side of Eglinton Avenue through the valley at Leslie Street. The south-side alignment would have avoided going through the signaled intersection at Leslie Street. Metrolinx explained that the alternate alignment "was more expensive and [would have] required an EA amendment. Due to project implementation timelines the project is proceeding with the EA option". They also stated, "It is very difficult (if not impossible) to relocate the portal from the centre of Eglinton (as proposed in the current design) and shift it to the south side of the right-of-way and continue to use the existing bridge."[27]

Westward extension

Surface station plan (2007–2019)

In a later phase, Metrolinx had planned for the Eglinton Crosstown to be extended westwards from Mount Dennis along Eglinton Avenue West to Toronto Pearson International Airport. However, during his successful campaign in the 2014 Toronto mayoral election, John Tory proposed SmartTrack, which would have included a heavy rail transit line established along this section of Eglinton Avenue. In 2016, the City of Toronto released a feasibility report that found this proposal would have significant capital costs ranging from $3.6billion to $7.7billion. In comparison, extending the Eglinton Crosstown as approved would cost $1.3billion. It was also found that a light rail transit line would attract higher ridership than a heavy rail line.

The City of Toronto's chief planner recommended the extension of the Eglinton Crosstown line (referred to as Crosstown West) to Pearson Airport in lieu of establishing SmartTrack on Eglinton Avenue, based upon negative community impacts, higher costs, and lower projected ridership associated with a heavy rail corridor. On January 19, 2016, Tory agreed with the analysis and supported Metrolinx's original plan of extending the Crosstown.[28] Tory included the Crosstown West as a light-rail component of his SmartTrack plan.[29]

In June 2016, the estimated completion date was 2023.[30] The estimated cost to build the Eglinton West LRT was $2.47billion of which the City of Toronto would contribute $1.18billion, the federal government would contribute $822.9million, and the City of Mississauga and the Greater Toronto Airports Authority (GTAA) would be asked to contribute $470million for the portion of the line in Mississauga. Approvals for the financing were still to be secured as of November 2, 2016.[31]

Public meetings for the extension, renamed the Eglinton West LRT, began November 13, 2017.[32] [33]

The 2010 Environmental Assessment for Transit City originally considered an entirely at-grade light rail line running west from Weston Road and Mount Dennis station. However, by October 2017, the city was considering grade separation using fly-overs and fly-unders at six intersections: Martin Grove Road, Kipling Avenue, Islington Avenue, Royal York Road, Scarlett Road, and Jane Street, with surface running between stations.[34] [35]

On November 21, 2017, city staff recommended just 10 stops along Eglinton West between Mount Dennis station and Renforth station on the Mississauga Transitway. The most recent recommendation dropped the stops at Rangoon, East Mall, and Russell / Eden Valley.[36] [37]

At a city executive committee meeting on November 28, 2017, city staff recommended building the extension without any grade separation. City staff had concluded that a fully at-grade extension would provide better access for transit users and have fewer environmental impacts. Grade separation would have little improvement on traffic because the at-grade option would use signal coordination; however, grade separation would require fewer restrictions on left turns. There would be no difference in development potential with either option. However, because of feedback from the public and local politicians, Mayor John Tory recommended more study on grade separation.[38] A fully at-grade extension was estimated to cost $1.5 to $2.1billion. Grade separation would add an extra $881.9million to $1.32billion to that cost.

Grade-separated station plan (2019–present)

In April 2019, the brother of Rob Ford, Ontario premier Doug Ford, announced a plan for transit in the Greater Toronto Area. This included the planned extension of Line 5 Eglinton west to Pearson Airport with a section of the line built underground from Royal York to Martin Grove.[39] In February 2020, Metrolinx released an initial business case analysis of the project with four options, including three which were below-grade.[40] Metrolinx ultimately decided on a mostly grade-separated line with seven stations (four underground, two elevated, one at ground level).[41]

The decision to run trains above ground near the proposed station at Jane Street led to protests from late 2022 and the erection of a tipi and other temporary structures by local First Nations groups from early February 2023.[42] [43] As of that month, the coalition was asking Metrolinx to pause development until a resolution was found. The group also requested more "transparency about the projectits costs, its size, and its impact".[44]

Building a mostly grade-separated extension is expected to cost $4.7billion and would have 7 stations and an estimated 37,000 daily boardings. For comparison, a surface line would have cost $2.9billion and have had 10 ground-level stations and an estimated 42,500 daily boardings. Travel time savings on an underground line would have been double that for a surface line and such a line would have been fully weatherproof, but the reduction in stations was projected to have led to a lower estimated ridership, though local bus service would have been retained given the increased spacing between stations.[45] During the 2018 Ontario provincial election, Liberal and Progressive Conservative candidates Yvan Baker and Kinga Surma supported the underground option.[46] Of the three major parties, only NDP candidate Erica Kelly supported the surface option. Doug Ford, campaigning to become the premier of Ontario, preferred underground construction.[47]

Construction and implementation

Central section

Crosslinx

Crosslinx Transit Solutions (CTS), a consortium of more than 26 companies, was awarded the contract to design, build and finance the Eglinton Crosstown line and to maintain it for 30 years. The contract, which excludes boring the tunnels, is for completing all other remaining work, including the stations and the finishing work within the tunnels. Some of the members of the consortium are SNC-Lavalin, Aecon, EllisDon, ACS Infrastructure Canada, Dragados, IBI Group and Scotiabank. The contract defines a public–private partnership.[48] [49]

The 30-year contract to build and maintain the line will total $9.1billion. Capital costs will be $5.3billion, with each of the 15 underground stations costing $80–$100million to build and the ten street-level stops $3–$5million each. The remainder will be for financing, lifecycle and maintenance costs.

In July 2015, the Crosslinx Transit Solutions Maintenance General Partnership consortium awarded Bombardier Transportation a 30-year contract to maintain Line 5's light-rail vehicles. The contract was worth $403million.[50] Bombardier will also maintain wayside systems (track and overhead catenary) for Line 5.[51]

Timeline

2010

On July 28, 2010, Metrolinx ordered four tunnel boring machines (TBMs) from Caterpillar at a cost of $54million.[52] Each TBM is long, in diameter and weighs . They bore per day, 16to below the surface. The TBMs were named Dennis, Lea, Humber, and Don. The names were chosen by Jason Paris, a moderator of the UrbanToronto blog and web forums. Dennis is named after Mount Dennis, Lea is named after Leaside, Humber is named after the Humber River, and Don is named after the Don River. The names Dennis and Lea combined allude to the Canadian poet Dennis Lee. When boring work was completed, enough dirt had been removed to fill the Scotiabank Arena to the height of the CN Tower.

2011

In August 2011, preparation for construction of a launch shaft for tunnel boring machines at Black Creek Drive began,[53] while in October of that year, the first part of tunnel construction started.[54]

On November 9, 2011, in Keelesdale Park, Mayor Rob Ford and Premier Dalton McGuinty officially broke ground on the new project.[55]

2012

In May 2012, TTC staff released a report saying that completion of the Eglinton Crosstown was unlikely by 2020 and that a more realistic in-service date would be 2022–2023. The main reason given was that the project management had been transferred from the TTC to Infrastructure Ontario which uses the Alternative Finance and Procurement strategy. That strategy would use a private contractor to complete the project, effectively requiring that contractor to redo all design work already completed by the TTC.[56] The TTC also warned that Metrolinx's aggressive timeline would lead to severe construction-related disruptions to communities and traffic because large stretches of the Eglinton Avenue would have to be torn up concurrently to meet deadlines.

2013

In January 2013, Infrastructure Ontario issued a request for qualifications to shortlist companies to construct the line. A request for proposal was expected in mid-2013.[57]

On February 22, 2013, TBMs Dennis and Lea arrived in Keelesdale Park.[58]

In June 2013, the TBMs Dennis and Lea began tunnelling on the line. Traffic on Eglinton Avenue near Keele Street was reduced to one lane in each direction.[59]

On November 12, 2013, Metrolinx awarded a contract to a joint venture between Aecon Group and ACS Dragados Canada to construct the eastern portion of the line between Yonge Street and Laird Drive.

2014

In March 2014, work began to clear utilities and trees on the south side of Eglinton Avenue just east of Brentcliffe Road to set up the eastern launch shaft. For two and a half years, traffic around the excavation site will be reduced from two to one lane in each direction. West of the site, more lane restrictions would go into effect to construct head walls (below-ground walls that form the ends of each subway station) at the future, Bayview (later renamed Leaside) and Mount Pleasant stations. There will also be lane restrictions for two years near Hanna Road to build an emergency exit near Leaside High School.

By April 2014, the TBMs had arrived at Caledonia station. In April 2014, The Globe and Mail reported that the two western tunnel boring machines were excavating "approximately 1000cuyd of spoil", per day.

For the year prior to May 2014, the two TBMs Dennis and Lea had been excavating and installing concrete tunnel liners at a rate of approximately 10m (30feet) per day. The tunnels are lined with precast concrete liner segments. Six 2.5tonne segments form each ring.

In early December 2014, Dennis and Lea arrived at Eglinton West station.[60] Dennis stopped to allow Lea to catch up so that they would arrive at Eglinton West station at the same time.

2015

On the weekend of April 18 and 19, 2015, the boring machines, Dennis and Lea, were lifted out of a shaft west of Allen Road and moved about to a shaft just east of Allen Road.

In April 2015, merchants along Eglinton Avenue West were complaining of lost revenue (up to a 35 percent dip in sales), because construction was discouraging customers with snarled traffic, limited parking options, reduced foot traffic and dusty sidewalks.

By September 2015, the TBMs Don and Humber arrived for assembly in the shaft at Brentcliffe Road before starting to drill the 3.25km (02.02miles) section west to Yonge Street.

On September 24, 2015, Transportation Minister Steven Del Duca issued a statement saying the Crosstown would not operate until September 2021, in order "to mitigate disruption to the local community and infrastructure as much as possible." The earlier plan had been to open in 2020 with tunnelling and station construction to start in 2012.[61] Infrastructure Ontario has awarded the Crosstown construction contract to Crosslinx, a consortium led by SNC Lavalin. It will take about four years to build the stations, 15 of which will be underground.

On September 29, 2015, TBM Don started to bore the north tunnel from the Brentcliffe Road launching site westwards towards Yonge Street. TBM Humber will start boring the south tunnel approximately one month later.[62]

On November 3, 2015, Del Duca announced that the contract awarded to Crosslinx Transit Solutions to complete the Crosstown and maintain it for 30 years will cost $2billion less than originally estimated.

2016

On March 10, 2016, a ground-breaking ceremony was held at the site of Keelesdale station, the first station to be started for construction along the Eglinton Crosstown line.[63]

In February 2016, work began on the extraction shaft for TBMs Humber and Don, which are digging the eastern segment of the line. However, the hole in the street there will be much smaller than the one near Leslie Street.

On April 18, 2016, at the site of the future Forest Hill station, the façade of the former House of Chan restaurant and the scaffolding that was holding it up collapsed, injuring seven people.[64]

On May 10, TBMs Dennis and Lea, both of which had been boring the western segment of the line, completed their work by reaching Yonge Street. Dennis and Lea bored, installing 25,647 precast concrete tunnel segments to construct the 4,279 rings to line the twin tunnels.

On August 17, TBMs Don and Humber, which had been boring the eastern segment of the line, completed their work by reaching Yonge Street. Don and Humber bored, installing 26,178 precast concrete tunnel segments to construct the 4,363 rings to line the twin tunnels.[65]

On September 1, Bombardier Transportation, which is producing cars for the line, failed to meet the delivery deadline for the pilot vehicle. As a result, Metrolinx filed notice to terminate the contract with Bombardier.

On November 3, 2016, Metrolinx filed a "notice of intention" to cancel its contract with Bombardier for the Crosstown's rolling stock.

