Caledonian Maritime Assets Explained

Caledonian Maritime Assets Limited
Type:Public corporation (state-owned)
Foundation:2006
Location:Port Glasgow, Scotland[1]

Caledonian Maritime Assets Limited (usually shortened to CMAL or CMAssets; Stòras Mara Cailleannach Earr in Scottish Gaelic) owns the ferries, ports, harbours and infrastructure for the ferry services serving the west coast of Scotland, the Firth of Clyde and the Northern Isles.

CMAL is a wholly owned public corporation of the Scottish Government, with Scottish ministers as sole shareholders.[2]

History

Until 1 October 2006 Caledonian MacBrayne Ltd, which was wholly owned by the Scottish government, provided the majority of the Clyde and Hebrides ferry services and owned the associated vessels and a number of the ports and harbour facilities that the vessels used. These services required an annual revenue deficit grant from the then Scottish Executive to maintain lifeline service levels.

To comply with European guidelines on State Aids in Maritime Transport, an open public tender was deemed necessary in respect of these ferry services and the Clyde and Hebrides Ferry Services (CHFS) was tendered as a single bundle, with the exception of the Gourock-Dunoon service.[3]

In recognition of the uniqueness of the fleet and to ensure a level playing field for all bidders, on 1 October 2006 Caledonian MacBrayne Ltd was split into:

This was done by Caledonian MacBrayne Ltd transferring its operations—but not its assets—to CFL. The operation of the lifeline ferry service was then put out to open competitive tender.

CMAL now owns all vessels, the majority of land based assets (ports, harbours etc.) and the Caledonian MacBrayne brand, and makes them available to an operator through an open tendering process. CFL continues to operate the services after winning the tendering process and holds the Public Services Contract (PSC) until 30 September 2013. Under the terms of the tender CFL is bound to use the vessels of CMAL.[4]

Business

CMAL's responsibilities include:

Ferries

CMAL currently owns 37 ferries, of which 32 are operated by Calmac Ferries on routes to the islands and peninsulas of the west of Scotland.[5] In April 2018 it was agreed that the five vessels operated by NorthLink Ferries on routes to the Orkney and Shetland islands would also join the fleet.[5] [6] Many ferries are specially built for the ports they serve yet are still interchangeable and able to serve different crossings and can carry from one to 143 cars. The total fleet value was estimated at £130m in 2017.[7]

and ceased operation with Caledonian MacBrayne in early 2018,[8] [9] and are now no longer part of the fleet.[5]

Clyde and Hebrides Islands ferries (Caledonian MacBrayne)

See main article: Caledonian MacBrayne fleet.

Northern Isles ferries (NorthLink Ferries)

See main article: NorthLink Ferries.

Harbours

CMAL is Harbour Authority at 24 locations across Scotland and owns the associated port infrastructure and properties at each of these locations. Additionally, CMAL owns and leases a number of properties at various locations associated with the delivery of Clyde and Hebrides Ferry Services.[10]

As Statutory Harbour Authority for a number of these harbours, CMAL's responsibilities and duties include:[11]

Completed projects

Hybrid ferries project

On 17 December 2012, the world's first seagoing roll-on/roll-off vehicle and passenger diesel–electric hybrid ferry was launched by CMAL on the Clyde. incorporates a low-carbon hybrid system of diesel electric and lithium-ion battery power. The 135-tonne ferry is nearly 150 feet long and can accommodate 150 passengers, 23 cars or two heavy-goods vehicles.[12] She began service between Sconser on Skye and Raasay in the summer of 2013.[13] A second hybrid ferry,, was launched in May 2013 and initially operated on the Tarbert (Loch Fyne) - Portavadie route, currently operating on the Lochaline - Fishnish route. A third, to be named,[14] was launched in spring 2016 and operates on the Claonaig - Lochranza route, additionally to Tarbert (Loch Fyne) and Portavadie in the winter.

Brodick terminal redevelopment

CMAL completed the redevelopment of Brodick ferry terminal. The redevelopment included an entirely new pier with linkspan and airbridge, a second berth with concrete ramp, a new two-storey terminal building with bus station and car marshalling space. The old linkspan was removed and the causeway transformed into an outdoor seating area.[15]

Sustainable ferries study

CMAL was commissioned to carry out a feasibility study for Scottish Enterprise to evaluate the technical and commercial possibilities of using hydrogen fuel cells to enable the development of zero-emission ferries.[16] Along with Orkney Islands Council, Ballard Power Systems, Kongsberg Maritime and others, CMAL are part of the HySeas III consortium hoping to demonstrate that fuel cells can be integrated with a marine hybrid electric drive system.[17] The project hopes to develop a vessel to operate between Kirkwall and Shapinsay.[18] The project was completed in June 2022.[19]

