Dungeness nuclear power stations explained

The Dungeness nuclear power stations are a pair of non-operational nuclear power stations located on the Dungeness headland in the south of Kent, England.

Dungeness A is a legacy Magnox power station consisting of two 250MWe reactors which were connected to the National Grid in 1965 and reached its end of life in 2006.

Dungeness B is an advanced gas-cooled reactor (AGR) power station consisting of two 520MWe reactors, which began operation in 1983 and 1985. They were the first in a series of AGR reactors to be constructed across the UK. In March 2009, unexpected problems discovered during a maintenance shutdown on unit B21 resulted in the reactor remaining offline for nearly 18 months. In 2015, the plant received upgrades and was given a second ten-year life extension to 2028. In September 2018, as both units were shut down for a scheduled maintenance outage, EDF encountered "significant and ongoing technical challenges" which ultimately led to the announcement of its closure on 7 June 2021.

Dungeness A

Dungeness A Nuclear Power Station
Coordinates:50.9132°N 0.9641°W
Country:England
Location:Kent, South East England
Owner:Nuclear Decommissioning Authority
Operator:Magnox Ltd
Th Fuel Primary:Nuclear
Np Reactor Type:Magnox
Np Reactor Supplier:The Nuclear Power Group
Ps Electrical Capacity:500MWe
Ps Cooling Source:Sea water
Ps Units Operational:4 × 142.5MW
Ps Units Decommissioned:2 × 219MWe net
Commissioned:1965
Status:Decommissioning in progress
Decommissioned:2006
Ps Annual Generation:See graph in text

Dungeness A is a legacy Magnox power station that was connected to the National Grid in 1965 and has reached the end of its life. It possessed two nuclear reactors producing 219MW of electricity each, with a total capacity of 438MW.[1] The construction was undertaken by a consortium known as the Nuclear Power Group ('TNPG').[2] The reactors were supplied by TNPG and the turbines by C. A. Parsons & Co.[1] There were originally four × 142.5MW turbo-alternators, these were later down-rated to 106MW machines.[3] Steam pressure and temperature at the turbine stop valves was and .

Electricity output

Electricity output from Dungeness A power station over the period 1966-84 was as follows.Dungeness A annual electricity output GWh.Nuclear fuel for Dungeness power stations can be delivered and removed via a crane loading facility at the end of the 9miles Appledore-Lydd-Dungeness branch railway. This is connected to the Ashford to Hastings line via an east-facing junction located to the west of Appledore station. The close proximity of the Appledore-Lydd-Dungeness branch to the nuclear power stations allow for a more direct route to and from major fuel fabrication sites all whilst minimising the use of road convoys thus lowering traffic impact on nearby communities.[4]

Closure and decommissioning

On 31 December 2006, Dungeness A ceased power generation after over 40 years of operation. Defuelling was completed in June 2012, with all fuel having been sent to Sellafield for reprocessing.[5] After the site was declared fuel-free, demolition works accelerated beginning with the demolition of the turbine hall in June 2015.[6] Similar to other legacy Magnox stations, the site will undergo decommissioning where radiologically contaminated equipment is removed and redundant structures demolished. Once complete, the reactor buildings will be re-cladded to ensure they are able to remain an effective barrier to the elements and the facility will enter a 'care and maintenance' stage.

The care and maintenance stage is part of the Nuclear Decommissioning Authority (NDA) decommissioning strategy and spans an 80+ year period. This waiting period allows for radiation levels within the reactor core to decline and helps to facilitate a smoother demolition process. Dungeness A is due to enter the care and maintenance phase in 2027. Demolition of reactor buildings and final site clearance is planned for 2088 to 2098.[7] The ongoing decommissioning process is being managed by Magnox Ltd, a subsidiary of the NDA.