2017

On February 10, 2017, Bombardier filed an injunction, seeking to compel Metrolinx to stick with their contract. Metrolinx responded that Bombardier did deliver a prototype for testing, as required by the contract. However, Metrolinx claimed that the prototype was so incomplete that it would not power up.

Between March 13 and 17, the TBMs Don and Humber were removed in pieces from the extraction shaft on Eglinton Avenue just east of Yonge Street.[66] [67]

In July 2017, construction crews began preparation for constructing the eastern at-grade portion of the line by removing the median in the roadway.

On August 9, the first piece of track, a turnout, was installed at the Eglinton Maintenance and Storage Facility (EMSF) in Mount Dennis. The facility was scheduled for completion in late 2018[68] but this date was later revised to early 2019.

2018

In July 2018, Crosslinx Transit Solutions, the construction company building the LRT line, sued Metrolinx, claiming that utility work prior to construction exceeded timelines Metrolinx had specified. Crosslinx sought to extend the 2021 deadline for the opening of the transit line by one year.[69] [70] In August 2018, Metrolinx submitted a filing with the Ontario Superior Court of Justice to dismiss the lawsuit. This was based on an agreement with Crosslinx to resolve disputes only after construction has been completed.[71] The lawsuit was settled by Metrolinx in September 2018 under undisclosed terms.[72] It was revealed by the Auditor General of Ontario that one of the terms included an additional $237million to be paid to Crosslinx for an assurance to meet Metrolinx's 2021 deadline.[73]

In October 2018, the Eglinton Maintenance and Storage Facility was substantially complete.[74]

By December 2018, of track had been installed. The line requires of track in total.

2019

On January 8, 2019, Bombardier delivered the first Flexity Freedom vehicle to the Eglinton Maintenance and Storage Facility, which, according to Metrolinx, was "substantially complete and ready to receive the vehicles" by this date.

In January 2019, the first concrete pour for the surface section occurred at the location of the future O'Connor stop at Eglinton Square. Before being encased in concrete, conduit pipes were laid to support communications and power cables for the Crosstown's stations and stops.[75]

From July 1 to late August 2019, Leslie Street at Eglinton Avenue was closed for the installation of tracks and infrastructure at the intersection. During this time, the TTC 51 Leslie bus route turned back at Leslie and Eglinton at a temporary bus loop. The temporary closure allowed work to be completed in one section instead of two, thus eliminating joints in the road and track. This provided a higher quality result, reducing future maintenance. The closure also reduced the construction period at the intersection from six months to two.[76]

In November 2019, Crosslinx informed Metrolinx that it expected the line not to be completed before May 6, 2022, and that the construction costs would total $12.58billion, an increase of $330million over previous estimates. The main problems reported were defective caissons (underground watertight compartments) built in the 1950s at Eglinton station, groundwater at the Avenue station site and construction difficulties at the CP Rail / Metrolinx bridge adjacent to the Mount Dennis station.[77]

On December 14, 2019, testing began between the Eglinton Maintenance and Storage Facility and the Western portal using Flexity Freedom vehicles, initially testing track clearances at slow speed. On December 17, Crosslinx conducted an inaugural run with staff and guests from the handover platform at the EMSF to the elevated guideway over Black Creek Drive. At that time, overhead wire had been installed between the EMSF to just short of the Keelesdale platform.[78] [79]

2020

By the end of January 2020, Crosslinx had laid 50 percent of the line's track.[80]

In February 2020, Metrolinx announced that the line would not open until "well into 2022", a delay from the previous target of September 2021.[81] This was despite Metrolinx reaching a settlement with Crosslinx the previous year, paying the consortium $237million to commit to a September 2021 deadline. Metrolinx cited reasons for the delay: Crosslinx had started work nine months late, and had been slow to finalize some aspects of the design. Also, at Eglinton station, pipes embedded in concrete built in the 1950s were discovered in a position that impeded excavation for the Crosstown under Line 1 Yonge–University.[82]

In early March 2020, the provincial government announced it would provide $3million in aid to local merchants negatively affected by Crosstown construction near their businesses. The Ministry of Transportation and Metrolinx also announced that they would look into an earlier, partial opening of the Crosstown line.[83]

By March 2020, Crosslinx had installed the first passenger-waiting shelter on the surface section of the line at the Pharmacy stop. The shelters were pre-fabricated and hoisted into position on the LRT boarding platform.

On March 9, 2020, Crosslinx began work to extract tunnel boring machines Dennis and Lea at Duplex Avenue, one block west of Yonge Street.[84]

On May 4, 2020, Metrolinx reported the first test trip by a light rail vehicle (LRV) in a Line 5 tunnel. The trip was from the maintenance and storage facility to just short of the platform at the underground Keelesdale station. The test run was to check clearances, trackwork, and overhead power and communications; it involved several movements in and out of the tunnel at speeds of up to 25km/h.

On October 1, 2020, Crosslinx proposed partially opening Line 5 on February 28, 2022, with the Line 5 portion of Eglinton station not opening until May 2022. However, the direct connection for riders transferring between Lines 1 and 5 at Eglinton station would not be completed until September 2022; until then, passengers who wished to transfer would need to exit to the surface and descend by the entrance next door. Crosslinx says defective infrastructure from 1954 at Eglinton station, difficult hydrogeological conditions and the COVID-19 pandemic had hindered the project. Moody's Investors Service also reported delays at Kennedy, Forest Hill, Mount Pleasant and Cedarvale stations.[85] On October 8, Crosslinx filed a lawsuit against Metrolinx and Infrastructure Ontario, claiming $134million in unexpected costs due to the pandemic. Metrolinx countered that Crosslinx had been falling behind schedule before the pandemic.[86]

In early December 2020, the first pieces of artwork were being installed at Science Centre and Mount Dennis stations.[87]

2021

By early April 2021, tracks had been laid on the surface into the Brentcliffe Portal just east of Brentcliffe Road. This location will be the transition between underground and surface running on Line 5 between Laird station and the Sunnybrook Park stop.[88] In addition, as of April 2021, 85 percent of track had been installed along the entire line.

In April 2021, the last concrete "invert pour" on the line was completed at Eglinton station. The invert pour created the station's base level slab (also called an "invert"), which lies over the "mudslab", a concrete layer that sits on top of the earth.[89]

On May 3, 2021, Crosslinx energized the overhead catenary system between Laird and Kennedy stations for testing purposes. Traction power substations along the surface route supply electricity to the catenary; there will be 15 such substations.[90] [91]

On May 17, 2021, Crosslinx won a case in Ontario Superior Court against Metrolinx and Infrastructure Ontario to allow compensation for the extra construction costs and project delays due to the pandemic. The court decision allowed Crosslinx to negotiate with the two provincial agencies for financial compensation and a later completion date. (The completion per the contract was to have been September 2021, later revised to 2022 by Metrolinx.) Crosslinx sought approximately $134million in compensation for extra safety measures, absenteeism and supply-chain problems due to the COVID-19 pandemic.[92]

Between May 25 and June 2, 2021, six LRVs were delivered by truck from the Eglinton Maintenance and Storage Facility to Eglinton Avenue East and Rosemount Drive along the eastern end of the line. After unloading, each LRV (powered by the catenary) ran westwards to be stored within the Brentcliffe portal. (Until this point, only the section west from Caledonia station had been operational for testing trains.) Clearance and static testing was scheduled to take place in June with LRVs moving at walking speed.[93] [94] [95]

Effective June 20, 2021, the TTC renumbered the Avenue Rd bus route from 5 to 13 in order to free up the route number 5 for the Eglinton line.[96]

By July 2021, 93 percent of the rail had been installed along the line. At Chaplin station, track work was being completed. However, at neighbouring Avenue station, concrete was still being poured in the tunnel at one end of the station box.[97]

Until late August 2021, Crosslinx had tested the interaction between the vehicles and communications and signal systems east of the Brentcliffe portal. Vehicles ran at slow speeds. On August 24, 2021, Crosslinx started a new phase of testing east of the Brentcliffe portal involving coupled vehicles, increased speed, braking and concurrent vehicle operation.[98]

By early October 2021, Crosslinx was finishing the trackwork at Eglinton station, which included a crossover.[99] By November 1, 2021, the last section of track was laid under Yonge Street at Eglinton station, making the rails continuous between Mount Dennis and Kennedy stations. Full completion of the catenary, signals and the communication system was not expected until 2022.[100]

In November 2021, an LRV travelled from the EMSF to Laird station under its own power at slow speed in order to test clearances and systems along the way; the section between Laird and Fairbank stations had limited power. Then, the three coupled pairs of LRVs stored at Laird station were driven back to the EMSF for maintenance and replaced by two trains for further testing of the line east of Laird station.[101]

By December 2021, Metrolinx and Infrastructure Ontario had come to a settlement with Crosslinx to pay the consortium an extra $325million to handle additional costs due the COVID-19 pandemic and due to an unexpected obstruction at Eglinton station that was impeding construction. The line was expected to be substantially complete by September 2022 but possibly not be open until 2023.[102]

2022

By late February 2022, the last signal to control LRT train movements along the line was installed in the tunnel at Laird station.[103]

In March 2022, Metrolinx announced that all 76 of the light rail vehicles had been brought together at the Eglinton Maintenance and Storage Facility, the fleet's final deliveries having arrived in 2021.[104]

In July 2022, Metrolinx started to test three-car trains together with the train control system along the line. Three cars is the maximum train length for the line and can carry up to 490 passengers.[105]

In late September 2022, Metrolinx announced that Crosslinx was behind schedule and thus Line 5 would not be completed by year-end as was previously expected. Metrolinx did not provide a revised completion date.[106] However, CBC Toronto cited an unnamed source with knowledge of the project who stated that Line 5 would likely be delayed a year, until September 2023. The completion of underground stations was behind schedule, particularly at Eglinton station where tunnelling under Line 1 was difficult.[107]

According to an internal Metrolinx report from September 2022, Crosslinx had expected to complete the project by March 2023, but Metrolinx felt that date to be unrealistic. Metrolinx blamed Crosslinx and old infrastructure at Eglinton station for project delays. Metrolinx also had complaints about deficiencies in work completed. Crosslinx had over $260million in outstanding claims against Metrolinx.[108]

In December, CBC Toronto obtained confidential documents from Metrolinx which indicated that the company did not believe Crosslinx had a "credible plan" to complete the line. The records stated that 98 percent of construction and engineering work was completed at the time of their writing, while only 79 percent of track and train testing had been completed.

2023

In February 2023, Crosslinx reported it had made good progress at Eglinton station, but some utility and road restoration work still needed to be done. By April 2023, Metrolinx had not given a project status update to the public since September 2022. Documents obtained by the Toronto Star indicated the silence from Metrolinx was at the direction of the provincial government.[109]

In late April 2023, construction crews started to remove the platform at the Sloane stop due to uneven concrete, which was causing water to pool on the platform. Replacement of the platform (built in 2020) would take one month of work, and Metrolinx said that Crosslinx would be responsible for the cost.[110]

On April 26, 2023, Brian Lilley of the Toronto Sun cited unnamed sources in government and industry who indicated that Line 5 would not open until 2024 at the earliest.[111] A day later, Metrolinx CEO Phil Verster gave a status report but gave no completion date. The project had 260 non-conformance issues for Crosslinx to fix. The major problem identified was improperly laid tracks in tunnels that might be only a few millimetres out of gauge but could result in a derailment. Testing was only 50 percent complete. Training of TTC staff to operate the line would not start until the line was fully ready.[112]

On May 14, 2023, the TTC opened the northern platform extension at Eglinton station along Line 1 Yonge–University so that Line 1 trains stop further north. Upon Line 5's opening, the northern extension would offer riders a more convenient transfer between trains on Lines 1 and 5. The southern end of the original platform is closed off from trains but is still publicly accessible from the centre of the island platform to allow for access to the elevator.[113]

On May 16, 2023, Metrolinx announced that Crosslinx intended to sue the provincial agency and also to cease working with the TTC on the project. Crosslinx claimed that changes requested by the TTC were creating project delays and extra costs and that this resulted from a lack of a signed operating agreement between Metrolinx and the TTC. Crosslinx wanted the courts to remove its obligation to work on the project while issues with Metrolinx and the TTC remained unresolved. On the same day, Verster confirmed the line would not open until sometime in 2024.[114]

On September 27, 2023, Metrolinx CEO Phil Verster announced he would not give an estimated opening date for Line 5 until after "high-risk testing and commissioning work is completed". At the time of the announcement, there were about 200 unresolved defects on the project.[115]

On December 8, 2023, Metrolinx CEO Phil Verster again refused to provide any estimated opening date, saying that the date would be announced three months before opening. Crosslinx president Bill Gifford said a key piece of work could not be done in the winter months. By December 2023, 15.3 percent of the integration testing had been completed. Ten test trains were operating along the line, but testing would require increased train frequencies of 3 to 5 minutes. Training of TTC operators was 12 percent complete.[116] In December 2023, for budget purposes, the TTC made the assumption that Line 5 would open no earlier than September 2024.[117]

2024

On March 25, 2024, Metrolinx CEO Phil Verster stated that all major construction had been completed but that the most serious obstacle remaining was defects in software for the signalling and train control system.[118] The software defects were corrected with the sixth version of the software tested in April and May 2024.

