Cambambe Power Station | |
Location Map: | Angola |
Coordinates: | -9.7533°N 14.4808°W |
Country: | Angola |
Location: | Cuanza Norte Province |
Status: | UC |
Construction Began: | 7 October 1959 |
Opening: | 6 October 1963 |
Dam Type: | A |
Dam Crosses: | Kwanza River |
Dam Height Thalweg: | 132m (433feet) |
Dam Length: | 300m (1,000feet) |
Spillway Count: | 7 |
Spillway Capacity: | 4500m3/s |
Res Surface: | 5.5km2 |
Plant Turbines: | Cambambe 1: 4 x 65 MW, Francis-type Cambambe 2: 4 x 175 MW Francis-type |
Plant Capacity: | Cambambe 1: 260 MW Cambambe 2: 700 MW Total: 960 MW |
The Cambambe Hydroelectric Power Station is a hydroelectric power plant across the Kwanza River at the border between Cuanza Norte Province and Bengo Province in Angola. Following rehabilitation and expansion, the generation capacity of this installation is .[1]
The power station is located across the Kwanza River, in Cambambe, Angola, about 198km (123miles), by road, southeast of Luanda, the capital and largest city in the country. The geographical coordinates of the power station are:09°45'12.0"S, 14°28'51.0"E (Latitude:-9.753333; Longitude:14.480833).
The construction of Cambambe 1 Dam was started on October 7, 1959 and finished in 1963.[2] Due to wear and tear as well as lack of maintenance, by 2002, output had fallen from 180 megawatts to approximately 80 megawatts.[1]
In April 2007, a consortium comprising Odebrecht, Voith, Alstom and Engevix, was hired by the Empresa Nacional de Electricidade, to carry out the project of rehabilitation, expansion and modernization of the dam and power station. The project includes the heightening of the structure by 30 meters,[3] the modernization of the generating units of the Cambambe 1, replacing the four 45 MW turbines by four 65 MW turbines, and the construction of a new plant, called Cambambe 2, with four generating units of 175 MW each, for a total of 700 MW. The works in Cambambe 1 started in March, 2009 and in Cambambe 2 in 2013.[1]
In July 2015, it was anticipated that the first 175 megawatts turbine of Cambambe II, would be installed and come online in June 2016, with completion expected in 2017.[4]
Other upgrades included the construction of three new energy transformation substations, with capacities 400KV, 220KV and 60KV, to support connection between Cambambe 1 and 2, Capanda Hydroelectric Power Station and Laúca Hydroelectric Power Station. The renovation and upgrade of Cambambe 1 and the construction of Cambambe 2, cost an estimated US$2 billion.[4]
The completed power station was commissioned on 27 July 2017, in front of 500 invited guests.[5]