Chernobyl New Safe Confinement Explained

Chernobyl New Safe Confinement
Native Name:Ukrainian: Новий чорнобильський саркофаг
Native Name Lang:uk
Map Type:Ukraine
Alternate Names:New Shelter
Status:Operational
Building Type:Containment structure
Location:Chernobyl Nuclear Power Plant
Location Town:Pripyat
Location Country:Ukraine
Start Date:September 2010
Completion Date:November 2016[1]
Destruction Date:-->
Cost:€2.1 billion
Client:Government of Ukraine
Height:108m (354feet)
Weight:[2]
Other Dimensions:Span 260m (850feet), external length 165m (541feet)
Structural System:Arch-shaped lattice, clad with sandwich panels
Material:Steel, with polycarbonate inner panels
Main Contractor:Novarka with 50/50 partners Vinci Construction Grands Projets and Bouygues Travaux Publics as well as Mammoet for conveyance
Website:https://www.chnpp.gov.ua/en/

The New Safe Confinement (NSC or New Shelter) is a structure put in place in 2016 to confine the remains of the number 4 reactor unit at the Chernobyl Nuclear Power Plant, in Ukraine, which was destroyed during the Chernobyl disaster in 1986. The structure also encloses the temporary Shelter Structure (sarcophagus) that was built around the reactor immediately after the disaster. The New Safe Confinement is designed to prevent the release of radioactive contaminants, protect the reactor from external influence, facilitate the disassembly and decommissioning of the reactor, and prevent water intrusion.[3]

The New Safe Confinement is a megaproject that is part of the Shelter Implementation Plan and supported by the Chernobyl Shelter Fund. It was designed with the primary goal of confining the radioactive remains of reactor 4 for 100 years.[4] It also aims to allow for a partial demolition of the original sarcophagus, which was hastily constructed by Chernobyl liquidators after a beyond design-basis accident destroyed the reactor.[5] The word is used rather than the traditional to emphasize the difference between the containment of radioactive gases—the primary focus of most reactor containment buildings—and the confinement of solid radioactive waste, which is the primary purpose of the New Safe Confinement.[6]

In 2015, the European Bank for Reconstruction and Development (EBRD) stated that the international community was aiming to close a €100 million funding gap, with administration by the EBRD in its role as manager of the Chernobyl decommissioning funds. The total cost of the Shelter Implementation Plan, of which the New Safe Confinement is the most prominent element, is estimated to be around €2.15 billion (US$2.3 billion). The New Safe Confinement accounts for €1.5 billion.

The French consortium Novarka with partners Vinci Construction Grands Projets and Bouygues Travaux Publics designed and built the New Safe Confinement. Construction was completed at the end of 2018.[7]

Legacy structure

See main article: Chernobyl Nuclear Power Plant sarcophagus. The original shelter, formally referred to as the Shelter Structure and often called the sarcophagus, was constructed between May and November 1986. It was an emergency measure to confine the radioactive materials within reactor 4 at the Chernobyl Nuclear Power Plant. The shelter was constructed under extreme conditions, with very high levels of radiation, and under extreme time constraints. The Shelter Structure was moderately successful in confining radioactive contamination and providing for post-accident monitoring of the destroyed nuclear reactor unit; it has been estimated that up to 95% of the original radioactive inventory of reactor 4 remains inside the ruins of the reactor building.[8]

The Shelter Structure is primarily supported by the damaged remains of the reactor 4 building. These are largely considered to be structurally unsound as a result of explosive forces caused by the accident. Three major structural members support the roof of the Shelter Structure. Two beams, usually referred to as B-1 and B-2, run in an east-west direction and support the roof beams and panels. A third, more massive member, the "Mammoth Beam", spans the largest distance across the roof from east to west and assists in supporting the roof beams and panels. The roof of the shelter consists of diameter steel pipes laid horizontally north to south, and steel panels that rest at an angle, also in the north-south direction.

The Shelter Structure was never intended to be a permanent containment structure.[9] Its continued deterioration has increased the risk of its radioactive inventory leaking into the environment. Between 2004 and 2008, workers stabilized the roof and western wall of the shelter. However, construction of the New Safe Confinement was necessary to continue confining the radioactive remains of Chernobyl Nuclear Power Plant reactor 4.

