Chatuge Dam Explained

Chatuge Dam
Name Official:Chatuge Dam
Dam Crosses:Hiwassee River
Res Name:Chatuge Lake
Location:Clay County, North Carolina, United States
Operator:Tennessee Valley Authority
Dam Length:2850feet
Dam Height:144feet
Construction Began:July 17, 1941
Opening:February 12, 1942
Coordinates:35.0175°N -83.7911°W

Chatuge Dam is a flood control and hydroelectric dam on the Hiwassee River in Clay County, in the U.S. state of North Carolina. The dam is the uppermost of three dams on the river owned and operated by the Tennessee Valley Authority, which built the dam in the early 1940s for flood storage and to provide flow regulation at Hiwassee Dam further downstream.[1] The dam impounds the 7000acres Chatuge Lake, which straddles the North Carolina-Georgia state line.[2] While originally built solely for flood storage, a generator installed at Chatuge in the 1950s gives the dam a small hydroelectric output.[3] At the time it was built, Chatuge Dam was the highest earthen dam in the world until the Aswan Dam was built in Egypt in 1964.[4] The dam and associated infrastructure was listed on the National Register of Historic Places in 2017.[5]

Chatuge Dam is named for an 18th-century Cherokee village once situated near the dam site. The dam is the easternmost TVA energy facility in North Carolina.[6]

Location

Chatuge Dam is located 121miles above the mouth of the Hiwassee River, just north of the North Carolina-Georgia state line. Chatuge Lake extends southward for 13miles along the Hiwassee and eastward for roughly 6miles along Shooting Creek, which once emptied into the Hiwassee immediately upstream from the dam site. The dam and the North Carolina section of the reservoir are surrounded by the Nantahala National Forest, and the Georgia section of the reservoir is surrounded by the Chattahoochee National Forest. Hayesville, North Carolina (north of the dam) and Hiawassee, Georgia (to the south) are the nearest communities of note.

The dam also serves as a social gathering place for Clay County citizens. The county's annual Independence Day fireworks celebration is held at the dam, crossing the dam and back provides a one-mile walk, a relatively flat 3.5 mile paved walk extends from the dam to campgrounds and recreation areas, and Clay County Schools' cross country teams practice and hold meets at the dam.[7]

Capacity

Chatuge Dam is an earth-and-rock dam 144feet high and 2850feet long, and has a generating capacity of 10,000 kilowatts. The dam's concrete overflow "ski-jump" spillway consists of 50 bays with a combined discharge of 11500cuft/s. Chatuge Lake has a flood storage capacity of and 132miles of shoreline.

Water passes Chatuge Dam via the dam's intake tower (connected to the dam by a footbridge), from which a steel conduit carries the water under the dam and empties it downstream.

Background and construction

Various private entities recognized the hydroelectric potential of the Hiwassee in the early 1900s, although plans for dams were typically focused further downstream from the Chatuge site. TVA had considered an alternate site two miles downstream at Blair Creek. After taking control of flood control operations in the valley in the 1930s, the Tennessee Valley Authority built Hiwassee Dam and carried out an extensive survey of the river (the waters of which were a major contributor to flooding in Chattanooga) in which they identified the Chatuge site. The outbreak of World War II in Europe brought an emergency demand for electricity, mainly to power aluminum production in East Tennessee, and TVA offered to meet this demand by building a series of dams on the Hiwassee and several other Tennessee River tributaries. The Chatuge Dam project (originally called the Hayesville project), along with several other dam projects, was authorized July 16, 1941. Work on the dam began the following day.

The construction of Chatuge Dam and its reservoir required the purchase of 11641acres of land, 1904acres of which had to be cleared. 278 families, 532 graves, and 40miles of roads (including part of U.S. Route 64 and all of NC 69) had to be relocated.[8] One house relocated from the Elf community during the clearing of the land later became the Clay County School District superintendent’s office until 2005. TVA kept the dam's design simple and relied on basic building materials (i.e., earth and rock) in order to complete the dam as quickly as possible in hopes of allowing the reservoir to collect the 1941-1942 winter rains. The dam was constructed of impervious earthen fill fortified on both sides by riprap. The spillway was the only major part of the dam that required concrete. Since the reservoir would fill slowly and create mosquito-breeding environments, various measures were taken to prevent malaria outbreaks.

Chatuge Dam was completed and its gates closed on February 12, 1942. The cost of the whole project was just over $9 million. Construction took 1.5 million man-hours to complete. One worker died during the construction. For most of its early years, Chatuge was operated as a flood storage unit in conjunction with nearby Nottely Dam (which has an almost identical design) to regulate water flow at Hiwassee Dam 45miles downstream. A 300foot long saddle dam was also built to the east of Chatuge Dam. In 1954, both it and the main dam were raised ten feet and flash boards were installed on the spillway so the lake could rise an additional 4feet.[9] A small generator was also installed at Chatuge in 1954.

External links

Notes and References

  1. Tennessee Valley Authority, The Hiwassee Valley Projects Volume 2: The Apalachia, Ocoee No. 3, Nottely, and Chatuge Projects, Technical Report No. 5 (Washington, D.C.: U.S. Government Printing Office, 1948), pp. 1-8, 17-19, 50-55, 209, 214, 222, 232, 496-497.
  2. Tennessee Valley Authority, The Nickajack Project: A Report on the Planning, Design, Construction, Initial Operations, and Costs, Technical Report No. 16 (Knoxville, Tenn.: Tennessee Valley Authority, 1972), pp. 10-11.
  3. Tennessee Valley Authority, Chatuge Reservoir. Retrieved: 28 January 2009.
  4. Book: Moore . Carl S. . Clay County, NC Then and Now: A Written and Pictorial History . Impact of National Forest & TVA Chatuge Dam . Genealogy Publishing Service . 1 Jan 2007 . 9781881851240.
  5. Web site: National Register Database and Research - National Register of Historic Places (U.S. National Park Service) . 2024-03-15 . www.nps.gov . en.
  6. Web site: Office . U. S. Government Accountability . Tennessee Valley Authority: Additional Steps Are Needed to Better Manage Climate-Related Risks U.S. GAO . 2024-03-28 . www.gao.gov . en.
  7. Web site: Annual Events . Clay County Chamber of Commerce . Fireworks are typically held near Chatuge Dam. Watch from your boat, the Chatuge Dam parking lot, the Clay County Recreation Area or Gibson Cove Campground. .
  8. Book: Padgett, Guy . A History of Clay County, North Carolina . Clay County Bicentennial Committee . 1976 .
  9. News: Chatuge Lake to rise 4 ft. . The Cherokee Scout . Murphy, N.C. . 1954-04-15 . A1 .