A Metrolinx report dated June 27, 2024, indicated that construction had been completed for 14 of the 15 stations along the line. Eglinton station was the only station where work was outstanding due to its complexity. By June 2024, 17 TTC staff had been trained as instructors. It was planned they would, in turn, train 110 operators.[119]

West section

The delivery strategy from Metrolinx and Infrastructure Ontario includes five separate contracts: a first advance tunnel between Renforth Drive and Scarlett Road; a second advance tunnel between Jane Street and Mount Dennis station; an elevated guideway between Scarlett Road and Jane Street; stations, rail and systems for the entire LRT; and the airport segment.

Advance tunnel 1 – Renforth to Scarlett

On March 10, 2020, Metrolinx and Infrastructure Ontario issued a request for qualifications (RFQ) for the construction of tunnels, marking the first phase of procurement of the western Eglinton extension.[120] On May 20, 2021, the design–build–finance contract was awarded to West End Connectors (a consortium of Dragados, Aecon and Ghella).[121]

The contract included the design, construction and financing of:

On April 11, 2022, tunnelling began from the launch shaft located adjacent to Renforth station; two tunnel-boring machines (TBM), dubbed Rexy and Renny, will tunnel eastwards to the west side of Scarlett Road, where the extraction shaft will be located. Each TBM weighs about, and are in diameter and in length. The tunnels will be underground. The underground stations will be built using the cut-and-cover method. Renny started boring in April 2022 but Rexy started later, in early August, as the launch area was only large enough to launch one TBM at a time. The extraction shaft will be near the west side of Scarlett Road.[122]

Elevated guideway – Scarlett to Jane

In December 2021, Metrolinx issued a pre-qualification request for a design–build contract to build a 1.5km (00.9miles) elevated guideway from the portal west of Scarlett Road to the portal east of Jane Street. This elevated guideway will connect both advance tunnel contracts and will take the line over the Humber River.[123] On December 15, 2023, the contract was awarded to Aecon, with construction of the guideway to begin sometime in 2024.[124]

Advance tunnel 2 – Jane to Mount Dennis

On December 2, 2021, Metrolinx and Infrastructure Ontario issued the request for qualification (RFQ) for the construction of tunnels between Jane Street and Mount Dennis station. On February 16, 2024, the contract was awarded to Strabag. The contract includes the design and construction of a 500m (1,600feet) tunnel from east of Jane Street to Mount Dennis station, as well as modifications to the station to enable through service.[125]

Stations, rails and systems

On March 25, 2024, Infrastructure Ontario issued an RFQ for the stations, rails and systems contract.[126] This design–build contract will involve:[127]

Extension to Pearson Airport

A further extension would take the line to Toronto Pearson International Airport., the route for this extension has not been finalized, with a conceptual route heading north, crossing Highway 401, then following Highway 427 north before turning west towards the airport terminals.[128] Metrolinx is working with the Greater Toronto Airports Authority on the project.[129] [130]

Route

Right-of-way

Line 5 Eglinton will mostly run underground for 21km (13miles) from Renforth Drive to just east of Don Mills Road, with elevated sections across the Humber River and Black Creek valleys, as well as short at-grade sections at Renforth and Sunnybrook Park. East of Don Mills Road, it rises to the surface to continue another 6km (04miles) to end at Kennedy station.[131] [132] The central section will have of track, including six double crossovers, five mono-directional crossovers and three pocket tracks.[133] Additional crossovers for west extension will be located west of Jane station and east of Renforth station. When the line is extended further west to the airport, there will be an additional crossover on the west side of Renforth station. Both Jane and Renforth stations will have pocket tracks.[134]

Parts of the surface route will use "green track", that is, track with vegetation growing beside and between the rails. Green track will be used between the Brentcliffe Road tunnel portal (western end of the surface route) and Birchmount Road (Birchmount stop in the east end) with paved gaps at intersections, surface stops and the underground Science Centre station.[135] Each section of green track will have irrigation chambers, a water supply, and an energy source for the irrigation system. Green track will dampen train sounds, absorb runoff water, reduce ambient temperatures in summer and minimize the spread of dust.[136] Surface stops will be located at accessible, signalized intersections, and will have a transparent design for passenger security. Platforms will have a sign post bearing the stop's name, a barrier along the road to protect waiting passengers, Presto machines, screens displaying the next vehicle arrival time and advertising, platform illumination and covered waiting shelters with benches and a passenger assistance intercom. The platforms will be designed for level boarding.

Stations and stops

Station/stop[137] Type Notes
Under construction
SurfaceLocated east of Weston Road; direct connection to Kitchener line, Union Pearson Express
UndergroundLocated at Keele Street
UndergroundFuture connection to Barrie line
UndergroundLocated at Dufferin Street
Underground
Cedarvale (Eglinton West)UndergroundConnection to Yonge–University at the existing Eglinton West station, to be renamed Cedarvale when Line 5 opens[138]
UndergroundLocated at Bathurst Street
Underground
Underground
UndergroundLocated at Yonge Street; connection to Yonge–University
Underground
UndergroundLocated at Bayview Avenue
Underground
Sunnybrook ParkOn-streetParallel side platforms located at Leslie Street.[139]
UndergroundLocated at Don Mills Road; future connection to Ontario Line
Aga Khan Park & MuseumOn-streetParallel side platforms located on the west side of the Don Valley Parkway, near its namesake Aga Khan Park and Aga Khan Museum.[140]
WynfordOn-streetParallel side platforms located in the Don Mills neighbourhood just west of the bridge over Wynford Drive[141]
SloaneOn-streetCentre platform located in the Victoria Village neighbourhood at Bermondsey Road and Sloane Avenue.[142]
O'ConnorOn-streetParallel side platforms located in the Golden Mile neighbourhood between Victoria Park Avenue and Eglinton Square.[143]
PharmacyOn-streetParallel side platforms located in the Golden Mile neighbourhood at Pharmacy Avenue[144]
Hakimi LebovicOn-streetFar-side platforms located in the Golden Mile neighbourhood at Hakimi and Lebovic Avenues.[145]
Golden MileOn-streetFar-side platforms located in the Golden Mile neighbourhood at Warden Avenue.[146]
BirchmountOn-streetParallel side platforms located in the Ionview neighbourhood at Birchmount Road[147]
IonviewOn-streetParallel side platforms located at Ionview Road[148]
UndergroundConnection to Bloor–Danforth and Kennedy GO Station for Stouffville line
Future
RenforthOpen trenchLocated on the north side of the existing bus rapid transit station at the eastern terminus of the Mississauga Transitway
Martin GroveUndergroundLocated on north side of Eglinton at the northeast corner with Martin Grove Road
KiplingUndergroundLocated under Eglinton on the west side of Kipling Avenue with an entrance at the northwest corner and an emergency exit at the west end of the platform
IslingtonUndergroundLocated on north side of Eglinton at the northeast corner with Islington Avenue
Royal YorkUndergroundLocated on north side of Eglinton at the northwest corner with Royal York Road
ScarlettElevatedLocated on north side of Eglinton above Scarlett Road
JaneElevatedLocated on north side of Eglinton above Jane Street

Station names

In the planning stages for Line 5 Eglinton, many stations and stops were given working names identical or similar to names of existing subway stations or GO Transit stations within Toronto. On November 23, 2015, a report to the TTC Board recommended giving a unique name to each station within the subway system, including those on Line 5. Thus, several stations with non-unique working names were renamed mostly after the neighbourhoods these stations serve, even those which will be comparatively simple on-street surface stops: Weston (renamed Mount Dennis), Keele (Keelesdale), Dufferin (Fairbank), Bathurst (Forest Hill), Oriole Park (Avenue), Bayview (Leaside), Leslie (Sunnybrook Park), Don Mills (Science Centre), Victoria Park (O'Connor) and Warden (Golden Mile).[149]

There were other name changes for on-street stops even though the original names did not conflict with existing station names. The Aga Khan Park & Museum stop was originally named Ferrand after the nearby Ferrand Drive.[150] Sloane was originally named Bermondsey.

The Hakimi Lebovic stop was originally named Lebovic. Metrolinx changed the name after the TTC noted Hakimi Avenue led to more prominent locations such as Centennial College while support for the Lebovic name remained.[151] Metrolinx later named the station in honour of Joe Lebovic and Karim Hakimi, whom the streets are named after.[152]

Despite its unique name, Eglinton West station will be renamed Cedarvale after its surrounding neighbourhood to avoid confusion with Eglinton station.[153] Eglinton station is not expected to be renamed "Eglinton–Yonge" (as was the case with Sheppard–Yonge station, which was named "Sheppard" before Line 4 Sheppard opened) given that Eglinton station is located in the former village of Eglinton.[154]

As of May 2024, alternate names for stations along the under-construction western extension at cross streets (Kipling Avenue, Islington Avenue, Royal York Road, and Jane Street) with existing stations on Line 2 Bloor–Danforth had not yet been announced.

Since the permanent closure of the Ontario Science Centre's original main location in Don Mills in June 2024, there have been talks about renaming Science Centre station.[155] [156]

Public art

See also: Toronto subway public art. As part of the Crosstown project, six stations along Line 5 EglintonMount Dennis, Caledonia, Cedarvale (Eglinton West), Eglinton, Science Centre and Kennedywill feature eight artworks. These stations were chosen because they are all interchange stations expected to host higher passenger volumes. Some of the other stations feature other artwork, such as a photograph of pick-up sticks at Oakwood station.

All artworks will be integrated into station design and construction rather than being stand-alone pieces. Because of the controversy over the artwork LightSpell at Pioneer Village station, in which commuters can display messages that can violate the 2009 revision of TTC's By-Law No. 1 that prohibits the use of inappropriate language, none of the Line 5 artworks will be interactive. The art budget is about $10million. About $1million of that budget will be used for digital art to appear on screens at stations along the line.[157]

Operations

Operating characteristics of the line include:

Rolling stock

As the line is owned by the province of Ontario, Metrolinx chose the Bombardier Flexity Freedom light rail vehicle, which uses standard gauge rather than the TTC's own slightly larger gauge. Metrolinx wanted to avoid using a custom gauge in order to secure a better price from the manufacturer and to create a standard for other light-rail projects in the province.[166] The vehicles have an operator's cab at only one end of the vehicle; thus, the LRVs must be run in back-to-back coupled pairs.[167] Trains will use automatic train control within the tunnelled portion of the line. Like the Flexity Outlook vehicles Bombardier built for the TTC's streetcar system, initial work building the chassis was performed at Bombardier's Mexican plant in Ciudad Sahagún, Hidalgo, with final assembly at Bombardier's plant in Thunder Bay.[168]

In 2010, Metrolinx ordered 182 Flexity Freedom vehicles not only for Line 5 but for other light-rail projects in Ontario. The first two deliveries were expected in the second quarter of 2015 but had not arrived by May 2017. After being unsure if a timely delivery of the Bombardier vehicle order could be relied upon, Metrolinx reduced the Bombardier order from 182 to 76 to supply just Line 5 and made a contingency order with Alstom for 61 Citadis Spirit vehicles, of which 44 would be for Line 5 and the remaining 17 for Line 6 Finch West.[169] If the Flexity Freedom order did arrive after all, surplus Alstom vehicles would be used on other Metrolinx projects (most likely the Hurontario LRT in Mississauga in Peel Region).[170] [171] On October 30, 2018, Bombardier announced that the first Flexity Freedom vehicle had completed its in-house testing and would be delivered for on-site testing in Toronto in November 2018. However, the first vehicle arrived late, on January 8, 2019.[172] As a commissioning test, each vehicle must travel at least 600km (400miles) before accepting passengers.