Dungeness B

Dungeness B Nuclear Power Station
Coordinates:50.9138°N 0.9599°W
Country:England
Location:Kent, South East England
Th Fuel Primary:Nuclear
Status:Defuelling
Construction Began:1965
Commissioned:1983
Decommissioned:2021
Operator:EDF Energy
Ps Units Operational:2 x 660MWe (Operating at ≈545MWe net[8])
Ps Thermal Capacity:2 x [9]
Np Reactor Type:AGR
Np Reactor Supplier:Fairey Engineering Ltd
Ps Electrical Capacity:1,320MWe

Dungeness B is an advanced gas-cooled reactor (AGR) power station consisting of two 1,496MWt reactors, which began operation in 1983 and 1985 respectively. Dungeness B was the first commercial scale AGR power station to be constructed. Its design was based on the much smaller Windscale AGR prototype, the WAGR. The £89million contract was awarded in August 1965 to Atomic Power Construction ('APC'),[10] a consortium backed by Crompton Parkinson, Fairey Engineering, International Combustion and Richardsons Westgarth.[2] The completion date was set as 1970.

During construction, many problems were encountered in scaling up the WAGR design. Problems with the construction of the pressure vessel liner had distorted it, so that the boilers, which were to fit in an annular space between the reactor and the pressure vessel, could not be installed, and the liner had to be partially dismantled and rebuilt. This work cost about £200,000, but there was a huge cost of financing an extra 18 unproductive months for a power station costing around £100million, of which 60% was already complete.[11] Serious problems were also discovered with the design of the boilers, which had to withstand the pounding of hot carbon dioxide, pressurised to 600psi and pumped around the reactor coolant circuit by massive gas circulators. As a consequence, the casings, hangers and tube supports all had to be redesigned. The cost of the modifications, and financing during the delays, caused severe financial pressures for the consortium and its backers, and in 1969 APC collapsed into administration.

The CEGB took over project management, imposed light penalties in order not to cripple Fairey and International Combustion, and appointed British Nuclear Design and Construction (BNDC) as main contractor. In 1971, problems with corrosion of mild steel components in the first generation Magnox reactors gave the designers cause for concern. The Dungeness B restraint couplings - mechanical linkages that held the graphite core in place whilst allowing it to expand and contract in response to temperature changes - were made of mild steel and could be subject to the same corrosion. It was decided to replace them with components made from a new material.[12] In 1972, problems were found with the galvanised wire that was used to attach thermocouples to stainless steel boiler tubes. During heat treatment of the tubes at temperatures up to, the galvanising zinc diffused into the tubes and made them brittle. The cost had by then risen to £170million.[13] By 1975, the CEGB was reporting that the power station would not be completed until 1977 and that its cost had risen to £280million.[14] By 1979, the cost had risen further to £410million.[15]

Reactor 1 first generated power on 3 April 1983, 13 years behind schedule and at a cost of £685million, four times the initial estimate in inflation-adjusted terms.[16] The original construction consortium had collapsed.[17]

As with the "A" station, the turbines were built by C.A. Parsons & Company[1] and the station has two 660MWe turbo-alternator sets, producing a maximum output of 1,320MWe,[9] though net output is 1,090MWe after the effects of house load, and downrating the reactor output due to corrosion and vibration concerns.[18]

In 2005, the station's closure date was extended from 2008 by ten years, which would allow it to continue operating until 2018, 35 years after first power generation.

In March 2009, serious problems were found when Unit 21 was shut down for maintenance, and the reactor remained out of action for almost 18 months.[19] [20] On 24 November 2009, a small fire in the boiler annexe of Unit 22 caused the second reactor to be shut down as well. Subsequently, Unit 22 has been intermittently shut down for up to several months at a time. Unit 21 was restarted in August 2010.[21] [22] [23] Unplanned shutdowns continued into 2011,[24] [25] with 21 down for repairs from November 2011 to March 2012.[26]

In 2015, the plant was given another ten-year life extension, allowing an upgrade to control room computer systems and improved flood defences, taking the accounting closure date to 2028.[27]

Electricity output

In 2015, Dungeness B produced 4.4TWh of energy. The operators claimed that this amounted to a saving of 3.4million tonnes of CO2.[28]

Decommissioning

In September 2018, the Office for Nuclear Regulation (ONR) directed that EDF Energy carry out a reassessment of corrosion of safety-related concealed systems. Inspections showed that seismic restraints, pipework and storage vessels were found to be "corroded to an unacceptable condition", and that would have been the state when the reactor was operating. Remedial measures included the upgrading of more than of pipeline and of carbon dioxide storage vessels. The ONR classified this as a level 2 incident on the International Nuclear Event Scale. Dungeness B was initially expected to return to service in February 2019,[29] [30] later put back to 30 September 2019 to complete inspections.[31] In August 2020, the shut down of units B21 and B22 was extended to December 2020 after being taken offline in September 2018.[32]