Further upgrades to the area in preparation for New Safe Confinement construction were completed in 2010. These included road and rail connections, site services (power, water, drains, and communications), facilities for workers (including medical and radiation protection facilities), and the installation of a long-term monitoring system.[10]

International design competition

In 1994, Ukraine's government held an international competition for proposals to replace the sarcophagus.[11]

In the autumn of 1992, Design Group Partnership (DGP) of Manchester was invited to assist the Atomic Energy Authority (AEA) for the UK's submission for the international competition organized by the Ukrainian government.

DGP's senior management was assembled to generate a solution. David Haslewood suggested an arch, built off-site, and then slid over the existing Soviet-built sarcophagus because:

Of the 394 entries, only the British submission proposed a sliding arch approach.[12] There was no top design choice, but the French submission came as second best with the UK and German proposals coming joint third.

Subsequently, a pan-European study (the TACIS programme) re-examined the proposals of the competition's top three finalists. The study selected the sliding arch concept as the best solution for their further investigations and recommendations, primarily to reduce the chance of the construction workers receiving a harmful dose of radiation. The French consortium named Novarka eventually won the contract for the final sliding arch design.

On 17 September 2007 Vinci Construction Grands Projets and Bouygues Travaux Publics announced that they won the contract to design and build the New Safe Confinement as 50/50 partners of the French consortium Novarka. The original 432 million euros contract comprises the design and construction of the New Safe Confinement and planned to employ 900 people at its peak.

The consortium collaborated with both foreign and domestic contractors. For example, the arch's structural components were created and constructed in Italy. The cranes were made in the US. A Dutch business handled the lifting and sliding operations, whereas the contractor responsible for the arch cladding was from Turkey. The project has involved workers and specialists from at least 24 countries in addition to Ukraine.

Structural design

The New Safe Confinement design is an arch-shaped steel structure with an internal height of 92.5m (303.5feet) and a 12m (39feet) distance between the centers of the upper and lower arch chords. The internal span of the arch is 245m (804feet), and the external span is 270m (890feet). The dimensions of the arch were determined based on the need to operate equipment inside the new shelter and decommission the existing shelter. The overall length of the structure is 150m (490feet), consisting of 13 arches assembled apart to form 12 bays. Vertical walls assembled around, but not supported by the existing structures of the reactor building seal the ends of the structure.

The arches are constructed of tubular steel members and are externally clad with three-layer sandwich panels. These external panels are also used on the end walls of the structure. Internally, polycarbonate panels cover each arch to prevent the accumulation of radioactive particles on the frame members.

Large parts of the arches were shop-fabricated and transported to the assembly site west of reactor 4. The steel used in the construction of the tubular members has a yield strength of no less than 2500abbr=onNaNabbr=on.

To prevent corrosion of the structure, stainless steel was chosen as the material for the inner and outer walls. An air conditioning system also circulates warm, dry air at 50 Pa between the layers of the panels to further prevent corrosion. Dehumidifiers keep the air below 40% humidity, preventing both condensation and water from dripping into the interior of the structure.[13]

Design goals

The New Safe Confinement was designed with the following criteria:

Foundation design

The foundations of the New Safe Confinement were designed to meet the primary requirements:

The site of the New Safe Confinement is slightly sloped, ranging in elevation from on the eastern side to on the western side. The foundation was required to account for this difference without extensive site leveling.

The ground upon which the foundation was built is unique in that it contains a technogenic layer just below the surface that is approximately 2.5to in overall depth. Radioactive contamination from the accident created the technogenic layer. It consists of various materials including nuclear material, stone, sand, loamy sands, unreinforced concrete, and construction wastes. It is considered unfeasible to determine the geotechnical characteristics of this soil layer. As a result of this, no assumptions about the load-bearing properties of the technogenic layer were made during the design of the foundation.

The water table at Chernobyl Nuclear Power Plant fluctuates from 109.9m (360.6feet) on average in December to 110.7m (363.2feet) on average in May.

Several options were considered for the foundation design for the New Safe Confinement. Ultimately, the final design was specified as consisting of three lines of two 4.5mby1mm (14.8feetby03feetm) foundation panels, each 21m (69feet) in length, and a 4m (13feet) high pile cap that reaches to a height of of elevation. This option was selected to minimize the cost of the foundation, the number of cuts into radioactive soil layers, dose uptake of workers, and risk to the environment from further contamination. The foundation has a slight elevation difference between the area in which the New Safe Confinement was constructed and the final resting area around reactor 4.

