Cinere–Serpong Toll Road Explained

Country:IDN
Type:Toll
Cinere–Serpong Toll Road
Map Custom:yes
Maint:PT Cinere Serpong Jaya (CSJ)
Length Km:10.1
Terminus A:Serpong Interchange
Direction A:Northwest
Direction B:Southeast
Terminus B:Cinere
Formed:1 April 2021

Cinere–Serpong Toll Road is one of the toll roads which are part of the Jakarta Outer Ring Road 2 which connects the Kunciran–Serpong Toll Road in the west and the Cinere–Jagorawi Toll Road in the east. This toll road that connects South Tangerang with Depok, crosses several areas, such as Jombang, Ciputat, Pamulang, Pondok Cabe and Cinere. The toll road is managed by PT Cinere Serpong Jaya (CSJ), the majority of whose shares are owned by PT Jasa Marga.[1] [2]

History

The toll road project was initiated in 2006, but the construction of the project was halted and delayed due to land acquisition issue, which again restarted in September 2017 after being halted for approximately eight years.[3] The toll road was previously expected to be operational in 2019, [4] however, the first section was inaugurated in 1 April 2021 along with Cengkareng–Batu Ceper–Kunciran Toll Road.[5] While the second section is currently undergoing land acquisition phase which will be used to connect this toll road with Cinere–Jagorawi Toll Road, this section is expected to be operational in 22 December 2023.[6] On 22 December 2023, the entirety of the toll road has been inaugurated.[7]

Sections

This toll road is divided into two sections:

See also

Notes and References

  1. News: Jasa Marga, Waskita Karya to build Cinere–Serpong toll road. The Jakarta Post. 19 September 2018.
  2. Web site: Tol Cinere–Serpong Mulai Dibangun Awal 2017. Dana. Aditiasari.
  3. News: Tol Cinere-Serpong Mulai Dibangun Awal 2017. id. Cinere-Serpong Toll Road Construction to Start in 2017. finance.detik.com. Detik.com. Aditiasari. Dita. 16 November 2016. 7 November 2022.
  4. News: Cinere–Serpong Toll to Operate in 2019. Tempo. 19 September 2018.
  5. News: DIRESMIKAN PRESIDEN JOKOWI, 2 RUAS TOL JORR 2 JALAN TOL CENGKARENG - BATUCEPER - KUNCIRAN DAN TOL SERPONG CINERE SEKSI I. id. Inaugurated by President Jokowi, 2 toll roads Cengkareng-Batuceper-Kunciran and Serpong-Cinere section 1. Badan Pengatur Jalan Tol. 3 November 2022. 1 April 2021.
  6. News: Ini Alasan Tol Serpong-Cinere Tak Kunjung Beroperasi. id. These are the reasons why Serpong-Cinere Toll Road is yet to be Operating. cnbcindonesia.com. CNBC Indonesia. 19 May 2022. Emir. Yanwardhana. 7 November 2022.
  7. News: Hore! Jalan Tol Serpong-Cinere Seksi 2 Pamulang-Cinere Sudah Bisa Dilalui. Yudho. Winarto . Amalia Nur. Fitri. Kontan. id.
  8. Web site: Jalan Tol Serpong – Cinere (10,14 km) – KPPIP. 2018-09-19. 2017-11-07. https://web.archive.org/web/20171107011115/https://kppip.go.id/proyek-strategis-nasional/a-sektor-jalan/jalan-tol-serpong-cinere-1014km/. dead.