Chienshan Power Plant Explained

Chienshan Power Plant
尖山發電廠
Coordinates:23.5631°N 119.6611°W
Country:Republic of China
Location:Huxi, Penghu, Taiwan
Status:O
Commissioned:November 2000 (Unit 2-3)
December 2000 (Unit 1)
February 2001 (Unit 4)
May 2002 (Unit 5)
June 2002 (Unit 6)
August 2002 (Unit 7-8)
November 2002 (Unit 9-10)
January 2003 (Unit 11-12)
Owner:Taipower
Operator:Taipower
Th Fuel Primary:Diesel fuel
Ps Units Operational:4 × 10.443 MW (diesel)
8 × 11 MW (diesel)
8 × 0.6 MW (wind)
6 × 0.9 MW (wind)
Ps Electrical Capacity:140 MW

The Chienshan Power Plant is a fuel-fired power plant in Huxi Township, Penghu County, Taiwan.[1] With the total capacity of 140 MW, the power plant is the largest diesel fuel-fired power plant in Taiwan.[2] Chienshan Power Plant is the only major power plant in Penghu Island.

History

In November 1994, the Executive Yuan approved the construction of the power plant. In June 1990, the first phase of the power plant was commissioned with four generation units with a total installed capacity of 10.4 MW. In March 1998, the Executive Yuan approved for the expansion of the power plant on Unit 5–12 with the total installed capacity of 11 MW. The construction of those eight generation units were completed in December 2002.[3]

See also

Notes and References

  1. Web site: http://www.brain-c-jcoal.info/news_images/JapanTaiwanCCTWorkshop2009_05.pdf . 1 August 2013 . dead . https://web.archive.org/web/20131015111609/http://www.brain-c-jcoal.info/news_images/JapanTaiwanCCTWorkshop2009_05.pdf . 15 October 2013 .
  2. Web site: 尖山發電廠簡介. 8 February 2011. 2014-08-23. https://web.archive.org/web/20160304023031/http://info.taipower.com.tw/TaipowerWeb//upload/files/32/d390.pdf. 4 March 2016. dead.
  3. Web site: Chienshan Power Plant. Taipower. 7 September 2020. 3 November 2021.