On 7 June 2021, EDF announced that Dungeness B would not be restarted and would move into the defuelling phase immediately, once regulatory permissions are granted, citing "station-specific risks within some key components, including parts within the fuel assemblies" identified since September 2018.[33] [34] [35]

EDF has estimated the cost of defuelling Dungeness B at £0.5£1.0billion,[36] with the process expected to take up to ten years.[37] A UK Parliament committee report noted that the cost of decommissioning is shouldered in part by UK taxpayers.[38]

Consideration of Dungeness C

On 15 April 2009, Dungeness was included in a list of 11 potential sites for new nuclear power stations, at the request of EDF Energy, which owns and operates Dungeness B.[39] The government did not include Dungeness C in its draft National Policy Statement published on 9 November 2009, citing environmental reasons and concerns about coastal erosion and associated flood risk.[40] The site was ruled out by Secretary of State for Energy and Climate Change Chris Huhne in October 2010, with the former government's list of eleven potential sites reduced to eight.[41] Despite these environmental concerns, local Conservative MP Damian Collins, supported by some residents, lobbied Parliament to reconsider that position.[42] [43]

HVDC station

From 1961 to 1984, Dungeness power station also housed the mercury arc valves of the static inverter plant converting AC into DC for transmission on HVDC Cross-Channel, the high-voltage direct current power cable carrying electric power across the English Channel to France. In 1983, a more powerful new inverter at Sellindge replaced this facility.

Ownership

Both stations were originally built, owned, and operated by the CEGB. Following privatisation of the electricity supply industry and the later part-privatisation of the nuclear power generating industry they are now owned by two different bodies: the original Magnox station Dungeness A by the non-departmental government body the NDA and newer AGR Dungeness B by EDF Energy.

Location

The stations are built on a large area of open shingle, measuring 12by, which has been deposited by the sea and built up over thousands of years. The entire area is moving slowly north and east as the sea moves the shingle from one side of the headland to the other. It is surrounded by a nature reserve Site of Special Scientific Interest (SSSI). A fleet of lorries is used to continuously maintain shingle sea defences for the plant as coastal erosion would otherwise move shingle away at an estimated rate of 6m (20feet) per year. Around 30000m2 of shingle are moved each year. It seems that deposition on the north shore of the headland does not keep pace with erosion, although the power stations are about 1km (01miles) to the west of that shore. In all, 90000m2 are moved each year along parts of the coast between Pett Level and Hythe. This is necessary for the safety of the entire area including the power stations. During operation, around 100e6l of cooling water was extracted and returned to the sea each hour, after being heated by .

The headland and the coastline between Pett Level and Hythe are volatile. In recorded history Walland Marsh to the west of the power stations has been flooded.[44] In the space of sixty years severe inundation occurred, temporarily bringing the sea inland to Appledore and the original mouth of the River Rother from north of the headland at Romney to the south at Rye Harbour. The site is a few metres above Mean Sea Level and would be isolated in the event of flooding of the magnitude that submerged large areas of East Anglia and the Netherlands in 1953. It has been conjectured that the Great Storm of 1987 did not bring the sea to the stations because there was a low tide at the time. Climate change could cause more frequent and powerful storms, and associated waves and surges are possible though not probable, and might increase the instability of the headland.

