Comanche Solar Project Explained

Comanche Solar Project
Coordinates:38.2053°N -104.5667°W
Country:United States
Location:Pueblo, Colorado
Status:O
Construction Began:August 2015
Commissioned:September 2016
Cost:$253 million
Owner:Novatus Energy
Operator:Swinerton Renewable Energy
Solar Type:Flat-panel PV
single-axis tracking
Ps Site Area:900acres
Ps Electrical Capacity:156 MWp, 120 MWAC
Ps Electrical Cap Fac:27.7% (average 2017-2020)
Ps Annual Generation:291 GW·h, 323 MW·h/acre

The Comanche Solar Project is a 120 megawatt (MWAC) photovoltaic power station near the city of Pueblo, Colorado. It became the largest solar facility in the state when it came online in late 2016. The electricity is being sold to Public Service of Colorado, a subsidiary of Xcel Energy, under a 25-year power purchase agreement (PPA). Xcel determined through an open bid process that the PPA's terms were competitive with natural gas.[1] [2]

Construction details

The project occupies a total of about 900 acres split into two parcels that are adjacent to the coal-fired Comanche Generating Station; thus providing access to existing high-capacity substation and transmission infrastructure. It uses 502,056 Trina Solar polycrystalline silicon panels that are mounted in rows and onto single-axis trackers.[3] [4] The rows are organized into 75 blocks, and the electricity produced from each block is connected to the electric grid through an inverter built by TMEIC.

In early 2015, SunEdison awarded an EPC contract for the project to Renewable Energy Systems (RES) of Broomfield. Work at the site began in August and proceeded through the winter months, with most balance of system (BOS) construction activities completed by April 2016. The panel installation, electrical integration, and acceptance testing proceeded through the summer, enabling the start of commercial operations in September. The completed facility is operated and maintained by Swinerton Renewable Energy.

Development and ownership history

The project was originated by Community Energy, which completed many of the initial negotiations such as the grid integration strategy, land leases, and required permits.[5] SunEdison announced its acquisition of the project in July 2014 concurrent with the results of Xcel's open solicitation/competitive bid process.[6] In August, SunEdison announced its strategy to finance the $253 million Comanche project using a novel special purpose vehicle named "First Reserve".[7] [8] As designed with its partner Everstream Capital Management, this funding mechanism - a special type of warehouse - would expand to meet demand from new investors as Comanche (and future projects) moved into construction, thus reducing the need for incremental equity contributions by SunEdison while preserving a first right of call provision for its TerraForm Power yield co.[9] [10]

With all requirements in place, the start of construction was announced in August 2015.[11] Most BOS work was complete by the time that SunEdison filed for Chapter 11 bankruptcy protection on April 21, 2016. Nevertheless, work at Comanche and other SunEdison projects continued unabated due to the company's receipt of $300 million in bankruptcy debt financing.[12] On May 16, 2017 Novatus Energy announced its purchase of the operating Comanche facility, although terms were not disclosed.[13] [14] [15]

Electricity production

Generation (MW·h) of Comanche Solar [16]
Year Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Total
201629,335 23,889 17,647 13,72184,592
201711,466 17,862 24,991 27,586 32,522 35,245 30,570 25,582 21,429 25,376 16,188 16,621285,438
201815,452 18,172 23,498 28,477 32,816 35,266 30,739 30,690 29,497 21,995 18,131 13,127297,860
201915,125 15,937 23,742 27,950 29,756 33,470 31,681 32,251 26,622 26,168 16,264 11,855290,821
202016,771 17,112 26,628 28,533 33,986 32,285 31,235 29,451 26,492 19,131 16,898 12,209290,731
202113,370 11,618 18,124 21,098 21,311 29,678 33,758 30,274
Average Annual Production (years 2017-2020) ---> 291,122

See also

External links

Notes and References

  1. Web site: Pueblo Solar Power - Renewable Energy Systems has wrapped up construction of the largest solar facility in Colorado . altenerg.com . September 2016 . February 15, 2019 .
  2. Web site: Coming soon: The biggest solar farm east of the Rocky Mountains . fortune.com . August 20, 2015 . February 15, 2019.
  3. Web site: Swinerton - Comanche . swinertonrenewable.com . February 15, 2019.
  4. Web site: Novatus - Comanche . novatusenergy.com . February 15, 2019.
  5. Web site: Community Energy's 120 MW Comanche Solar Project Provides Bulk of Solar Power in Approved Xcel Energy Resource Plan . communityenergysolar.com . March 4, 2014 . February 15, 2019.
  6. Web site: SunEdison acquires Comanche Solar project from Community Energy . renewable-technology.com . July 24, 2014 . February 15, 2019.
  7. Web site: SunEdison Closes $253 Million of Financing, Breaks Ground on 156 Megawatt Solar Project in Colorado . prnewswire.com . August 20, 2015 . February 15, 2019.
  8. Web site: SunEdison Turns To ‘Warehouse’ To Fund Comanche Solar And Other Large-Scale Projects . solarindustrymag.com . August 25, 2019 . February 15, 2019.
  9. Web site: Everstream Capital Management - Comanche . everstreamcapital.com . February 15, 2019 .
  10. Web site: Warehouse 8K . sec.gov . May 6, 2015.
  11. Web site: RES Selected to Construct Comanche Solar Project . prnewswire.com . August 20, 2015 . February 15, 2019.
  12. Web site: SunEdison files for Chapter 11 bankruptcy . Bomey . Nathan . April 21, 2016 . USA TODAY . February 3, 2019.
  13. Web site: Novatus Energy acquires the 156 MW Comanche solar project in Colorado . novatusenergy.com . May 16, 2017 . February 15, 2019.
  14. Web site: Novatus goes deeper into solar with Colorado’s largest plant . pv-magazine-usa.com . May 19, 2017 . February 15, 2019.
  15. Web site: Novatus to Acquire First Reserve Comanche Project . relationshipscience.com . March 13, 2017 . February 15, 2019.
  16. Web site: Comanche Solar, Monthly . Electricity Data Browser . . November 8, 2021.