Special consideration was necessary for the excavation required for foundation construction due to the high level of radioactivity found in the upper layers of soil. The conceptual designers of the New Safe Confinement recommended the use of rope operated grabs for the first 0.3m (01feet) of pile excavation for the Chernobyl site. This reduced the direct exposure of workers to the most contaminated sections of the soil. Deeper excavation for the foundation piles were accomplished using hydraulic clam shells operated under bentonite slurry protection.

The foundation is designed to withstand horizontal acceleration structural loads of up to, as well as to withstand an F3 tornado. The original design for the structure required it to withstand an F1 tornado until an independent beyond-design-basis analysis was carried out to evaluate the effects of an F3 tornado on the structure.

Assembly process

The system used in the assembly of the New Safe Confinement derived from civilian bridge launching and bridge cantilever methods. The New Safe Confinement was assembled in the following steps:

  1. Stabilization of the Shelter Structure to prevent collapse during construction.
  2. Excavation and construction of the foundation.
  3. Assembly of first and second arches to form Bay 1, installation of east wall on arch 1.
  4. Bay 1 was slid East to accommodate the construction of arch 3 and Bay 2.
  5. Subsequent sliding of the complete structure and adding of arches and bays to complete the structure.
  6. Installation of cranes and large maintenance equipment.
  7. Installation of the west wall.
  8. Final slide into place over reactor 4.[7]
  9. Deconstruction of the fragmentation, decontamination, and auxiliary buildings. (planned)

This process of assembly was deemed advantageous because it took advantage of the designed mobility of the structure to maximize the distance between workers and the reactor building, thereby minimizing their exposure to radiation.

As each bay was completed, infrastructure equipment—including that for ventilation systems, radiation monitoring, plumbing, and electrical was installed.

Positioning

The New Safe Confinement was constructed west of reactor 4, and slid into place. Sliding of the structure along foundation rails was a difficult process. It was pushed on Teflon pads by hydraulic pistons, and guided by lasers., the New Safe Confinement is the world's largest movable land-based structure.[14] [15]

Two options were initially considered for moving the structure: hydraulic jacks to push the structure forward, or pulling the structure with large, multi-stranded steel cables. The first option would require the relocation of the hydraulic jacks after each push. This process would necessitate more worker interaction with the system and a greater worker exposure to radiation. The second option was initially chosen because it would expose workers to a lower radiation dose, and would have moved the structure into its final position in less than 24 hours. However, the structure was moved using hydraulic jacks, beginning the 327m (1,073feet) move on November 14, 2016, and finishing on November 29.

Demolition of existing structures

The operational phase of the New Safe Confinement involves the demolition of the unstable structures associated with the original Shelter Structure. The goal of demolition has imposed significant requirements upon the load carrying capacity of the arches and foundation of the New Safe Confinement, as these structures must carry the weight of not only the disassembled structure, but also the suspended cranes to be used in demolition.

Demolition equipment

The New Safe Confinement design includes two bridge cranes suspended from the arches.[16] These cranes travel east to west on common runways and each has a span of .

Each crane can carry a variety of interchangeable carriages. Three types of carriages have been designed for the New Safe Confinement:

The cranes' carriage interchangeability allows the rotation of the largest members to be demolished, reducing the overall size of the New Safe Confinement by approximately one arch bay.

After the members to be demolished are removed by crane, they must be fragmented into pieces small enough to decontaminate. It is expected that the primary contamination of most demolished elements will be loose surface dust and can easily be removed. Decontamination will take place using vacuum cleaners with HEPA filters, grit blasting (for steel elements), and scarifying (for concrete elements). Once decontaminated to the maximum extent practical, pieces will be further fragmented for eventual disposal. Fragmentation tools include plasma arc cutting torches, diamond circular cutting wheels, and diamond wire cutting. The tools selected for the demolition process were selected based on a number of factors including minimization of individual and collective radiation exposure, the amount of secondary waste generated, the feasibility of remote operation, the cutting efficiency, fire safety, capital cost and operating costs.

The exact methods for disposing of wastes generated by the demolition process have not been determined, and may include on-site burial outside the New Safe Confinement for low-level waste, and long-term storage inside the New Safe Confinement for medium and high-level wastes., no policy has been decided for the disposal and processing of fuel containing materials.