Eglinton Maintenance and Storage Facility

See main article: Eglinton Maintenance and Storage Facility. A maintenance and storage facility is required for Line 5, given the new technology employed, track gauge and the number of vehicles ordered. The Eglinton Maintenance and Storage Facility will have storage for 162 Flexity Freedom LRT vehicles and have extensive maintenance facilities to keep them running smoothly.[173] The facility is being built near the line's western terminus at Mount Dennis station on lands formerly occupied by Kodak's Toronto campus[174] [175] [176] and near the Mount Dennis bus garage.

Eglinton East LRT

See main article: Eglinton East LRT. Under Mayor John Tory, Toronto City Council approved an eastern extensions for Line 5 Eglinton on March 31, 2016,[177] and it is a City of Toronto project still in the proposal stage. However,, the Eglinton East LRT has become a proposal for a separate line rather than an extension of Line 5.

Between 2016 and 2021, the City of Toronto proposed that the Eglinton East LRT (EELRT) be an eastward extension of Line 5 Eglinton, extending from Kennedy station to Malvern Town Centre via Eglinton Avenue East, Kingston Road and Morningside Avenue. By 2022, the city had decided that the EELRT would be a separate, independent line with no rail connection to Line 5 at Kennedy station. Unlike Line 5 Eglinton and its western extension, which are Metrolinx projects, the EELRT is a City of Toronto project.[178]

By 2022, city planning staff had concluded a through-service connection with Line 5 at Kennedy station was not feasible as an EELRT tunnel would be only above the SSE tunnel at Kennedy station, and the SSE tunnel structure would not be strong enough to safely support an EELRT tunnel above it.[179] As a separate line, the EELRT would use trains long or less. The EELRT would use its own distinct vehicles (i.e. different from those used on Line 5 Eglinton) in order to better adapt to the line's conditions: no running in tunnels, shorter trains and platforms, and a better ability to climb steeper grades to avoid expensive road infrastructure changes that would otherwise be required if the EELRT were a Line 5 extension. It would also connect with Line 2 again at Sheppard Avenue and McCowan Road.

