Cannock Mineral Railway Explained

The Cannock Mineral Railway was a railway company that built a line from Cannock to join the London and North Western Railway (LNWR) at Rugeley, in England. It was conceived and authorised as the Derbyshire, Staffordshire and Worcestershire Junction Railway, with the intention of connecting Dudley and Uttoxeter, but it was hopelessly undercapitalised and badly managed.

As finally built it was seven miles in length, and joined the South Staffordshire Railway (SSR) at Cannock. It was leased to, and then absorbed by the LNWR, and with the SSR it simply formed part of the LNWR network in the district, chiefly serving extractive industries.

It opened to passenger and goods traffic in 1859. Passenger traffic was discontinued in 1965, but was resumed in 1989 and is still (2022) in operation, with a typically half-hourly service operated by West Midlands Trains under the branding London Northwestern.

Development of scheme

Early proposals

An ambitious railway scheme called the Derbyshire, Staffordshire & Worcestershire Junction Railway was proposed during the Railway Mania period of 1846. It was intended to connect Uttoxeter to Dudley, and by running powers over the North Staffordshire Railway to connect to Manchester.[1] [2]

The route had been surveyed by Sir John Rennie and George Remington; during the Parliament hearings, Rennie admitted that he had never laid a line through such a thinly populated district. This proved to be a fatal remark, as the South Staffordshire Junction Railway (SSJR) Bill was passed in Parliament at the same time. The SSJR scheme was for a railway linking Walsall and Dudley, and the DS&WJR proposal included similar ground. Two new railways over a thinly populated terrain were unsustainable, and the SSJR scheme looked more fruitful; the DS&WJR Bill was thrown out by the Lords Committee.[1] [2]

Short Title:Derbyshire, Staffordshire and Worcestershire Junction Railway Act 1847
Type:Act
Parliament:Parliament of the United Kingdom
Year:1847
Citation:10 & 11 Vict. c. cx
Royal Assent:2 July 1847
Collapsed:yes

In the next session of Parliament, the SSJR was proposing an additional line, from Walsall to Cannock. The DS&WJR too was in Parliament in the next session with a revised scheme. Avoiding a second confrontation with the SSJR, it put forward a more modest proposal, a railway from Uttoxeter to Cannock. It proposed to make an end-on junction with the North Staffordshire Railway at Uttoxeter, and another at Cannock with the SSJR. The bill passed through Parliament, the (10 & 11 Vict. c. cx) receiving royal assent on 2 July 1847. The authorised share capital was £440,000, and the line was to be 18 miles in length.[1] [2] [3] [4]

A contractor named George Mould was given the contract to build from Rugeley to Cannock. However ten months later on 26 November 1852 the company's engineer John Addison reported that work had been suspended due to the very bad state of the weather, and the following year on 16 September 1853 he reported that little had been done since his last inspection. Addison was criticised by the board and was suspended, but a month later on 19 December 1853 he was reinstated.

Speeding up the construction

The parliamentary powers for construction of the line were time limited, and by now there were only six months left. At the Annual General Meeting on 25 February 1854 it was agreed to seek an extension of time. More significantly it was recognised that a lack of sufficient share take-up meant that the company had little money to proceed with the project, and a major partner would be required, with enough financial backing to enable the construction to move forward. In 1852 Addison had prepared a scheme for an extension from Cannock to Wolverhampton via Four Ashes, connecting with the Great Western Railway. Further plans were made to join the GWR at Wednesbury instead, and a partnership with the GWR was proposed. Addison was instructed to approach Isambard Kingdom Brunel, the Engineer of the GWR, and on 16 July Addison reported that Brunel was favourably disposed to the idea. However, the London and North Western Railway was dominant in the area and was known to be hostile; the scheme would need Parliamentary approval, and it was expected that the LNWR would be able to frustrate the GWR alliance.[5]

Short Title:Cannock Mineral Railway Act 1855
Type:Act
Parliament:Parliament of the United Kingdom
Long Title:An Act to change the corporate Name of the Derbyshire, Staffordshire, and Worcestershire Junction Railway Company, to repeal their Act and consolidate their Powers, to alter and define their Undertaking, to reduce their Capital; and for other Purposes.
Year:1855
Citation:18 & 19 Vict. c. cxciv
Royal Assent:14 August 1855
Original Text:https://www.legislation.gov.uk/ukla/Vict/18-19/194/pdfs/ukla_18550194_en.pdf
Collapsed:yes

There was now desperation to find a well-funded partner. In 1854 and 1855 approaches were made for help to John McClean, the lessee of the South Staffordshire Railway, but he was not interested.[6] On 7 May 1855 the board agreed to abandon any intention of proceeding north of Rugeley, making the planned extent of the line miles; and to reduce the share capital to £200,000 (later altered to £160,000). In addition the name of the company was to be changed to the Cannock Mineral Railway.[7] [8] [9] The new company was authorised by the (18 & 19 Vict. c. cxciv) of 14 August 1855.[10]