Elements to be demolished

The following elements of the Shelter Structure are planned for demolition:

Element Quantity Mass of each
(tonnes)
Length of each
(meters)
Length of each
(feet)
Southern roof flat panels 6 31 28.7 94.2
Southern roof flat panels 6 16 28.7 94.2
Southern hockey stick panels 12 38 25.5 83.7
Mammoth beam 1 127 70 229.7
Northern beam B1 1 65 55 180.4
Southern beam B1 1 65 55 180.4
Northern hockey stick panels 18 9 18 59.1
Eastern hockey stick panels 1 7.25 7 23.0
Light roof 6 21 36 118.1
Piping roof 27 20 36 118.1
Northern beam B2 1 57 40 131.2
Southern beam B2 1 57 40 131.2
Total 85 1944.25

Types of materials to be demolished

The elements that are to be demolished fall into several broad material types:

Waste storage

For the removal and storage of nuclear waste within the New Safe Confinement area, the strategies for removing waste is split into three systems.[17] Disposal of solid nuclear waste had the Vector Radioactive Waste Storage Facility[18] built near to the Chernobyl site, consisting of the Industrial Complex for Solid Radwaste Management (ICSRM),[19] a nuclear waste storage site. It is being constructed by Nukem Technologies, a German nuclear decommissioning company, a subsidiary of the Russian Atomstroyexport. This storage is reported to be able to contain 75000m2 of material.[20] [21] The storage is for both temporary high level waste as well as low and intermediate level long-term waste storage.[22] [23]

The Plant on Liquid Radwaste Management (PLRWM) was constructed to remove, store, and process liquid nuclear waste from the Chernobyl site.[24] [25] Processed liquid is turned into solid waste in 200-L barrels where it can then be stored long-term, at a rate of 2,500 cubic meters a year.[26]

Spent fuel is stored long-term in the Spent Fuel Storage Facility.[17] 232 storage containers of nuclear waste can be stored in the facility for an expected 100 years.[27]

Worker safety and radioactive exposure

Even with the distance given from the main reactor during construction of the New Safe Confinement, construction workers were still subject to radiation. Before the slippage procedure began, construction workers may only have been able to stay on the site for 30 minutes at a time due to radiation.[28] The concrete foundation reduced radiation to workers when assembling the structure, and workers were provided decontaminated housing during construction.[28]

Radioactive dust in the shelter is monitored by hundreds of sensors. Workers in the 'local zone' carry two dosimeters, one showing real-time exposure and the second recording information for the worker's dose log. Workers have a daily and annual radiation exposure limit. Their dosimeter beeps if the limit is reached, and the worker's site access is cancelled. The annual limit (20 millisieverts) may be reached by spending 12 minutes above the roof of the 1986 sarcophagus, or a few hours around its chimney. Workers are required to also check their radiation exposure before they leave the New Safe Confinement as an additional measurement for safety.[29]

To minimize radiation to workers when working inside of the New Safe Confinement, many robots and tools are used to interact with objects inside the shelter remotely. The two installed bridge cranes can be operated from within an isolated control room, which allows for demolition to occur without posing risk to any operators.[30] For the radiation mapping that occurs within the New Safe Confinement, robots have been deployed in both areas of high contamination where humans cannot enter and replacing routes that operators would normally take.[31] [32] Boston Dynamics' Spot model has been implemented in areas of higher radiation to provide detailed radiation mapping without causing additional radiation spikes by minimizing contact points with radiated surfaces. Without posing risk to workers, the implemented systems were able to look inside reactor 4, deep within the New Safe Confinement.[33]

Project timeline and status

There has been concern about Ukraine's ability to properly maintain the New Safe Confinement, with Deputy project manager Victor Zalizetskyi stating that "It looks like Ukraine will be left alone to deal with this structure"[34]

Year !! Planned
completion
2005
June 2003February 2008
20092012
February 20102013
April 2011Summer 2015.
November 2016November 2017
December 2017December 2018
The New Safe Confinement was originally intended to be completed in 2005, but the project suffered lengthy delays.