See also

External links

Notes and References

  1. News: Wilson . Codi . TTC planning for possible opening of Eglinton Crosstown LRT in September 2024 . . December 15, 2023.
  2. Web site: Eglinton Crosstown West Extension - FAQs . Metrolinx . December 7, 2023.
  3. News: Consiglio . Alex . TTC to operate city's new LRT lines . . October 3, 2012 . November 1, 2012 . November 3, 2012 . https://web.archive.org/web/20121103024458/http://www.thestar.com/news/gta/transportation/article/1266093--ttc-to-operate-city-s-new-lrt-lines . live.
  4. Web site: Eglinton LRT 2012 update . Metrolinx . February 2012 . November 1, 2013 . https://web.archive.org/web/20130213025406/http://www.metrolinx.com/en/projectsandprograms/transitexpansionprojects/EglintonScarboroughCrosstownUpdate_Feb72012.pdf . February 13, 2013.
  5. Web site: Next steps announced for Eglinton Crosstown West subway extension into Etobicoke, Mississauga . September 7, 2020 . Global News . August 19, 2020 . https://web.archive.org/web/20200819234229/https://globalnews.ca/news/7286235/eglinton-crosstown-west-extension-subway-etobicoke-mississauga/ . live.
  6. Web site: April 11, 2022 . Tunnelling starts on the Eglinton Crosstown West Extension . dead . https://web.archive.org/web/20220412040648/https://blog.metrolinx.com/2022/04/11/tunnelling-starts-on-the-eglinton-crosstown-west-extension/ . April 12, 2022 . Metrolinx.
  7. Web site: Eglinton Crosstown West Extension - FAQs . Metrolinx . December 7, 2023.
  8. Web site: Eglinton-Scarborough Crosstown Update . Metrolinx . June 23, 2011 . July 28, 2011 . November 5, 2013 . https://web.archive.org/web/20131105234642/http://www.metrolinx.com/en/docs/pdf/presentations/EglintonCrosstownSlidesCombinedPresentationFINAL.pdf . dead.
  9. Web site: Agenda Item History . September 7, 2020 . app.toronto.ca . March 17, 2016 . https://web.archive.org/web/20160317014722/http://app.toronto.ca/tmmis/viewAgendaItemHistory.do?item=2016.EX13.3 . live.
  10. Web site: FAQs . Eglinton Crosstown: The Project . Metrolinx . Q: What is the timeline for the project? A:The project will be complete in 2021 . February 12, 2017 . February 20, 2017 . https://web.archive.org/web/20170220104124/http://www.thecrosstown.ca/the-project/faq . live.
  11. News: Metrolinx agrees to new date to complete Crosstown LRT, says credit rating agency . Spurr . Ben . . November 24, 2021 . November 25, 2021 . November 25, 2021 . https://web.archive.org/web/20211125000129/https://www.thestar.com/news/gta/2021/11/24/metrolinx-agrees-to-new-date-to-complete-crosstown-lrt-says-credit-rating-agency.html . live.
  12. News: Metrolinx refuses to say when long-delayed Eglinton Crosstown LRT might open . . September 27, 2023.
  13. Web site: TIMELINE: A brief history of Toronto's Eglinton Crosstown LRT project. April 29, 2022. April 13, 2022. https://web.archive.org/web/20220413164803/https://www.toronto.com/news/timeline-a-brief-history-of-torontos-eglinton-crosstown-lrt-project/article_d256bb01-c3b1-538f-abe5-d5226b5b2296.html. live.
  14. Web site: Eglinton Crosstown Light Rail Transit stops and stations . . November 2010 . July 30, 2011 . https://web.archive.org/web/20210204062933/http://www.ttc.ca/PDF/About_the_TTC/Transit_City/Eglinton_LRT_route_diagram1.pdf . February 4, 2021.
  15. News: Spears . John . Distance between LRT stops criticized . . August 9, 2008 . August 14, 2008 . August 12, 2008 . https://web.archive.org/web/20080812012645/http://www.thestar.com/article/475187 . live.
  16. News: Eglinton Transit City line may survive . . January 4, 2011 . April 24, 2011 . November 9, 2012 . https://web.archive.org/web/20121109050156/http://www.cbc.ca/news/canada/toronto/story/2011/01/04/eglinton-lrt-metrolinx653.html . live.
  17. Web site: Truncated version of Transit City does not satisfy mayor . East York Mirror . May 6, 2010 . May 28, 2021 . https://web.archive.org/web/20210528131029/https://www.toronto.com/news-story/51154-truncated-version-of-transit-city-does-not-satisfy-mayor/ . May 28, 2021.
  18. D'Cruz . Andrew . Mayor Rob Ford: "Transit City is over" . https://web.archive.org/web/20101204123034/http://www.torontolife.com/daily/informer/streetcar-named-disaster/2010/12/01/mayor-rob-ford-%E2%80%9Ctransit-city-is-over%E2%80%9D/ . December 4, 2010 . . December 1, 2010 . August 4, 2014.
  19. http://thecrosstown.ca/news-media/whats-new/Online-Consultation-Laird-Don-Valley
  20. News: Kalinowski . Tess . Metrolinx puts Leslie back on the Crosstown map . . May 12, 2013 . November 8, 2013 . November 9, 2013 . https://web.archive.org/web/20131109004841/http://www.thestar.com/news/gta/2013/05/12/metrolinx_puts_leslie_back_on_the_crosstown_map.html . live.
  21. News: Kalinowski . Tess . Scarborough councillors seek subway line instead of LRT: A group of Toronto councillors wants to replace the planned LRT for Scarborough with a subway. But a subway would cost $500million more . . May 6, 2013 . July 3, 2013 . https://web.archive.org/web/20130509024718/http://www.thestar.com/news/gta/2013/05/06/scarborough_councilors_seek_subway_line_instead_of_lrt.html . May 9, 2013 . live . An LRT would use the same route as the SRT. It would be versus of subway. The LRT would have seven stations, the subway, only three..
  22. News: Kalinowski . Tess . TTC report threatens to reopen Scarborough subway debate: One commissioner says it's proof Scarborough can have a new subway line under construction within the decade, but Metrolinx dismisses that . . January 17, 2013 . July 3, 2013 . https://web.archive.org/web/20130926184147/http://www.thestar.com/news/city_hall/2013/01/17/ttc_report_threatens_to_reopen_scarborough_subway_debate.html . September 26, 2013 . Glenn DeBaeremaeker (Ward 38, Scarborough Centre) said the latest TTC report gives him new confidence that there will be a subway underway in Scarborough within a decade..
  23. Web site: Metrolinx Announces Design Changes and Public Meetings on Eglinton LRT (Update 8) . . Jamie . Robinson . email to Steve Munro . May 10, 2013 . November 2, 2017 . Metrolinx had identified some potential issues with the Brentcliffe Road launch site. ... We believed that our proposals would result in significant improvements to construction staging, schedule and traffic impacts. However, in discussions with the local community and with local community organizations it was clear that there was a strong preference for a stop at Leslie Street ....
  24. Web site: Metrolinx Announces Design Changes and Public Meetings on Eglinton LRT (Update 8) . . Jamie . Robinson . email to Steve Munro . June 17, 2013 . November 2, 2017 . [One of the options recommended] included a continuation of the bored tunnel from the west to pass under the West Don River and portal east of the Don Valley Parkway. That option was selected because the cost differential with the at-grade options was minimal, provided that a station at Leslie Street was not required. If a Leslie Station would be required, then one of the at-grade south side options was the preferred option..
  25. News: Eglinton-Crosstown LRT: Leasiders fight to put Leslie stop back on the map . . Tess . Kalinowski . February 12, 2013 . October 11, 2014 . The stop is being eliminated as part of a change to the LRT construction plan. Disappointed condo-dwellers at Leslie and Eglinton and, nearby Leaside are vowing to fight the decision by Metrolinx..
  26. Web site: Metrolinx Awards Contract for Crosstown LRT East Tunnel Section . . Jack . Landau . November 12, 2013 . https://web.archive.org/web/20140903141813/http://urbantoronto.ca/news/2013/11/metrolinx-awards-contract-crosstown-lrt-east-tunnel-section . September 3, 2014 . October 12, 2014 . live . With the winning bid for the eastern tunnel section announced, additional specific details about the Crosstown are now beginning to emerge. A newly released rendering from Metrolinx gives us our first look at the configuration of the future transition from tunneled section to surface track bed between Brentcliffe and Leslie..
  27. Web site: Metrolinx Announces Design Changes and Public Meetings on Eglinton LRT (Update 8) . . Jamie . Robinson . email to Steve Munro . June 17, 2013 . November 2, 2017 . [With a south-side alignment,] the LRT would have been in a completely separate right-of-way on a new bridge across the West Don River in order to maintain current vehicle capacity of Eglinton Avenue East (i.e., no conversion of travel lanes to LRT tracks). ... It is very difficult (if not impossible) to relocate the portal from the centre of Eglinton (as proposed in the current design) and shift it to the south side of the right-of-way and continue to use the existing bridge. The “viaduct” option that HMM reviewed, was suggested by the public and was presented during the recent consultations for the changes in the East, was more expensive and required an EA amendment. Due to project implementation timelines the project is proceeding with the EA option..
  28. News: Toronto Star . January 19, 2016 . SmartTrack still on track despite changing plan, Mayor Tory says . September 3, 2017 . September 16, 2017 . https://web.archive.org/web/20170916010726/https://www.thestar.com/news/gta/2016/01/19/smarttrack-still-on-track-despite-changing-plan-mayor-tory-says.html . live.
  29. News: Toronto City Council approves planning for raft of transit projects . . Moore . Oliver . July 13, 2016 . July 14, 2016 . April 4, 2017 . https://web.archive.org/web/20170404124448/http://www.theglobeandmail.com/news/toronto/toronto-city-council-shows-support-for-scarborough-subway-expansion/article30910103/ . live.
  30. News: Mayor John Tory's transit priorities face financial, political challenge: analysis . . Ben . Spurr . Jennifer . Pagliaro . June 26, 2016 . July 20, 2016 . June 28, 2016 . https://web.archive.org/web/20160628142728/https://www.thestar.com/news/gta/2016/06/26/mayor-john-torys-transit-priorities-face-financial-political-challenge-analysis.html . live.
  31. News: Mississauga fumes over $470million Toronto LRT funding assumption . . San . Grewal . November 2, 2016 . November 2, 2016 . November 4, 2016 . https://web.archive.org/web/20161104075349/https://www.thestar.com/news/gta/2016/11/02/mississauga-fumes-over-470-million-toronto-lrt-funding-assumption.html . live.
  32. Web site: Johnson . Andrew . Public Meetings for Eglinton West LRT to Begin November 13th . Urban Toronto . November 13, 2017 . November 7, 2017 . November 14, 2017 . https://web.archive.org/web/20171114093044/http://urbantoronto.ca/news/2017/11/public-meetings-eglinton-west-lrt-begin-november-13th . live.
  33. Web site: About the Eglinton West LRT . Eglinton West LRT . City of Toronto . November 13, 2017 . November 14, 2017 . https://web.archive.org/web/20171114040716/http://www.eglintonwestlrt.ca/47-2/about/ . live.
  34. Web site: Public Meetings for Eglinton West LRT to Begin November 13th . . Andrew . Johnson . November 7, 2017 . November 22, 2017 . November 14, 2017 . https://web.archive.org/web/20171114093044/http://urbantoronto.ca/news/2017/11/public-meetings-eglinton-west-lrt-begin-november-13th . live.
  35. Web site: Eglinton West LRT: Stage One Report . . October 3, 2017 . November 22, 2017 . December 1, 2017 . https://web.archive.org/web/20171201034728/http://www.eglintonwestlrt.ca/wp-content/uploads/2017/10/Stage-One-Report.pdf . live.
  36. Web site: Attachment 2 Eglinton West LRT Extension Technical & Planning Update . . 2 . October 3, 2017 . November 22, 2017 . December 1, 2017 . https://web.archive.org/web/20171201081319/https://www.toronto.ca/legdocs/mmis/2017/ex/bgrd/backgroundfile-109250.pdf . live.
  37. News: City staff recommend moving ahead on SmartTrack stations despite financing uncertainty . . Jennifer . Pagliaro . November 21, 2017 . November 22, 2017 . A report from city staff released Tuesday ... recommends a 10-stop LRT along Eglinton Ave. West. . November 22, 2017 . https://web.archive.org/web/20171122054216/https://www.thestar.com/news/city_hall/2017/11/21/city-staff-recommend-moving-ahead-on-smarttrack-stations-despite-financing-uncertainty.html . live.
  38. News: Tory backs second look at tunnelled Eglinton West LRT . . Jennifer . Pagliaro . November 28, 2017 . November 29, 2017 . November 29, 2017 . https://web.archive.org/web/20171129101643/https://www.thestar.com/news/city_hall/2017/11/28/tory-backs-second-look-at-tunnelled-eglinton-west-lrt.html . live.
  39. News: What you need to know about Doug Ford's contentious plan for transit in the GTA . December 21, 2019 . CBC News . April 10, 2019 . December 31, 2019 . https://web.archive.org/web/20191231172534/https://www.cbc.ca/news/canada/toronto/doug-ford-toronto-transit-plan-1.5091916 . live.
  40. Web site: Eglinton Crosstown West Extension Initial Business Case . metrolinx.com . Metrolinx . March 6, 2020 . February 2020 . March 12, 2020 . https://web.archive.org/web/20200312025430/http://www.metrolinx.com/en/regionalplanning/projectevaluation/benefitscases/2020-02-28_ECWE_IBC.PDF . live.
