DND–KMP Expressway explained

DND–KMP Expressway
Alternate Name:(NH–148NA)[1]
Header Type:UC
Country:IND
States:Delhi, Haryana and Uttar Pradesh
Cities:New Delhi, Noida, Faridabad, Ballabgarh, Sohna & Jewar
Established:12 February 2023 (partially)
Maint:National Highways Authority of India (NHAI)
Map Custom:yes
Length Km:59
Direction A:North
Terminus A:DND Flyway, Maharani Bagh, Delhi
Junction:Spur to Jewar Airport
Direction B:South
Terminus B:KMP, Khalilpur, Nuh district, Haryana

The DND–Faridabad–KMP Expressway, formally known as NH-148NA is a 59 km long, 6-lane wide access-controlled expressway in Delhi NCR, India.[2] It connects the junction of DND Flyway and Ring Road at Maharani Bagh in Delhi with KMP Expressway at Khalilpur, Nuh district (near Sohna) in Haryana. The NH-148NA is a spur (branch) of Delhi–Mumbai Expressway project. This expressway will have an additional 31 km long spur from Sector-65, Faridabad bypass to Jewar Airport.[3]

The DND/ Maharani Bagh interchange and Kalindi Kunj metro are the 2 entry points in the state of Delhi. In Haryana, it passes entirely through existing Faridabad bypass road. The HSVP has transferred the Faridabad bypass to NHAI for the construction of NH–148NA highway. The construction work was started in May 2021 and 20 Km stretch from KMP interchange to NH-2 interchange at Kail Gaon (Ballabhgarh) has been opened on 12 February 2023. The entire project is expected to get completed by January 2025.

Route

The NH–148NA highway connects Sarai Kale Khan & Kalindi Kunj (Delhi), Noida, Jewar, Faridabad and Ballabhgarh to the main alignment of via an interchange at Khalilpur, Nuh district (Haryana).[4] [5]

NCT of Delhi (12 km)

See also: NCT of Delhi.

Haryana (47 km)

See also: Haryana.

KMP interchange

After reaching KMP interchange at Khalilpur, traffic coming from Maharani Bagh (Delhi) and Faridabad bypass has 2 options:

1. They can turn south towards Dausa and Mumbai, or turn north towards Gurgaon and Sohna.

2. They can also use KMP Expressway and turn east for Palwal and turn west for Manesar.

Construction

The construction work of the 'DND–Faridabad–KMP' section was awarded by the National Highways Authority of India (NHAI) to Dineshchandra R. Agrawal Infracon Private Limited (DRA Infracon) in August 2020.[7] This project will reduce congestion on Ashram to Ballabhgarh route (via Badarpur). In Haryana it will have multiple Flyovers and a 3-lane service road on either side of Faridabad bypass road.

7 km out of 9 km route of Package-1 in Delhi state will be elevated with two-level crossings at 4 locations of the Delhi Metro rail line (near Okhla Vihar and Kalindi Kunj metro station), making it the 1st expressway in India to cross above elevated metro rail line. NH-148NA exits Delhi at MCD Toll Plaza (near Mithapur) which is 12.5 km from the DND starting point.

Packages

The NHAI has divided the construction work of 59 km long DND–Faridabad–KMP section of Delhi–Mumbai Expressway project into three packages and awarded it to DRA Infracon. Its construction cost is around 5,332 crores (including land acquisition cost).[8] [9]

Sr NoPackageLength in kmValue in croresState
1.Junction of DND Flyway & Ring Road in Delhi to Jaitpur–Pushta road in Delhi09 1,881Delhi
2. Jaitpur–Pushta road in Delhi to Sector-62/65 dividing road in Faridabad241,832Delhi & Haryana
3.Sector-62/65 dividing road in Faridabad to KMP Expressway at Khalilpur in Nuh district261,619Haryana

Note:

Jewar Airport link

The NHAI had announced in August 2021, that an additional 31 km long spur will also be constructed from Noida International Airport in Jewar to Faridabad bypass road on this expressway.[10] Tender for this Spur package has been awarded by the NHAI to Apco Infratech Pvt. Ltd. on 29 July 2022.