Major project milestones include:

March 2004 : An international tender for New Safe Confinement design and construction is announced. Two bid candidates are identified, but in September 2006 the plant's general director Ihor Hramotkyn announces his intent to annul all bids on the project.
  • September 17, 2007 : The project contract is signed, with French consortium (consisting of Vinci Construction Grands Projets and Bouygues Construction as 50/50 partners) constructing the 190mby200mm (620feetby700feetm) arch structure. Construction costs are estimated at $1.4bn with a project time of five years. The estimated time for completion is given as 53 months, including 18 months of planning and design studies, with a projected completion in mid-2012.
  • 2009 : Progress is made with stabilization of the existing sarcophagus, which is then considered stable enough for another 15 years.
  • September 2010 : Novarka begins construction.
  • April 2011 : Some project milestones, including infrastructure and preparatory work such as the New Safe Confinement pilings, are completed.
  • April 2012 : Steel erection begins.
  • November 26, 2012 : The first sections are raised.
  • June 13, 2013 : The second lifting operation on the eastern arch is performed.
  • April 2014 : The fully lifted eastern arch is moved 112m (367feet) eastward on its rails to a parking position to clear the construction area for building the western arch.
  • August 4, 2014 : The western arch completes the second of three lifting operations which raises the height of the arch.
  • November 12, 2014 : Successful completion of the third ascent of the western part arches.
  • April 2015 : The two arches are fused, and the west wall is under construction.
  • April 2016 : Construction of the arches is completed.[35]
  • November 14, 2016 : The arch slipping procedure begins.[36]
  • November 29, 2016 : The New Safe Confinement slipping is completed, taking a total of fifteen days.[37] It is pushed on polytetrafluoroethylene pads by hydraulic pistons, guided by lasers.[38]
  • November 2017 : Development company Rodina begins construction on the first PV project to be developed within the Chernobyl exclusion zone. 3,762 solar modules will be installed at the site with a generation capacity of .[39]
  • December 2017 : Construction completion is delayed until late 2018 due to a contractor being unable to finish its work in time.[40] The reason is the extremely high level of radiation, forcing workers to limit their presence at the site.[41]
  • January 2019 : Various subsystems are in operation, including the radiation monitoring system, the back-up power supply system, the fire protection system, as well as lighting, communication, and HVAC.[42]
  • April 25, 2019: Successful conclusion of the 72-hour trial operation test.[43]
  • July 2019 : Construction on the €1.5 billion structure is completed and the sarcophagus is opened to media visits on July 3.[44] [45] On July 10, government officials, including Ukrainian President Volodymyr Zelenskyy, attended a ceremony where the transfer of ownership of the New Safe Confinement was given to the Ukrainian government.
  • February 24, 2022: During the Russian invasion of Ukraine, Russian forces subsequently captured Chernobyl.[46] While there is an increase in radiation in the area, this is due to Russian forces disturbing the soil in the Red Forest and releasing radioactive dust and not from the reactor 4 itself.[47] The New Safe Confinement is reportedly unharmed.[48]
    March 31, 2022 : Russian forces leave Chernobyl and the New Safe Confinement.[49]

    Responsible organizations

    The European Bank for Reconstruction and Development (EBRD) is responsible for managing the Shelter Implementation Plan, including overseeing the construction of the New Safe Confinement.[50]