  41. Web site: Eglinton Crosstown West Extension . . September 21, 2020 . March 10, 2020 . https://web.archive.org/web/20200310090152/http://www.metrolinx.com/en/greaterregion/projects/eglinton-crosstown-west.aspx . live.
  42. Web site: Protestors say elevated LRT will destroy valuable forest and parkland . January 7, 2023 . . February 20, 2023 . February 20, 2023 . https://web.archive.org/web/20230220204202/https://toronto.citynews.ca/video/2023/01/07/protestors-say-elevated-lrt-will-destroy-valuable-forest-and-parkland/ . live.
  43. Web site: Group wants Metrolinx, Ford government to bury an elevated track that's set to run through local green space . . January 7, 2023 . February 20, 2023 . February 20, 2023 . https://web.archive.org/web/20230220204201/https://www.cbc.ca/news/canada/toronto/eglinton-crosstown-indigenous-coalition-protest-1.6706945 . live.
  44. Web site: About Stop / What We Want . February 2023 . February 20, 2023 . February 20, 2023 . https://web.archive.org/web/20230220205729/https://www.stopthetrainsinourparks.ca/about-stop-what-we-want . live.
  45. News: Burying the Eglinton West LRT will cost an extra $1.8billion and may serve fewer local riders. So why do it? . . Ben . Spurr . September 20, 2020 . September 21, 2020 . September 24, 2020 . https://web.archive.org/web/20200924211348/https://www.thestar.com/news/gta/2020/09/20/burying-the-eglinton-west-lrt-will-cost-an-extra-18-billion-and-may-serve-fewer-local-riders-so-why-do-it.html . live.
  46. Web site: 2018 . Yvan Baker supports tunneling . August 24, 2022 . Youtube . August 24, 2022 . https://web.archive.org/web/20220824185833/https://www.youtube.com/watch?app=desktop&v=5pv9jbD0VK4&skip_registered_account_check=true&noapp=1 . live.
  47. News: Moore . Oliver . February 28, 2020 . Costs of major transit projects will far exceed their benefits, according to Metrolinx reports . . March 17, 2020 . March 2, 2020 . https://web.archive.org/web/20200302104530/https://www.theglobeandmail.com/canada/toronto/article-costs-of-major-transit-projects-will-far-exceed-their-benefits/ . live.
  48. News: $9.1B Crosstown LRT mega-contract comes in under estimates . . Tess . Kalinowski . November 3, 2015 . November 3, 2015 . November 5, 2015 . https://web.archive.org/web/20151105044549/https://www.thestar.com/news/gta/transportation/2015/11/03/91b-crosstown-lrt-mega-contract-comes-in-under-estimates.html . live.
  49. News: Ontario government shaves $2-billion off Eglinton Crosstown LRT price tag . . Oliver . Moore . November 3, 2015 . November 3, 2015 . November 4, 2015 . https://web.archive.org/web/20151104123132/http://www.theglobeandmail.com/news/toronto/ontario-government-shaves-2-billion-off-eglinton-crosstown-lrt-price-tag/article27085427/ . live.
  50. Web site: Bombardier wins $403M Eglinton Crosstown maintenance contract . Canadian Manufacturing . July 27, 2015 . April 28, 2021 . https://web.archive.org/web/20200921005142/https://www.canadianmanufacturing.com/manufacturing/bombardier-wins-403m-eglinton-crosstown-maintenance-contract-151894/ . September 21, 2020.
  51. Bombardier awarded 30-year services contract for Toronto's Finch West Light Rail Transit project . . December 23, 2020 . April 28, 2021 . https://web.archive.org/web/20201227032437/https://www.globenewswire.com/news-release/2020/12/23/2149922/0/en/Bombardier-awarded-30-year-services-contract-for-Toronto-s-Finch-West-Light-Rail-Transit-project.html . December 27, 2020.
  52. News: Kalinowski . Tess . Metrolinx orders tunneling machines . . July 28, 2010 . September 3, 2017 . December 26, 2012 . https://web.archive.org/web/20121226043051/http://www.thestar.com/news/gta/transportation/article/841424--metrolinx-orders-tunneling-machines . live.
  53. Web site: Crosstown Community Update | Crosstown . April 4, 2023 . April 4, 2023 . https://web.archive.org/web/20230404014608/http://thecrosstown.ca/fr/node/262 . live.
  54. Web site: Eglinton Crosstown under way, underground . . John . Thompson . March 8, 2016 . March 5, 2020 . February 1, 2021 . https://web.archive.org/web/20210201205835/https://www.railwayage.com/passenger/light-rail/eglinton-crosstown-under-way-underground/ . live.
  55. News: Alcoba . Natalie . Ford, McGuinty get up-close look at Eglinton LRT construction . . November 9, 2011 . August 4, 2014.
  56. News: Chu . Showwei . Eglinton LRT unlikely to meet 2020 completion date: TTC report . Citytv News . May 29, 2012 . Toronto . https://archive.today/20130119143535/http://www.citytv.com/toronto/citynews/news/local/article/207847--eglinton-lrt-unlikely-to-meet-2020-completion-date-ttc-report . January 19, 2013 . June 25, 2012.
  57. Web site: Request for Qualifications Issued for the Eglinton Crosstown LRT and Scarborough LRT Lines . Infrastructure Ontario . January 22, 2013 . March 10, 2013 . October 5, 2013 . https://web.archive.org/web/20131005015642/http://www.infrastructureontario.ca/WorkArea/DownloadAsset.aspx?id=2147489840 . dead.
  58. News: Kalinowski . Tess . Eglinton Crosstown LRT tunneling a step closer . . February 22, 2013 . August 4, 2014 . November 5, 2013 . https://web.archive.org/web/20131105232505/http://www.thestar.com/news/gta/transportation/2013/02/22/eglinton_crosstown_lrt_tunneling_a_step_closer.html . live.
  59. News: Machines begin tunnelling for Eglinton Crosstown LRT . . June 5, 2013 . July 5, 2013 . July 19, 2013 . https://web.archive.org/web/20130719223007/http://www.cbc.ca/news/canada/toronto/story/2013/06/05/toronto-eglinton-tunnel-construction.html . live.
  60. Web site: TBM tracker. Google My Maps. May 16, 2023. May 16, 2023. https://web.archive.org/web/20230516165851/https://www.google.com/maps/d/viewer?mid=1JpRKWrWuT1bPzal943pWtlxf8Ic&hl=en. live.
  61. Web site: Achieving 5 in 10 – A Revised Plan for the Big 5 Transit Projects . Metrolinx . Collins . Jack . May 19, 2010 . September 27, 2015 . Complete and in-service by 2020 . February 13, 2013 . https://web.archive.org/web/20130213041655/http://www.metrolinx.com/en/docs/pdf/board_agenda/20100519/Five_in_Ten_Board_web.pdf . dead.
  62. Web site: Launch of tunnel boring machines and tunnelling work in the east . Metrolinx . October 1, 2015 . October 13, 2015.
  63. Web site: Crews break ground on 1st of 25 Eglinton Crosstown stations . . March 10, 2016 . March 22, 2016 . March 15, 2016 . https://web.archive.org/web/20160315080248/http://www.cbc.ca/news/canada/toronto/wynne-tory-transit-1.3484775 . live.
  64. News: Johnston . Paul . Eglinton scaffolding collapse injures 7, including baby: paramedics . February 11, 2020 . CP24 . April 18, 2016 . December 31, 2017 . https://web.archive.org/web/20171231013951/https://www.cp24.com/news/eglinton-scaffolding-collapse-injures-7-including-baby-paramedics-1.2863982 . live.
  65. News: Big dig wraps for Eglinton Crosstown LRT . . Daniel . McKenzie . August 17, 2016 . August 18, 2016 . August 19, 2016 . https://web.archive.org/web/20160819225629/http://www.torontosun.com/2016/08/17/big-dig-wraps-for-eglinton-crosstown-lrt . live.
  66. Web site: Join us March 13 to say farewell to the Crosstown's TBM . . October 3, 2017 . March 13, 2017 . Metrolinx invites you to join us throughout the week of March 13, 2017 to watch the pieces of being lifted and transported offsite. We will start the process of extracting the tunnel boring machines (TBM) from the completed east tunnels, and say farewell to our faithful helpers, TBM Don and TBM Humber. The TBMs will be disassembled and lifted from extraction shaft just east of Yonge & Eglinton in four oversized sections over four days. ... Each piece will be lifted from the extraction shaft in the morning, and placed on the ground within the construction zone. Later, after 9 p.m. that night, the piece will be loaded onto a large truck and hauled away. TBM Don, the machine that bored the north tunnel, will be removed first..
  67. News: Work starts on stations, tracks for Eglinton-Crosstown LRT . Dolski . Megan . Toronto Star . March 13, 2017 . March 14, 2017 . March 14, 2017 . https://web.archive.org/web/20170314000654/https://www.thestar.com/news/gta/2017/03/13/work-starts-on-stations-tracks-for-eglinton-crosstown-lrt.html . live.
  68. Web site: Eglinton Crosstown LRT Updates – August 2017 . . August 11, 2017 . August 11, 2017 . April 22, 2022 . https://web.archive.org/web/20220422100327/https://mailchi.mp/metrolinx/eglinton-crosstown-lrt-updates-8ecbmx7xhp?e=67918bdda5 . live.
  69. Web site: Spurr . Ben . Companies building Eglinton Crosstown LRT sue Metrolinx for breach of contract . The Star . July 11, 2018 . August 8, 2018 . August 9, 2018 . https://web.archive.org/web/20180809025358/https://www.thestar.com/news/gta/2018/07/11/companies-building-eglinton-crosstown-lrt-launch-lawsuit-against-metrolinx.html . live.
  70. News: Auditor-General says Metrolinx paid massive settlement without thoroughly reviewing claim . December 18, 2018 . December 14, 2018 . https://web.archive.org/web/20181214012940/https://www.theglobeandmail.com/politics/article-auditor-finds-metrolinx-spent-237-million-to-rescue-crosstown-light/ . live.
  71. Web site: Spurr . Ben . Metrolinx asks court to block lawsuit over Eglinton Crosstown LRT line . The Star . August 8, 2018 . August 8, 2018 . August 8, 2018 . https://web.archive.org/web/20180808200050/https://www.thestar.com/news/gta/2018/08/07/metrolinx-asks-court-to-block-lawsuit-over-eglinton-crosstown-lrt-line.html . live.
  72. News: LRT legal challenge settled with terms kept confidential . September 7, 2018 . The South Bayview Bulldog . September 24, 2018 . September 24, 2018 . https://web.archive.org/web/20180924070932/http://bayview-news.com/2018/09/lrt-legal-challenge-settled-with-terms-to-remain-cofidential.html/ . live.
  73. Web site: Metrolinx—LRT Construction and Infrastructure Planning . www.auditor.on.ca . December 18, 2018 . December 18, 2018 . https://web.archive.org/web/20181218054622/http://www.auditor.on.ca/en/content/annualreports/arreports/en18/v1_307en18.pdf . live.
  74. Web site: Eglinton Crosstown Update . . January 11, 2019 . January 13, 2019 . April 7, 2022 . https://web.archive.org/web/20220407023241/https://mailchi.mp/4f16c9d20221/eglinton-crosstown-update-1021317?e=67918bdda5 . live.
  75. Web site: East Guideway Concrete Pour . https://ghostarchive.org/varchive/youtube/20211221/GWG1Gf3P5g0 . December 21, 2021 . live . . February 15, 2019 . April 7, 2019.
  76. Web site: Proposed Leslie Street Closure . March 29, 2019 . April 3, 2019 . April 2, 2019 . https://web.archive.org/web/20190402131401/http://www.thecrosstown.ca/news-media/whats-new/proposed-leslie-street-closure-backgrounder . live.
  77. Web site: Eglinton Crosstown LRT could be $330million over budget and open seven months late, internal documents warn The Star. thestar.com. December 30, 2019. February 19, 2020. March 14, 2020. https://web.archive.org/web/20200314081550/https://www.thestar.com/news/gta/2019/12/30/eglinton-crosstown-lrt-could-be-330-million-over-budget-and-open-seven-months-late-internal-documents-warn.html. live.
  78. Light rail at the end of the tunnel . GreggLintern . 1205868627297230849 . December 14, 2019.
  79. Web site: Training tale – First Eglinton Crosstown light rail vehicle hits tracks of main Toronto line . . January 9, 2020 . December 20, 2019 . https://web.archive.org/web/20191227020238/https://blog.metrolinx.com/2019/12/20/first-eglinton-crosstown-light-rail-vehicle-hits-tracks-of-main-toronto-line-see-the-video-here/ . December 27, 2019.
  80. Web site: Eglinton Crosstown Update February 2020 . . February 2020 . February 21, 2020 . https://web.archive.org/web/20200221223608/https://mailchi.mp/7da9f02ca700/eglinton-crosstown-update-1024349?e=67918bdda5 . February 21, 2020.
  81. Web site: Eglinton Crosstown LRT won't be ready until 'well into 2022,' Metrolinx says . CBC News . February 18, 2020 . February 18, 2020 . February 18, 2020 . https://web.archive.org/web/20200218165253/https://www.cbc.ca/news/canada/toronto/eglinton-crosstown-lrt-open-2022-1.5466847 . live.
  82. News: Eglinton Crosstown faces another setback, delayed until 2022 . . Ben . Spurr . February 17, 2020 . February 18, 2020 . February 18, 2020 . https://web.archive.org/web/20200218090021/https://www.thestar.com/news/gta/2020/02/17/eglinton-crosstown-faces-another-setback-delayed-until-2022.html . live.
  83. News: Ford government pledges $3M for businesses affected by Eglinton LRT construction . . David . Rider . March 9, 2020 . March 10, 2020 . March 10, 2020 . https://web.archive.org/web/20200310140114/https://www.thestar.com/news/city_hall/2020/03/09/ford-government-pledges-3m-for-businesses-affected-by-eglinton-lrt-construction.html . live.
  84. Web site: Eglinton Crosstown Update . . March 13, 2020 . March 16, 2020 . https://web.archive.org/web/20200316203017/https://mailchi.mp/b69960964b27/eglinton-crosstown-update-1024485?e=67918bdda5 . March 16, 2020.