In the media

The station was used in the filming of the Doctor Who serial The Claws of Axos in January 1971.[45]

The site provides a key plot point in the 2016 book, Alan Partridge: Nomad.[46]

The station is within sight of artist Derek Jarman's garden at Prospect Cottage.[47] The film The Garden was filmed at the house,[48] and it was the main subject of an episode of BBC's Countryfile in February 2020.[49]

See also

Other sources

  1. Book: Eddison, J . Romney Marsh Survival on a Frontier . Tempus . 2000 . 0-7524-1486-0 . Page 139 also reports the 1990 flooding mentioned above. Page 139 also reports the 1990 flooding mentioned above.
  2. Web site: Romney Marsh . 5 February 2006 .
  3. Web site: Kent Against a Radioactive Environment . 20 March 2006 . dead . https://web.archive.org/web/20060424044401/http://www.kare-uk.org/ . 24 April 2006 . dmy-all .
  4. Web site: British Energy . 16 April 2006 . dead . https://web.archive.org/web/20070928074437/http://british-energy.com/pagetemplate.php?pid=91. . 28 September 2007 . dmy-all .
  5. Web site: industcards . 16 April 2006 .
  6. Web site: Going Critical . 16 April 2006 .

External links

Notes and References

  1. Web site: Industcards.com. www.industcards.com. 23 August 2014. http://arquivo.pt/wayback/20090719150823/http://www.industcards.com/nuclear%2Duk.htm. 19 July 2009. dead. dmy-all.
  2. Web site: The UK Magnox and AGR Power Station Projects. 21 September 2010. 27 April 2020. https://web.archive.org/web/20200427135549/http://www.dalton.manchester.ac.uk/aboutus/reports/papers/uk_consortia1b.pdf. dead.
  3. CEGB Statistical Yearbook (various dates). CEGB, London.
  4. Book: Jacobs, Gerald. Railway Track Diagrams Book 5: Southern and TfL. Trackmaps. 2008. 9780954986643. Bradford on Avon. 18D.
  5. Web site: Decommissioning progress at Dungeness A. World Nuclear News. World Nuclear Association. 1 September 2015. 21 January 2015.
  6. Web site: Dungeness A turbine hall bites the dust. NDA. Nuclear Decommissioning Authority. 1 September 2015. 23 June 2015.
  7. Web site: The 2010 UK Radioactive Waste Inventory: Main Report . Nuclear Decommissioning Agency/Department of Energy & Climate Change . February 2011 . 22 May 2012 . dead . https://web.archive.org/web/20120325081518/http://www.nda.gov.uk/ukinventory/documents/Reports/upload/2010-UK-Radioactive-Waste-Inventory-Main-Report.pdf . 25 March 2012 .
  8. Web site: Dungeness B EDF Energy. 28 April 2014.
  9. Web site: Nonbel . Erik . Description of the Advanced Gas Cooled Type of Reactor (AGR) . IAEA . nks (Nordic Nuclear Safety Research) . 12 February 2020 . AGR IAEA Description . 9 June 2022 . https://web.archive.org/web/20220609170021/https://inis.iaea.org/collection/NCLCollectionStore/_Public/28/028/28028509.pdf . dead .
  10. Web site: Events - World Nuclear Association. www.world-nuclear.org. 11 April 2009. 2 October 2012. https://web.archive.org/web/20121002232858/http://www.world-nuclear.org/sym/2007/archive/2006/hawley.htm. dead.
  11. The Times, Tuesday, 10 December 1968; pg. 24; Issue 57430; col A
  12. The Times, Thursday, 11 March 1971; pg. 19; Issue 58119; col E
  13. The Times, Saturday, 4 November 1972; pg. 19; Issue 58623; col C
  14. The Times, Thursday, 6 November 1975; pg. 20; Issue 59546; col A
  15. The Times, Wednesday, 23 January 1980; pg. 3; Issue 60531; col E
  16. Book: Going Critical: An Unofficial History of British Nuclear Power. Walter C. Patterson. Walter C. Patterson. Paladin. 1985. 0-586-08516-5. 12 June 2009.
  17. News: The Atom in Red, White and Blue . Nuclear Engineering International . 12 October 2022 . 8 November 2022.
  18. Web site: EDF. https://web.archive.org/web/20060501105917/http://www.british-energy.com/pagetemplate.php?pid=91. dead. 1 May 2006. EDF.
  19. Web site: Dungeness B reactor back up after repairs . 21 August 2010.
