Cedar Creek Wind Farm I & II | |
Coordinates: | 40.8711°N -104.0931°W |
Location: | 13km E of Grover, Colorado, United States |
Status: | Operational |
Construction Began: | 2007 |
Commissioned: | 21 November 2007 |
Cost: | US$480 million |
Owner: | Cedar Creek I - ArcLight Capital Cedar Creek II - BP Wind Energy (50%) & Sempra Generation (50%)) |
Operator: | Cedar Creek I - Infigen Energy Cedar Creek II - BP Wind Energy |
Ps Units Operational: | 397 - Total 274 - Cedar Creek I 123 - Cedar Creek II |
Ps Units Manu Model: | Mitsubishi, GE, Nordex 221x 1MW Mitsubishi MWT-1000 53x 1.5MW GE 1.5s/sle 63x 1.6MW GE 60x 2.5MW Nordex |
Wind Farm Type: | Onshore |
Ps Site Elevation: | 1674m |
Ps Electrical Capacity: | 551.3MW - Total 300.5MW - Cedar Creek I 250.8MW - Cedar Creek II |
Ps Electrical Cap Fac: | 31.5% (average 2011-2020) |
Ps Annual Generation: | 1,522 GW·h |
The Cedar Creek Wind Farm is a 551.3 megawatt (MW) wind farm located about 8 miles east of the town of Grover in north-central Weld County, Colorado. It consists of 397 wind turbines and was constructed in two phases, Cedar Creek I and Cedar Creek II, becoming fully operational in 2010. The electricity is sold to the Public Service Company of Colorado.
The initial 300.5 MW Cedar Creek I installation was completed on time, within budget, and without incident - with the operation commencing on 21 November 2007. Cedar Creek I is an important contributor to Colorado's New Energy Economy, providing enough wind-powered electricity for 81,135 homes.[1] Cedar Creek II has an additional 250.8 MW of generating capacity, and was commissioned in 2010.
The first phase has 221 1 MW wind turbines from Mitsubishi Heavy Industries and 53 1.5 MW turbines from General Electric.[2] The second phase has an additional 63 1.6 MW SLE turbines from General Electric, and 60 2.5 MW from German wind turbine supplier Nordex.
Cedar Creek I is currently owned by ArcLight Capital.[3] Cedar Creek II is owned by BP Wind Energy (50%) and Sempra Generation (50%).[4]
Electricity from Cedar Creek II reaches the grid through approximately 20 miles of new transmission lines that connect to the Cedar Creek I substation. From there, the project utilizes an existing 76-mile (230kV) transmission line to deliver the electrical power. The Cedar Creek II project employed some 350 workers during peak construction, and some 19 jobs have been created to monitor and maintain the facility.
Year | Cedar Creek 1 (300.5 MW Unit) [5] | Cedar Creek 2 (250.8 MW Unit) [6] | Total Annual MW·h |
---|---|---|---|
2007 | 106,803 | - | 106,803 |
2008 | 972,787 | - | 972,787 |
2009 | 913,282 | - | 913,282 |
2010 | 841,206 | - | 841,206 |
2011 | 891,305 | 508,691 | 1,399,996 |
2012 | 837,374 | 801,121 | 1,638,495 |
2013 | 879,922 | 811,375 | 1,691,297 |
2014 | 842,744 | 758,709 | 1,601,453 |
2015 | 744,451 | 654,254 | 1,398,705 |
2016 | 852,867 | 751,628 | 1,604,495 |
2017 | 794,301 | 713,395 | 1,507,696 |
2018 | 813,126 | 713,611 | 1,526,737 |
2019 | 707,748 | 661,089 | 1,368,837 |
2020 | 787,016 | 694,441 | 1,481,457 |
2021 | 516,379 | 476,740 | 993,119 |
Average Annual Production (years 2011–2020) : | 1,521,917 | ||
Average Capacity Factor (years 2011–2020) : | 31.5% |