  85. News: New report says the Eglinton Crosstown LRT could open five months late — and without its Eglinton stop . . Ben . Spurr . October 1, 2020 . October 1, 2020 . October 2, 2020 . https://web.archive.org/web/20201002041347/https://www.thestar.com/news/gta/2020/10/01/new-report-says-the-eglinton-crosstown-lrt-could-open-five-months-late-and-without-its-eglinton-stop.html . dead.
  86. Web site: In 'extraordinary step,' company building Eglinton Crosstown hits province with lawsuit . . October 8, 2020 . October 8, 2020 . October 10, 2020 . https://web.archive.org/web/20201010235256/https://www.cbc.ca/news/canada/toronto/eglinton-crosstown-lawsuit-1.5755066 . live.
  87. Web site: The art of the line – How Toronto's Crosstown LRT is adding creative touches to transit design . December 9, 2020 . December 11, 2020 . December 11, 2020 . https://web.archive.org/web/20201211170623/https://blog.metrolinx.com/2020/12/09/the-art-of-the-line-how-torontos-crosstown-lrt-is-adding-creative-touches-to-transit-design/ . live.
  88. Web site: Crosstown LRT crews complete installation of rail on important stretch of Toronto's Brentcliffe Portal . . April 7, 2021 . April 13, 2021 . https://web.archive.org/web/20210411181107/https://blog.metrolinx.com/2021/04/07/crosstown-lrt-crews-complete-installation-of-rail-on-important-stretch-of-torontos-brentcliffe-portal/ . April 11, 2021.
  89. Web site: Crosstown LRT projects sees significant concrete milestones as well as main entrance features at Science Centre Station . . April 21, 2021 . April 21, 2021 . https://web.archive.org/web/20210421205514/https://blog.metrolinx.com/2021/04/21/when-it-pours-crosstown-lrt-projects-sees-significant-concrete-milestones-as-well-as-main-entrance-features-at-science-centre-station/ . April 21, 2021.
  90. Web site: Overhead Catenary System Energization between Laird Drive and Kennedy Road . . May 3, 2021 . May 1, 2021 . https://web.archive.org/web/20210501190212/https://mailchi.mp/a46a6189c85a/overhead-catenary-system-energization-between-laird-drive-and-kennedy-road . May 1, 2021.
  91. Web site: Powering up the Eglinton Crosstown LRT for the first time . . May 10, 2021 . May 10, 2021 . https://archive.today/20210511001826/https://blog.metrolinx.com/2021/05/10/powering-up-the-eglinton-crosstown-lrt-for-the-first-time/ . May 11, 2021.
  92. News: Eglinton Crosstown LRT to cost more and take longer, after builder scores legal victory . . Ben . Spurr . May 17, 2021 . May 18, 2021 . May 17, 2021 . https://web.archive.org/web/20210517225753/https://www.thestar.com/news/gta/2021/05/17/eglinton-crosstown-lrt-to-cost-more-and-take-longer-after-builder-scores-legal-victory.html . live.
  93. Web site: Light Rail Vehicle Delivery and Testing between Laird Dr. and Kennedy Rd. . . May 13, 2021 . https://web.archive.org/web/20210514013236/https://mailchi.mp/5770d95ebb17/light-rail-vehicle-delivery-and-testing-between-laird-dr-and-kennedy-rd . May 14, 2021.
  94. Web site: Get an update on the first batch of Eglinton Crosstown LRT vehicles as they begin their testing journey . . May 27, 2021 . June 8, 2021 . https://web.archive.org/web/20210527154651/https://blog.metrolinx.com/2021/05/27/get-an-update-on-the-first-batch-of-eglinton-crosstown-lrt-vehicles-as-they-begin-their-testing-journey/ . May 27, 2021.
  95. Web site: See new videos of Crosstown light rail vehicles arrive in preparation for testing to come . . June 3, 2021 . June 8, 2021 . https://web.archive.org/web/20210603141725/https://blog.metrolinx.com/2021/06/03/see-video-of-crosstown-light-rail-vehicles-arrive-in-preparation-for-testing-to-come/ . June 3, 2021.
  96. Web site: TTC to renumber 5 Avenue and 6 Bay bus routes to prepare for future rapid transit lines . . June 18, 2021 . June 21, 2021 . https://web.archive.org/web/20210623040035/https://www.ttc.ca/News/2021/June/18_06_21NR_bay_avenue_routes_renumbered.jsp . June 23, 2021 . live.
  97. Web site: Crews use unusual formwork on Crosstown LRT project as team gets closer to putting down all rail . . July 12, 2021 . July 12, 2021 . https://web.archive.org/web/20210712203526/https://blog.metrolinx.com/2021/07/12/crews-use-unusual-formwork-on-crosstown-lrt-project-as-team-gets-closer-to-putting-down-all-rail/ . July 12, 2021.
  98. Web site: Testing begins as Crosstown LRT vehicles make their first move along Eglinton Avenue . . August 24, 2021 . August 28, 2021 . August 28, 2021 . https://web.archive.org/web/20210828163211/https://blog.metrolinx.com/2021/08/24/testing-begins-as-crosstown-lrt-vehicles-make-their-first-move-along-eglinton-avenue/ . live.
  99. Web site: Final pieces of trackwork being installed at Eglinton Station for Crosstown LRT project . . October 5, 2021 . https://web.archive.org/web/20211005212341/https://blog.metrolinx.com/2021/10/05/final-pieces-of-trackwork-being-installed-at-eglinton-station-for-crosstown-lrt-project/ . October 5, 2021 . live.
  100. Web site: Crews install last piece of track for Eglinton Crosstown LRT . . November 2, 2021 . https://web.archive.org/web/20211102153128/https://blog.metrolinx.com/2021/11/02/crews-install-last-piece-of-track-for-eglinton-crosstown-lrt/ . November 2, 2021 . live.
  101. Web site: See video as first Crosstown light rail vehicles travel from Laird Station back to their storage facility . . November 18, 2021 . https://archive.today/20211119003615/https://blog.metrolinx.com/2021/11/18/see-video-as-crosstown-light-rail-vehicles-travel-from-laird-station-back-to-their-storage-facility/ . November 19, 2021 . live.
  102. News: Eglinton LRT to cost $325million more — and won't open to riders until 2023 . . Ben . Spurr . December 22, 2021 . December 23, 2021 . December 23, 2021 . https://web.archive.org/web/20211223022436/https://www.thestar.com/news/gta/2021/12/22/new-deal-sees-eglinton-crosstown-cost-another-325-million-but-gives-no-word-on-when-riders-can-use-it.html . live.
  103. Web site: Not just any red light – Final Eglinton Crosstown LRT signal installed at Laird Station . . February 24, 2022 . https://web.archive.org/web/20220224164133/https://blog.metrolinx.com/2022/02/24/not-just-any-red-light-final-eglinton-crosstown-lrt-signal-installed-at-laird-station/ . February 24, 2022 . live.
  104. Web site: All of Toronto's Crosstown vehicles are ready to go as the line actually nears completion . April 1, 2022 . www.blogto.com . April 1, 2022 . https://web.archive.org/web/20220401125823/https://www.blogto.com/city/2022/03/toronto-crosstown-vehicles-ready/ . live.
  105. Web site: Full-length vehicle testing starts for Eglinton Crosstown – plus station updates . . July 21, 2022 . https://web.archive.org/web/20220721175950/https://blog.metrolinx.com/2022/07/21/full-length-vehicle-testing-starts-for-eglinton-crosstown-plus-station-updates/ . July 21, 2022 . live.
  106. News: Long-delayed Eglinton LRT delayed again, says Metrolinx . . September 22, 2022 . September 23, 2022 . September 23, 2022 . https://web.archive.org/web/20220923213027/https://www.thestar.com/news/gta/2022/09/23/long-delayed-eglinton-lrt-delayed-again-says-metrolinx.html . live.
  107. Web site: September 23, 2022 . Eglinton Crosstown LRT will be delayed by about a year, source says . live . https://web.archive.org/web/20220925173953/https://www.cbc.ca/news/canada/toronto/eglinton-crosstown-lrt-behind-schedule-metrolinx-1.6593957 . September 25, 2022 . September 23, 2022 . CBC Toronto.
  108. News: No 'credible plan' for completion of Eglinton LRT, says Metrolinx . . December 12, 2022 . December 9, 2022 . December 9, 2022 . https://web.archive.org/web/20221209011438/https://www.thestar.com/news/gta/2022/12/08/no-credible-plan-for-completion-of-eglinton-lrt-says-metrolinx.html . live.
  109. News: 'Something really stinks here': Why you still don't know when the Eglinton LRT will start running . . April 22, 2023 . April 22, 2023 . April 22, 2023 . https://web.archive.org/web/20230422205616/https://www.thestar.com/news/gta/2023/04/22/something-really-stinks-here-why-you-still-dont-know-when-the-eglinton-lrt-will-start-running.html . live.
  110. Web site: Never-used Eglinton Crosstown LRT station platform ripped up due to uneven concrete . . April 24, 2023 . https://web.archive.org/web/20230425003747/https://toronto.citynews.ca/2023/04/24/eglinton-crosstown-lrt-sloane-station-platform/ . April 25, 2023 . live.
  111. Web site: Eglinton Crosstown won't open until 2024 — at the earliest . . Brian . Lilley . April 26, 2023 . April 28, 2023 . May 18, 2023 . https://web.archive.org/web/20230518094744/https://torontosun.com/opinion/columnists/crosstown-wont-open-this-year-finch-line-unlikely-as-well . live.
  112. News: Metrolinx CEO sheds light on reasons for Eglinton LRT delays . . April 27, 2023 . April 28, 2023 . April 28, 2023 . https://web.archive.org/web/20230428220330/https://www.thestar.com/news/gta/2023/04/27/metrolinx-ceo-sheds-light-on-reasons-for-eglinton-lrt-delays.html . live.
  113. Web site: Upcoming TTC subway closures and weekend diversions . . May 11, 2023 . https://web.archive.org/web/20230512212914/https://www.ttc.ca/news/2023/May/Upcoming-TTC-subway-closures-and-weekend-diversions . May 12, 2023 . live.
  114. Web site: Michael . Ranger . Eglinton Crosstown won't open until 2024, construction group to take legal action: Metrolinx . CityNews . May 16, 2023 . May 16, 2023 . May 16, 2023 . https://web.archive.org/web/20230516163903/https://toronto.citynews.ca/2023/05/16/eglinton-crosstown-metrolinx-ttc-crosslinx/ . live.
  115. News: Metrolinx refuses to say when long-delayed Eglinton Crosstown LRT might open . . September 27, 2023.
  116. News: Metrolinx CEO still unable to give an opening date for years-delayed Eglinton Crosstown LRT . . December 8, 2023.
  117. News: TTC budget plans on Eglinton Crosstown and Finch West LRTs opening in the fall . . December 15, 2023.
  118. Web site: 'Major construction' complete on Eglinton Crosstown but software and quality assurance issues outstanding: Metrolinx . . March 25, 2024.
  119. News: Report sheds light on beleaguered Eglinton Crosstown LRT’s progress . . 2024-07-08 .
  120. Web site: Request for Qualifications Issued for Tunnelling Works on Scarborough Subway Extension and Eglinton Crosstown West Extension . May 6, 2023 . Infrastructure Ontario . en . May 6, 2023 . https://web.archive.org/web/20230506033702/https://www.infrastructureontario.ca/en/news-and-media/news/advance-tunnel-eglinton-crosstown-west-extension/request-for-qualifications-issued-for-tunnelling-works/ . live.
  121. Web site: Contract Awarded for Eglinton Crosstown West Extension Advance Tunnel Project . May 6, 2023 . Infrastructure Ontario . en . May 6, 2023 . https://web.archive.org/web/20230506033655/https://www.infrastructureontario.ca/en/news-and-media/news/advance-tunnel-eglinton-crosstown-west-extension/contract-awarded-for-eglinton-crosstown-west-extension-advance-tunnel-project/ . live.
  122. Web site: August 5, 2022 . Second tunnel starts as Rexy joins Renny in tunnelling the Eglinton Crosstown West Extension . live . https://web.archive.org/web/20220806205442/https://blog.metrolinx.com/2022/08/05/second-tunnel-starts-as-rexy-joins-renny-in-tunnelling-the-eglinton-crosstown-west-extension/ . August 6, 2022 . Metrolinx.
  123. Web site: Metrolinx - Abstract - SQ-2021-CSUB-101 - Sq-2021-csub-101: Prequalification For Design Build Of The Elevated Guideway (sc . November 22, 2022 . www.metrolinx.merx.com . November 22, 2022 . https://web.archive.org/web/20221122051623/https://www.metrolinx.merx.com/public/solicitations/2050395854/abstract . live.
  124. Web site: Contract awarded for Eglinton Crosstown West Extension guideway . . December 18, 2023 . https://web.archive.org/web/20231219020357/https://www.metrolinx.com/en/news/contract-awarded-for-eglinton-crosstown-west-extension-guideway . December 19, 2023 . live.
  125. Web site: Metrolinx has awarded the contract for the second underground segment of the Eglinton Crosstown West Extension. . . 2024-02-20 . https://web.archive.org/web/20240221222903/https://www.metrolinx.com/en/news/second-tunnelling-contract-awarded-for-eglinton-crosstown-west-extension . 2024-02-21 . live . mdy-all.
  126. Web site: Callan . Isaac . 25 March 2024 . Ford government prepares to build stations for Eglinton Crosstown West Extension . 2024-03-27 . Global News . en-US.
  127. Web site: Eglinton Crosstown West Extension – Stations, Rail and Systems . 2024-03-27 . Infrastructure Ontario . en.
  128. Web site: Eglinton Crosstown West Extension . 2024-03-11 . www.metrolinx.com . en.
  129. Web site: Progress updates . 2024-03-11 . Pearson Airport . en . We’re continuing to work with Metrolinx and all levels of government to advance planning and design for the proposed connection of the Eglinton Crosstown West Extension to Toronto Pearson..
  130. Web site: Eglinton Crosstown West Extension.FAQs . 2024-03-11 . www.metrolinx.com . en.