  20. Web site: No power from Dungeness for seven months so far . 11 February 2010 .
  21. News: Fire shuts nuclear power station . 24 November 2009 . BBC . 24 November 2009.
  22. Web site: One of two nuclear reactors back in action . 18 February 2009 .
  23. Web site: Dungeness reactor back online after repairs . 23 August 2010 .
  24. News: UPDATE 1-UK Hunterston B7 nuclear unit restarts Fri.. https://web.archive.org/web/20120830013120/http://af.reuters.com/article/energyOilNews/idAFLDE7231LW20110304 . dead . 30 August 2012 . 5 March 2011 . Reuters.
  25. News: UK Dungeness 22 unit back on grid since Jul 24-EDF. https://web.archive.org/web/20120923174101/http://af.reuters.com/article/energyOilNews/idAFL6E7IP02Z20110725 . dead . 23 September 2012 . 1 August 2011. Reuters.
  26. News: ABLE-UK nuclear power plant outages. 25 November 2011. Reuters.
  27. News: UK nuclear plant gets ten-year extension . World Nuclear News . 20 January 2015 . 21 January 2015.
  28. Web site: EDF Energy announces 10 more years for Dungeness B. 2015-06-03. EDF France. en-en. 2020-05-21.
  29. News: 24 January 2019 . Dungeness B corrosion rated at INES level 2 . Nuclear Engineering International . 30 January 2019.
  30. Web site: 31 December 2018 . External corrosion affecting multiple systems on a power reactor . 30 January 2019 . Office for Nuclear Regulation . IAEA.
  31. News: 12 March 2019 . Outage extensions for UK's Dungeness and Hunterston . Nuclear Engineering International . 18 March 2019.
  32. News: 12 August 2020 . More delays for restart of UK's Hunterston and Dungeness NPPs . Nuclear Engineering International . 15 August 2020.
  33. Web site: 7 June 2021 . EDF decides to move Dungeness B into defuelling phase . 7 June 2021 . EDF Energy.
  34. Web site: AGR reactors: Examining decommissioning costs of UK fleet .
  35. Web site: Arrangements for decommissioning the AGRs - Nuclear Engineering International .
  36. Web site: Varley . James . 2022-05-02 . AGR reactors: Examining decommissioning costs of UK fleet . 2022-06-11 . en-US.
  37. News: . Dungeness B: Kent's last nuclear power station closes early . BBC News . 8 June 2021 . 7 March 2024.
  38. Web site: Laville . Sandra . 2022-05-20 . UK nuclear power stations' decommissioning cost soars to £23.5bn . 2022-06-11 . The Guardian . en.
  39. News: Dungeness among 11 sites for new nuclear power station. 1 September 2015. Kent and Sussex Courier. This is Kent. 15 April 2009. https://web.archive.org/web/20150923210828/http://www.courier.co.uk/Dungeness-11-sites-new-nuclear-power-station/story-11985330-detail/story.html. 23 September 2015. dead. dmy-all.
  40. News: Press Release - Miliband sets strategic direction for overhaul of energy system. 9 November 2009. Department of Energy and Climate Change. https://web.archive.org/web/20091119060636/http://www.decc.gov.uk/en/content/cms/news/pn130/pn130.aspx. 19 November 2009.
  41. News: Nuclear power: Eight sites identified for future plants. 18 October 2010. BBC News. 18 October 2010.
  42. News: Dungeness C: Third nuclear plant can be achieved, says MP . . 15 February 2013 . 30 July 2018.
  43. House of Commons . 2.37 pm Damian Collins (Folkestone and Hythe) (Con) . 27 May 2010 . 355 . 357.
  44. Book: Eddison, J . Romney Marsh Survival on a Frontier . Tempus . 2000 . 0-7524-1486-0 . 139.
  45. Web site: Doctor Who: The Claws of Axos. Radio Times. Mark Braxton. 28 October 2009. 13 December 2012.
  46. News: Leith . Sam . Alan Partridge: Nomad review – bathos is everywhere, it's glorious . the Guardian . 23 December 2016 . en.
  47. Book: Billinghurst . Jane . Armchair Book of Gardens: A Miscellany . 2011 . Rowman & Littlefield . 978-0-7627-6782-3 .
  48. News: Campaign launched to raise £3.5 million to save Derek Jarman's house for the queer community . 3 February 2020 . PinkNews . 28 January 2020.
  49. Web site: Countryfile - Dungeness . www.bbc.co.uk.