In the 1857 session of Parliament, the company was seeking a time extension, and altered the proposed connection at the northern extremity to join the North Staffordshire Railway at Colwich, and omit the previous plan to connect with the LNWR. With this connection, the NSR contemplated making a line from Colwich to Wolverhampton.[11] However the Marquis of Anglesey, a director of the LNWR and a substantial landowner, objected to the purchase of land for the bill, so the connection to the NSR could not be made. This all proved irrelevant as in March 1857 it became apparent that the CMR company did not even have the resources to proceed with the residual Bill. The NSR was evidently still keen on the idea, so it agreed to pay for the costs of progressing with the bill, but this idea came to nothing.[12] [2] [13]

Changing control

The LNWR was evidently alarmed at the possibility of the North Staffordshire company forming this link up, and moved swiftly. On 3 June 1857 there was a CMR shareholders' meeting which approved leasing the line to the LNWR for £5,500 per annum and a guaranteed dividend of 5%. The parliamentary bill for the line to the NSR at Colwich was withdrawn. The NSR had directors on the CMR board, and they now all resigned, and the LNWR takeover of control was complete; the necessary Act for extension of time was passed on 27 July 1857.[12]

A new contractor T. R. Stephenson was appointed but he too was soon found wanting, and at the end of 1857 Thomas Brassey and Thomas Field were given the work. During the period of construction, an omnibus service was introduced, running from the LNWR at Rugeley to the SSR, newly opened at Cannock, and operated on behalf of the CMR.[14] [15]

There followed repeated erroneous predictions of when the line would be opened, culminating in a visit on 29 September 1959 by Colonel Yolland of the Board of Trade to pass the line for passenger operation; it was still deficient of requirements and he declined to do so. He made a re-inspection on 22 October, and found that things were better although a turntable had still not been provided at Rugeley. Despite this shortcoming, the Board of Trade permitted operation, and on 7 November 1859 the line opened.[16] [17] [11] [9]

Opening and operation

The first passenger train service consisted of three daily trains between Birmingham and Stafford.[18]

The 1895 edition of Bradshaw shows eight passenger trains each way daily at Cannock, with one additional on certain days of the week, and two on Sundays.[19] In 1922 the service had risen to ten each way with three on Sundays,[20] and by 1938 this had further risen to 23 weekdays and eight on Sundays.[21]

The LNWR lease of the CMR was to run for a period of 999 years from its opening date, but Brassey suggested that the LNWR might prefer to acquire the CMR outright. The Directors announced on 28 February 1862 that this was to take place, but once again matters dragged on, and it was only on 12 July 1869 that Parliament authorised it.[10] The share swap was £55 of Ordinary LNWR Stock or £70 of LNWR 5 per cent Perpetual Preference Stock to replace every £100 of CMR shares, with an alternative of £7 in cash for every £10 CMR share. The last Board Meeting of the CMR was held on 21 August 1869 at Euston.[18]

Locations

External links

Notes and References

  1. Bob Yate, The South Staffordshire Railway, volume 2, Oakwood Press, Usk, 2011, ISBN 978 0 85361 717 4, page 19
  2. Rex Christiansen, A Regional History of the Railways of Great Britain: volume VII: the West Midlands, David & Charles, Newton Abbot, 1973, ISBN 0 7153 6093 0, pages 129 and 130
  3. Donald J Grant, Directory of the Railway Companies of Great Britain, Matador, Kibworth Beauchamp, 2017, ISBN 978 1785893 537, page 144
  4. E F Carter, An Historical Geography of the Railways of the British Isles, Cassell, London, 1959, page 178
  5. Yate, page 20
  6. Yate, page 21
  7. In many other cases the title "Mineral Railway" implied that only mineral traffic would be carried, but in this case the words merely referred to the dominance in the area of extractive industries.
  8. Yate, page 22
  9. The Cannock Chase Railways, in the Railway Magazine, November & December 1948, pages 362 onward
  10. Grant, page 94
  11. Christiansen, pages 130 and 131
  12. Yate, page 23
  13. Rex Christiansen and R. W. Miller, The North Staffordshire Railway, David & Charles, Newton Abbot, 1971, ISBN 0 7153 5121 4, page 59
  14. Yate, volume 2, page 24
  15. George P Neele, Railway Reminiscences, McCorquodale, London, 1904, page 60
  16. Christiansen says that Brassey completed the construction "5 months ahead of the original forecast" but this seems to be a misunderstanding.
  17. Yate, pages 25, 27 and 29
  18. Yate, page 30
  19. Bradshaw's General Steam Navigation and Railway Guide, 12th mo, (December) 1895, reprinted by Middleton Press, Midhurst, 2011, ISBN 978 1 908174 11 6
  20. Bradshaw's General Railway and Steam Navigation Guide, 7th mo, (July) 1922, reprinted by Guild Publishing, London, 1985
  21. Bradshaws July 1938 Railway Guide, David & Charles Publishers, Newton Abbot, 1969, ISBN 0 7153 4686 5
  22. Col M H Cobb, The Railways of Great Britain -- A Historical Atlas, Ian Allan Publishing Limited, Shepperton, 2003, ISBN 07110 3003 0
  23. M E Quick, Railway Passenger Stations in England, Wales and Scotland: A Chronology, version 5.03, September 2021, Railway and Canal Historical Society, electronic download