Dehani lift irrigation scheme explained

The Dehani lift irrigation scheme is a technologically sophisticated project to irrigate Vidarbha, a large, semi-arid region of India.

Background

Vidharba is a semi-arid region that has an ailing agricultural community which has huge amounts of debts. This has led to a high farm suicide rate.[1] The Prime Minister has proposed a centrally funded package to irrigate nearly 7000ha and therefore provide economic relief.

Details

The project is being executed by Vidarbha Irrigation Development Corporation and IVRCL Infrastructures and Projects Limited. The region to be irrigated is 6968.01ha in Dehani, Babhulgaon taluk, Yavatmal district, over the river Bembla at Khadasawanga.The project costed INR 1,988,300,000 (1.988 billion)[2] and was completed in 2011.

This project was the first of its kind in India[3] and envisions the drip irrigation of a large area, while making use of the latest in communication technology. The Supervisory Control and Data Acquisition System (SCADA) will interconnect all components of the system via a satellite uplink, making it possible for the central command centre of the irrigation scheme to be able to control all components remotely.

Components

Bembla reservoir

The Bembla dam built over the river Bembla at Khadaksawanga is 7650m (25,100feet) long and 29.15m (95.64feet) high, with a capacity of 322068000m2. The Bembla project currently has a command area of 40170ha, and the completed project will have a command area of 52543ha. The total project cost is expected to be INR 12.8 billion.[4]

Approach channel

A 1700m (5,600feet) approach channel carries water from the Bembla reservoir into the Forebay Stage-1. The channel is of trapezoidal cross-section.[5]

Forebay Stage-1

The forebay is 40m (130feet) long and has an average depth of 12m (39feet). This structure functions as a storage space for water before it is pumped farther ahead.

Pumphouse Stage-1

This pumphouse is attached to the Forebay Stage-1 and has vertical turbine pumps with an installed capacity of 4800HP. Water is pumped from a reduced level of 265m (869feet) to the Main Distribution Chamber Stage-1 up to an elevation of 304m (997feet) via the Rising Mains Stage-1, which consist of one row of 1700mm steel pipe and one row of 900mm steel pipe.

Main Distribution Chamber (MDC) Stage-1

From MDC Stage-1, part of the water enters the forebay of Pumphouse Stage-2, which has an installed vertical turbine pump capacity of 1640HP. The remainder of the water is supplied to 34 Sub Distribution Chambers via pre-stressed concrete pipes which form part of the Gravity Mains.

Sub Distribution Chamber (SDC)

Each SDC is a circular underground tank with a capacity of 150000L. The average depth of each SDC below the ground level is 5m–6mm (16feet–20feetm). Each will service an area of 100ha. Each SDC, along with its associated instrument panel room and transformer, has been allocated a 20by area.

Each SDC has a 100HP pump installed. A trained operator will be employed in each instrument panel room to make the relevant data entries regarding the type of crops on the sub-zones being serviced by that particular SDC. The programme distributes the exact amount of water required in each sub-zone and cuts off the flow when the requirement has been fulfilled.

The entire project has been divided into two stages, the first stage consists of 34 SDCs and the second stage consists of 23 SDCs. In all there will be 57 SDCs servicing the 57 zones that are subdivisions of the command area. Each zone is to be divided into 27 sub-zones. The SCADA system to be implemented is capable of delivering the exact amount of water required at each field according to the cropping pattern. It is proposed to train three representatives of the farming community from each zone, so that they will be able to operate the instrument panel of each SDC. For the initial three years of functioning, the IVRCL personnel will run the entire project, after which the responsibility of the day-to-day activities at the SDC will be handed over to the representatives of the farming community.

Forebay Stage-2

Part of the water stored in the MDC Stage-1 is supplied into this forebay. From here 1640HP vertical turbine pumps (installed in the Pumphouse Stage-2) are used to pump the water farther ahead into the second stage of the project serviced by MDC Stage-2, which will supply 23 more SDCs.

External links

Notes and References

  1. Web site: Vidarbha farmers seek mercy killing . Timesofindia.indiatimes.com . 2006-07-16 . 2016-02-28.
  2. Web site: IVRCL Infrastructures secures orders worth Rs 516.09 Crores . Rupya.com . 2007-02-13 . 2016-02-28.
  3. Web site: http://www.ivrcl.com/ui/pdf/downloads/cor_brochure/IVRCL_BK_Part1.pdf . 26 October 2011 .
  4. Web site: http://www.vidc.gov.in/ceamt/pro/Bembla/SF.htm . 9 August 2009 .
  5. Web site: Dehani Presentation . Scribd.com . 2008-10-17 . 2016-02-28.