  131. Web site: City of Toronto: Get Involved > Eglinton Crosstown Light Rail Transit (LRT) > Frequently Asked Questions > Stations and Stops . . August 20, 2011 . October 24, 2011 . https://web.archive.org/web/20111021061801/http://www.toronto.ca/involved/projects/eglinton_crosstown_lrt/index.htm . October 21, 2011.
  132. Web site: Metrolinx's Eglinton West LRT Business Case Goes Underground . . Robert . Mackenzie . March 17, 2020 . September 21, 2020 . December 3, 2020 . https://web.archive.org/web/20201203230017/https://urbantoronto.ca/news/2020/03/metrolinxs-eglinton-west-lrt-business-case-goes-underground . live.
  133. Web site: Crosstown projects sees new track brought in for light rail vehicles . . April 29, 2021 . April 29, 2021 . https://web.archive.org/web/20210429190019/https://blog.metrolinx.com/2021/04/29/crosstown-projects-sees-new-track-brought-in-for-light-rail-vehicles/ . April 29, 2021.
  134. Web site: Eglinton Crosstown West Extension - LIVE Meeting . https://ghostarchive.org/varchive/youtube/20211221/jLHtUTYBAu0 . December 21, 2021 . live . . August 19, 2021 . 0:28:33–0:30:37.
  135. Web site: Science Centre Station and West At-Grade (Sunnybrook Park Stop to O'Connor Stop) Open House . . 29 . November 14, 2017 . November 14, 2017 . November 16, 2017 . https://web.archive.org/web/20171116074929/http://www.thecrosstown.ca/news-media/whats-new/science-centre-station-and-west-at-grade-sunnybrook-park-stop-to-oconnor-stop-o . live.
  136. Web site: The Eglinton Crosstown LRT is going green . . August 4, 2021 . August 30, 2021 . August 31, 2021 . https://web.archive.org/web/20210831014541/https://blog.metrolinx.com/2021/08/04/the-eglinton-crosstown-lrt-is-going-green/ . live.
  137. Web site: Stations and Stops . Metrolinx . January 10, 2018 . January 14, 2018 . https://web.archive.org/web/20180114172547/http://thecrosstown.ca/stations_stops . live.
  138. News: Toronto Star . Eglinton West station to become 'Cedarvale' because of Crosstown LRT . Tess . Kalinowski . November 24, 2015 . November 24, 2015 . November 24, 2015 . https://web.archive.org/web/20151124203734/http://www.thestar.com/news/gta/transportation/2015/11/24/eglinton-west-to-become-cedarvale-station-on-crosstown-lrt.html . live.
  139. Web site: Leslie Stop . The Crosstown.ca . January 14, 2017 . https://web.archive.org/web/20141008140223/http://www.thecrosstown.ca/the-project/stations-and-stops/leslie-stop . October 8, 2014 . November 4, 2017 . live.
  140. Web site: Aga Khan & Eglinton . . November 3, 2017 . September 18, 2020 . https://web.archive.org/web/20200918225713/https://www.metrolinxengage.com/en/content/aga-khan-eglinton . dead .
  141. Web site: Wynford Stop . Eglinton Crosstown . February 27, 2017 . November 4, 2017.
  142. Web site: Bermondsey Stop . Eglinton Crosstown . January 14, 2016 . November 4, 2017 .
  143. Web site: Victoria Park Stop . Eglinton Crosstown . May 11, 2018 . April 28, 2020 .
  144. Web site: Pharmacy Stop . Eglinton Crosstown . May 10, 2018 . April 28, 2020.
  145. Web site: Lebovic Stop . Eglinton Crosstown . December 3, 2015 . November 6, 2017 .
  146. Web site: Golden Mile (formerly Warden) Stop . Eglinton Crosstown . January 14, 2016 . November 6, 2017 .
  147. Web site: Birchmount Stop . Eglinton Crosstown . December 3, 2015 . November 7, 2017.
  148. Web site: Ionview Stop . Eglinton Crosstown. Metrolinx . December 5, 2015 . November 7, 2017 .
  149. Web site: Eglinton Crosstown Line Station and Stop Names . Metrolinx . October 2, 2015 . October 2, 2015 . October 21, 2020 . https://web.archive.org/web/20201021220535/https://www.metrolinxengage.com/en/content/eglinton-crosstown-line-station-and-stop-names . dead.
  150. Web site: Ferrand Stop . Eglinton Crosstown . February 27, 2017 . November 3, 2017 . November 7, 2017 . https://web.archive.org/web/20171107025055/http://www.thecrosstown.ca/the-project/stations-and-stops/ferrand-stop . dead .
  151. Web site: Eglinton Crosstown station name sparks contentious Metrolinx debate . Toronto Star . January 15, 2016 . January 15, 2016 . Kalinowski . Tess.
  152. News: Palamarchuk . Andrew . Metrolinx honours businessmen Karim Hakimi and Joe Lebovic . May 25, 2021 . Toronto.com . May 9, 2018.
  153. Web site: Line 5 Eglinton Station Names . November 23, 2015 . Board Presentation . Toronto Transit Commission . In order to reduce confusion with Eglinton Station and Line 5 Eglinton, Eglinton West Station will be renamed. ... TTC staff evaluated the initial report and the proposed names and provided feedback and recommendations. A primary TTC concern was to avoid replication and redundancy with existing TTC station names. The proposed names are unique and are not likely to be confused with existing station names. . November 30, 2015 . https://web.archive.org/web/20210831143710/http://ttc.ca/About_the_TTC/Commission_reports_and_information/Commission_meetings/2015/November_23/Reports/Eglinton_Line_Station_Names__Combined_Report.pdf . August 31, 2021.
  154. Web site: The Sheppard Subway - Transit Toronto - Content. transittoronto.ca. May 16, 2023. May 11, 2023. https://web.archive.org/web/20230511135419/https://transittoronto.ca/subway/5110.shtml. live.
  155. News: Colin . D'Mello . 2023-04-20 . Ford government to rename Science Centre subway station in Toronto . Global News . 2023-04-20.
  156. Web site: Rob. Ferguson. Robert. Benzie. 2024-06-21 . Ford government closing Ontario Science Centre today after report found roof in danger of collapsing . 2024-06-21 . Toronto Star . en.
  157. News: Art installations will enliven Eglinton Crosstown LRT . . Ben . Spurr . January 15, 2018 . January 18, 2018 . January 18, 2018 . https://web.archive.org/web/20180118061449/https://www.thestar.com/news/gta/transportation/2018/01/15/art-installations-will-enliven-eglinton-crosstown-lrt.html . live.
  158. News: How will the Eglinton Crosstown LRT's automatic train control work? We break down every major element in an infographic . Metrolinx News . . December 9, 2019 . January 9, 2020 . https://web.archive.org/web/20200109215906/https://blog.metrolinx.com/2019/12/09/how-will-the-eglinton-crosstown-lrts-automatic-train-control-work-we-break-down-every-major-element-in-an-infographic/ . January 9, 2020.
  159. Web site: Steve Munro . Munro . Steve . Metrolinx Announces Design Changes and Public Meetings on Eglinton LRT (Update 8) . June 17, 2013 . Steve Munro . June 17, 2013 . March 4, 2015 . https://web.archive.org/web/20150304012121/http://stevemunro.ca/2013/06/17/metrolinx-announces-design-changes-and-public-meetings-on-eglinton-lrt/ . live.
  160. Web site: Eglinton Crosstown LRT vehicles hit top speeds . . May 6, 2022 . https://web.archive.org/web/20220506161100/https://blog.metrolinx.com/2022/05/06/eglinton-crosstown-lrt-vehicles-hit-top-speeds-as-testing-continues/ . May 6, 2022 . live.
  161. Web site: TTC/City Of Toronto . Eglinton Crosstown Environmental Report . March 2010 . April 8, 2019 . May 26, 2021 . https://web.archive.org/web/20210526024130/http://thecrosstown.ca/sites/default/files/pdf/reports/Crosstown-LRT-Environmental-Project-Report/chapter-3-project-description-sections-3-1-to-3-4.pdf . live.
  162. News: Metrolinx threatens legal action over late delivery of light rail vehicles . . Ben . Spurr . July 20, 2016 . July 20, 2016 . July 20, 2016 . https://web.archive.org/web/20160720112525/https://www.thestar.com/news/gta/2016/07/20/metrolinx-threatens-legal-action-over-late-delivery-of-light-rail-vehicles.html . live.
  163. News: Report outlines steep costs of running new Toronto transit lines . . Ben . Spurr . Jennifer . Pagliaro . October 31, 2016 . October 31, 2016 . November 1, 2016 . https://web.archive.org/web/20161101102116/https://www.thestar.com/news/gta/2016/10/31/report-outlines-steep-costs-of-running-new-toronto-transit-lines.html . live.
  164. Web site: Eglinton Crosstown LRT Updates – July 2017 . . July 14, 2017 . July 14, 2017 . April 30, 2021 . https://web.archive.org/web/20210430151412/https://mailchi.mp/metrolinx/eglinton-crosstown-lrt-updates?e=67918bdda5 . live.
  165. Web site: Metrolinx enhances platform safety on Eglinton Crosstown LRT . . May 31, 2022 . https://web.archive.org/web/20220601210122/https://blog.metrolinx.com/2022/05/31/metrolinx-enhances-platform-safety-on-eglinton-crosstown-lrt/ . June 1, 2022 . live.
  166. News: Transit City measures up to international standard . . January 6, 2010 . October 4, 2014 . October 19, 2012 . https://web.archive.org/web/20121019162046/http://www.thestar.com/news/gta/transportation/article/746626--transit-city-measures-up-to-international-standard . live.
  167. Web site: The Toronto Flexity Freedom Light Rail Vehicles . Transit Toronto . James . Bow . June 13, 2019 . February 22, 2020.
  168. News: Metrolinx in talks with another company to replace Bombardier vehicles as fears mount over $500,000 a day late fees . . Ben . Spurr . March 2, 2017 . May 12, 2017 . April 10, 2017 . https://web.archive.org/web/20170410050416/https://www.thestar.com/news/gta/2017/03/02/metrolinx-talking-with-another-supplier-for-eglinton-crosstown-vehicles-amid-bombardier-legal-battle.html . live.
  169. Web site: Province had no choice but to seek Bombardier substitute for Eglinton LRT: Del Duca . Spurr . Ben . May 12, 2017 . May 12, 2017 . . May 12, 2017 . https://web.archive.org/web/20170512161742/https://www.thestar.com/news/gta/transportation/2017/05/12/province-had-no-choice-but-to-seek-bombardier-substitute-for-eglinton-lrt-del-duca.html . live.
  170. Web site: Metrolinx statement on Alstom/Bombardier . Metrolinx . May 12, 2017 . September 22, 2022 . https://web.archive.org/web/20220922011616/https://www.metrolinx.com/en/aboutus/mediarelations/news/20170512_MetrolinxStatement_AlstomBombardier.aspx . dead.
  171. News: How do TTC's streetcar options compare? It's Bombardier versus Alstom . . Ben . Spurr . May 13, 2017 . May 13, 2017 . June 12, 2018 . https://web.archive.org/web/20180612142349/https://www.thestar.com/news/gta/2017/05/13/how-do-ttcs-streetcar-options-compare-its-bombardier-versus-alstom.html . live.
  172. Web site: Bombardier delivers first LRV for Eglinton Crosstown, on track for TTC streetcar delivery . . January 8, 2019 . January 8, 2019 . January 9, 2019 . https://web.archive.org/web/20190109155504/https://toronto.citynews.ca/2019/01/08/bombardier-delivers-first-lrv-for-eglinton-crosstown-on-track-for-ttc-streetcar-delivery/ . live.
  173. Web site: Keele Street to Jane Section and Black Creek Maintenance & Storage Facility Environmental Project Report Addendum Online Consultation . 2016 . Metrolinx . Ultimate storage yard capacity of 162 vehicles; . July 25, 2016 . https://web.archive.org/web/20160725202126/http://thecrosstown.ca/node/402?device=desktop . live.
  174. News: Down (but not out) Mount Dennis area pins hopes on Metrolinx . . John . Lorinc . November 23, 2012 . https://web.archive.org/web/20160304113854/http://www.theglobeandmail.com/news/toronto/down-but-not-out-mount-dennis-area-pins-hopes-on-metrolinx/article5614315/ . March 4, 2016 . live . March 28, 2013 . A sprawling storage and maintenance facility for the light-rail vehicles will be built on the Kodak site within a few years..
  175. News: Eglinton LRT: Trouble Brewing in Mt. Dennis (Update 2) . Steve . Munro . Steve Munro . February 17, 2010 . March 4, 2015 . https://web.archive.org/web/20150304010743/http://stevemunro.ca/2010/02/17/eglinton-lrt-trouble-brewing-in-mt-dennis/ . live . Some speakers addressed the use of the Kodak lands for the proposed carhouse, and asked that alternative schemes be considered. Part of this relates to a proposed "big box" development on the land. However, Council approved the acquisition of this property, by expropriation if necessary, in December..
  176. News: Residents ask TTC for LRT tunnel through Mount Dennis . . Tess . Kalinowski . February 16, 2010 . October 3, 2013 . https://web.archive.org/web/20131003203624/http://www.thestar.com/news/gta/2010/02/16/residents_ask_ttc_for_lrt_tunnel_through_mount_dennis.html . In addition to the $4.6billion the province has committed to the Eglinton LRT, the centrepiece of Toronto's Transit City plan, the TTC also wants to build a carhouse on the old Kodak lands in Mount Dennis..
  177. Web site: Agenda Item History . September 7, 2020 . app.toronto.ca . March 17, 2016 . https://web.archive.org/web/20160317014722/http://app.toronto.ca/tmmis/viewAgendaItemHistory.do?item=2016.EX13.3 . live.
  178. Web site: Advancing City Priority Transit Expansion Projects – Eglinton East LRT and Waterfront East LRT . . May 25, 2022 . https://web.archive.org/web/20220601141513/https://www.toronto.ca/legdocs/mmis/2022/ex/bgrd/backgroundfile-226594.pdf . June 1, 2022 . live.
  179. Web site: Transit Network Expansion Update . . July 14, 2022 . https://web.archive.org/web/20220709121525/https://ttc-cdn.azureedge.net/-/media/Project/TTC/DevProto/Documents/Home/Public-Meetings/Board/2022/July-14/8_Transit_Network_Expansion_Update.pdf . July 9, 2022 . live.