    See also

    References

    Further reading

    External links

    Notes and References

    1. Web site: Chernobyl’s New Safe Confinement . European Bank for Reconstruction and Development . 27 December 2023.
    2. Web site: Transforming Chernobyl brochure . EBRD . 13 September 2018 . en . 11 March 2015.
    3. Web site: Chernobyl's New Safe Confinement . European Bank for Reconstruction and Development . 31 May 2018.
    4. Web site: Chernobyl's New Safe Confinement. 2020-09-02. www.ebrd.com. en.
    5. Web site: Contract for early Chernobyl dismantling work signed : Waste & Recycling – World Nuclear News . 2020-09-02 . world-nuclear-news.org.
    6. Web site: Chernobyl's New Safe Confinement. 2020-11-28. www.ebrd.com. en.
    7. Web site: Unique engineering feat concluded as Chernobyl arch has reached resting place . European Bank for Reconstruction and Development . 29 November 2016 . 12 January 2018.
    8. News: Ukraine raises $785m to seal Chernobyl under new 'shell'. Vidal. John. 19 April 2011. The Guardian. 2 March 2018.
    9. Inside Chernobyl's Mega Tomb, http://www.windfallfilms.com/show/6894/inside-chernobyls-mega-tomb.aspx.
    10. Web site: Chernobyl 25 years on: New Safe Confinement and Spent Fuel Storage Facility . January 2011 . European Bank for Reconstruction and Development . 2 March 2018.
    11. International Competition, 1994. Ukraine Government.
    12. A second shelter for Chernobyl: Its necessity and feasibility . Smith . Stuart . Lacombe . Herve . February 1997 . Proceedings of the Institution of Civil Engineers . 120 . 1 . 2–14 . 10.1680/icien.1997.29157 .
    13. Web site: New Safe Containment Project Cuts Corrosion Risk at Chernobyl . 2022-05-01 . www.materialsperformance.com.
    14. Web site: Chernobyl Shelter To Begin Full Operation In December, Says Ukraine President . www.nucnet.org . November 29, 2017 . The Independent Global Nuclear News Agency . 12 September 2018.
    15. Web site: A vast new tomb for the most dangerous waste in the world . Borys . Christian . 3 January 2017 . BBC Future Now . 2 March 2018.
    16. Web site: Chernobyl New Safe Confinement (NSC), Ukraine . 2022-05-06 . Power Technology . en-US.
    17. Book: Lidar . Per . Bergh . Niklas . Larsson . Arne . Hedin . Gunnar . Proceedings of the ASME 2013 15th International Conference on Environmental Remediation and Radioactive Waste Management. Volume 2: Facility Decontamination and Decommissioning; Environmental Remediation; Environmental Management/Public Involvement/Crosscutting Issues/Global Partnering . Waste Management Strategy for Cost Effective and Environmentally Friendly NPP Decommissioning . 2013-09-08 . http://dx.doi.org/10.1115/icem2013-96006 . American Society of Mechanical Engineers . 10.1115/icem2013-96006. 978-0-7918-5602-4 .
    18. Web site: News . Delegation of the European Union to Ukraine . July 31, 2008 . dead . https://web.archive.org/web/20110720161210/http://www.delukr.ec.europa.eu/press_releases.html?id=47113 . July 20, 2011.
    19. Web site: Industrial Complex For Solid Radwaste Management (ICSRM) at Chernobyl Nuclear Powerplant . https://web.archive.org/web/20081203143731/http://www.nukemgroup.com/fileadmin/user_upload/Chernobyl_Ukraine_Mai2008.pdf . dead . 2008-12-03 . May 2008 . Nukem Technologies . 31 July 2008.
    20. Web site: Chernobyl Receives Nuclear Waste Processing Complex . Gabriel . Gache . Softpedia.com . 25 April 2008.
    21. Web site: Nuclear waste storage inaugurated in Chernobyl . EU Business . https://web.archive.org/web/20080724123431/http://www.eubusiness.com/news-eu/1208978222.51/ . July 24, 2008.
    22. Safety issues in construction of facilities for long-term storage of radioactive waste at Vector site . Tokarevskyi . O. . Alekseeva . Z. . Kondratiev . S. . Rybalka . N. . November 2013 . Eurosafe Forum 2013 . https://www.eurosafe-forum.org/eurosafe2013#Seminar_2 . Cologne, Germany . inis..RN:45021661 . 12 January 2018.
    23. Book: Lee . William E. . Ojovan . Michael I. . Jantzen . Carol M. . Radioactive Waste Management and Contaminated Site Clean-Up: Processes, Technologies and International Experience . 31 October 2013 . Elsevier Science . 978-0-85709-744-6 . 404–406.
    24. Book: Semenova . Iryna Y. . Steinberg . Nikolay A. . Proceedings of the ASME 2001 8th International Conference on Radioactive Waste Management and Environmental Remediation . Chernobyl NPP Decommissioning and "Shelter" Object Transformation: Problems of Activity Coordination . 2001-09-30 . http://dx.doi.org/10.1115/icem2001-1177 . 997–1000 . American Society of Mechanical Engineers . 10.1115/icem2001-1177. 978-0-7918-8017-3 .