Delhi–Mumbai Expressway

The construction work of Delhi–Mumbai Expressway is divided by NHAI into 4 sections with a total of 52 tenders/ construction packages as given below. The entire 1,350 km long expressway is expected to be completed by January 2025.

SectionLength in kmNo. of packagesState-wise packages
DNDFaridabadKMP59 031 in Delhi and 2 in Haryana
844313 in Haryana, 13 in Rajasthan, 9 in Madhya Pradesh and 6 in Gujarat
35413
9205

Status updates

See also

Notes and References

  1. Web site: Faridabad bypass renamed as DND-KMP Expressway on Google Maps . Hindustan . 23 July 2023 .
  2. Web site: 59-km six-lane road to connect DND, Ring Road with Delhi-Mumbai expressway - delhi news. Hindustan Times. 4 August 2020.
  3. Web site: Delhi-Mumbai Expressway will be linked to Jewar Airport . Times of India . 8 July 2022 .
  4. Web site: Jewar Airport और Delhi-Mumbai एक्‍सप्रेसवे से लिंक रहेगा DND-Faridabad-KMP Expressway, रूट मैप देखिए . Navbharat Times. 25 March 2023 .
  5. Web site: DND-Faridabad-KMP Expressway to be connected with Delhi-Mumbai Expressway, Jewar Airport, check routes . DNA India . 27 March 2023 .
  6. Web site: दिल्ली-मुंबई एक्सप्रेस-वे पर हरियाणा के फरीदाबाद से आ रही खुशखबरी, जानें फायदा. Dainik Jagran . 8 April 2022 .
  7. Web site: Work awarded for new Delhi-Mumbai e-way link . Times of India .
  8. Web site: Delhi NCR: Six-lane highway to connect ring road-DND junction with Delhi-Mumbai Expressway . Times Now . 4 August 2020.
  9. Web site: Contract award status of Delhi–Mumbai Expressway as of May 2021 . NHAI . 28 May 2021 .
  10. Web site: Jewar International Airport will be linked to Delhi-Mumbai Expressway. News18 . 16 September 2021 .
  11. Web site: Nitin Gadkari to lay foundation stone for Rs 3,580 crore project to decongest Delhi . Economic Times .
  12. Web site: NHAI invites bids for highways under Bharatmala Pariyojana . Construction Week Online . 22 December 2019.
  13. Web site: Soil testing for Delhi-Mumbai Expressway link begins in Faridabad . Times of India.
  14. Web site: NHAI to start work on crucial decongestion projects in Delhi this year . Hindustan Times. 10 February 2021.
  15. Web site: NHAI to raze 500 structures for Delhi-Mumbai Expressway . The Tribune . 9 October 2021 .
  16. Web site: दिल्ली-मुम्बई एक्सप्रेसवे के पहले चरण का निर्माण शुरू, नोएडा से बनकर जा रहा प्री-कास्ट मैटेरियल . TriCity Today . 22 March 2022 .
  17. Web site: Tender opens for Expressway to link Faridabad & Jewar Airport . The Tribune . 31 July 2022 .
  18. Web site: Noida Airport: 2 साल में दिल्ली-मुंबई एक्सप्रेसवे से जुड़ेगा जेवर एयरपोर्ट, 6 लेन पर खर्च होंगे 16.60 अरब, NHAI ने निकाला टेंडर . Navbharat Times. 31 July 2022 .
  19. Web site: Ballabhgarh: Delhi-MumbaiExpressway link opens this week . The Times of India. 20 February 2023 .
  20. Web site: Entire stretch from DND Flyway to Delhi-Mumbai Expressway to be opened by year end: Nitin Gadkari . The Times of India . 15 Feb 2024.