    25. Web site: 2018-02-07 . Chernobyl starts tackling its liquid radioactive waste . 2022-05-07 . Bellona.org . en-US.
    26. Web site: Татьяна . Грива . Liquid Radioactive Waste Treatment Plant (LRTP) . 2022-05-07 . chnpp.gov.ua . en-gb.
    27. News: Ukraine authorizes Chernobyl spent fuel storage . 2022-05-07 . www.ans.org . en.
    28. Web site: Progress at Chernobyl New Safe Confinement . 2022-05-07 . ProQuest . . en.
    29. Web site: See Chernobyl's Safe Confinement Shelter . 2022-05-06 . Bechtel Corporate . en.
    30. Book: Parameswaran . N. A. (Vijay) . Chornyy . Igor . Owen . Rob . de Saint Victor . François . Proceedings of the ASME 2013 15th International Conference on Environmental Remediation and Radioactive Waste Management. Volume 2: Facility Decontamination and Decommissioning; Environmental Remediation; Environmental Management/Public Involvement/Crosscutting Issues/Global Partnering . Unique and Massive Chernobyl Cranes for Deconstruction Activities in the New Safe Confinement . 2013-09-08 . http://dx.doi.org/10.1115/icem2013-96346 . American Society of Mechanical Engineers . 10.1115/icem2013-96346. 978-0-7918-5602-4 .
    31. Web site: 2020-11-23 . Boston Dynamics' Spot Is Helping Chernobyl Move Towards Safe Decommissioning . 2022-05-06 . IEEE Spectrum . en . Evan . Ackerman.
    32. Web site: Radiation-mapping robots deployed at Chernobyl . 2022-05-06 . Nuclear Newswire . American Nuclear Society (ANS) . en . October 13, 2021.
    33. Web site: Bristol team gains unprecedented access to Chernobyl's Reactor 4 . 2022-05-06 . Newswise . en . 7 October 2021 . University of Bristol.
    34. Web site: Ukraine will 'struggle' to maintain new Chernobyl shelter. www.9news.com.au. July 11, 2019 .
    35. News: $1.7B Giant Arch to Block Chernobyl Radiation For Next 100 Years . Reuters . NBC News . 24 March 2016 . 20 November 2016.
    36. Web site: Chernobyl disaster: Giant shield begins move towards reactor . 14 November 2016 . BBC News . 30 November 2016.
    37. Unique engineering feat concluded as Chernobyl arch has reached resting place . 29 November 2016 . 30 November 2016 . European Bank for Reconstruction and Development.
    38. Web site: Chernobyl New Safe Confinement: a one-of-a-kind project . 29 November 2016 . 21 . . 2 March 2018 . April 25, 2017 . https://web.archive.org/web/20170425122521/https://www.vinci.com/vinci/actualites.nsf/8B8A50CC6F1891E8C1258079005011BA/$File/VINCI_RV_Dossier_de_presse_Tchernobyl_GB.pdf . dead .
    39. Web site: Rodina begins construction on first PV project inside Chernobyl exclusion zone . PV Tech . November 9, 2017 . 17 November 2017 . en.
    40. Web site: Ukraine postpones Chernobyl reactor safety cover . https://web.archive.org/web/20171206203326/http://news.xinhuanet.com/english/2017-12/07/c_136806475.htm . dead . December 6, 2017 . . 20 November 2017.
    41. Strahlung zu hoch: Fertigstellung des Tschernobyl-Sarkophags verzögert sich . Seidler . Christoph . 20 December 2017 . de . Spiegel Online. 20 December 2017.
    42. Web site: 8 February 2019 . Chernobyl confinement structure systems begin operation – World Nuclear News . 9 February 2019 . world-nuclear-news.org . World Nuclear Association.
    43. Web site: Delivery of the Chernobyl New Safe Confinement . 2022-05-06 . VINCI . en.
    44. News: What should we do with radioactive nuclear waste?. Vidal. John. 2019-08-01. The Guardian. 2019-08-02. en-GB. 0261-3077.
    45. Web site: Chernobyl's $1.7B nuclear confinement shelter revealed after taking 9 years to complete. Dedaj. Paulina. 2019-07-03. Fox News. en-US. 2019-08-02.
    46. Web site: Chernobyl nuclear plant targeted as Russia invades Ukraine . 2022-05-06 . www.aljazeera.com . en.
    47. News: 2022-03-29 . Unprotected Russian soldiers disturbed radioactive dust in Chernobyl's 'Red Forest', workers say . en . Reuters . 2022-05-06.
    48. Web site: 2022-03-03 . Explained: Why did Russian troops seize control of Chernobyl nuclear disaster site? . 2022-05-06 . The Indian Express . en.
    49. Web site: Varenytsia . Cara Anna and Inna . A nuclear risk 'nightmare'? After seizing Chernobyl, Russian troops exposed themselves to radiation. . 2022-05-06 . USA TODAY . en-US.
    50. Book: Onishi . Yasuo . Chernobyl – What Have We Learned?: The Successes and Failures to Mitigate Water Contamination Over 20 Years . Voitsekhovich . Oleg V. . Zheleznyak . Mark J. . 3 June 2007 . Springer Science & Business Media . 978-1-4020-5349-8 . 248.