Current projects

Dual-fuel ferries

In September 2015, it was announced that CMAL would order two ferries from Ferguson Marine Engineering (FMEL).[20] The vessels will be able to operate on liquefied natural gas (LNG) and marine diesel, future-proofing them for tighter sulphur emissions regulations. They will be the largest commercial vessels to be built on the Clyde since 2001. The first, named, was due to enter service at Ardrossan in 2018,[21] with the second, named MV Glen Rosa, following a few months later.[22] [23] Both vessels have been delayed, with the shipyard going into administration in August 2019.[24] The 'ferry fiasco' is an ongoing political scandal in Scotland, exposing management failures across all parties involved.

LNG facilities

At Uig and Ardrossan for the dual-fuel vessels under construction.[25]

Small vessel replacement programme

This project is to replace the oldest of the Loch class, in two phases over ten years. The new vessels would be more environmentally friendly and meet higher regulatory standards.[26] The first phase will be for the building of 7 new vessels for the following routes.[27] [28] The procurement process began in July 2024, with an invitation to tender expected to be issued around September 2024, and a contract expected to be awarded in March 2025.[29]

  1. ColintraiveRhubodach, replacing
  2. SconserRaasay, replacing (to be cascaded, probably to Cumbrae, to replace as second summer vessel, with a possibility for a higher passenger capacity)
  3. IonaFionnphort, replacing
  4. Tarbert (Loch Fyne), replacing Portavadie, replacing
  5. LochalineFishnish, replacing (to be cascaded elsewhere in the network)
  6. TobermoryKilchoan, replacing
  7. TayinloanGigha, replacing

The second phase began intial design and port feasibility studies in August 2024.[30] The following routes are in scope for this phase:[31]

  1. BarraEriskay, replacing
  2. BernerayLeverburgh, replacing
  3. MallaigArmadale, replacing

New Islay ferries

This project is to replace and (to be cascaded elsewhere in the network).[32] On 3 October 2022 the first steel was cut for the first vessel, named MV Isle of Islay, at Cemre Shipyard, Turkey. On the week of 13 January 2023 the first vessels' keel was laid and the second vessels' first steel was cut.[33] Voting for the names of the two vessels was launched on 24 April 2023, where the public was asked to pick two names, with the following options:

The names and were selected.[34] On 24 May 2023 the keel for Loch Indaal was laid.[35] The vessels utilise Voith Schneider Propulsion and bow thrusters. Isle of Islay is expected to be delivered by the end of 2024,[36] with Loch Indaal expected to be delivered in February 2025.[37]

New Little Minch ferries

This project is to replace (to be cascaded elsewhere in the network) and split the routes in the summer, having one vessel going to Lochmaddy and the other to Tarbert, giving more resilience to the fleet and the Outer Hebrides. The two vessels,will be of the same design as and . All four of these vessels will be built at the Cemre Shipyard in Turkey.[38]

CMAL confirmed on 19 May 2023 that the first steel for the first vessel will be cut on 24 May 2023.[39] On 20 September 2023, the keel was laid for the first vessel, while the first steel was cut for the second vessel.[40] A public vote to select the names for the two vessels began on 30 November 2023, with voting closing at midnight on Monday 18th December.[41] The names and were selected: MV Claymore is expected to be delivered in June 2025 with MV Lochmor expected to be delivered in October 2025.[42]

Gourock ferries and terminal redevelopment

Replacements for the three passenger-only fleet serving Dunoon and Kilcreggan.[43] This project also includes the redevelopment of all three terminals and related infrastructure.[44] This project is currently at the design phase, with construction due to begin in 2025/26.[45]

New Lochboisdale ferry and Gasay Ferry Terminal

A new vessel will be constructed to replace on the Mallaig-Lochboisdale (South Uist) service.[46] This also includes a new terminal at Gasay, near Lochboisdale, as the current pier is getting to the end of its life.[47] This project is currently at the design phase, and as of February 2024 a date for procurement was still to be confirmed.[48]

Future Mull ferries

The CMAL Corporate Plan for 2024-2027 envisages the start of the design phase for two new major units to replace and on the Oban-Craignure service.[45] As of August 2024 this project had yet to commence.

Criticism and Future

CMAL has come under significant criticism for its handling of procurement, particularly in relation to the building programme of MV Glen Sannox and MV Glen Rosa, both under construction at Ferguson Shipyard in Port Glasgow. The function and future of CMAL is currently under consideration by the Scottish Government via Project Neptune which is considering the management and delivery of Scottish ferry services. The future of CMAL is subject to a number of proposals being made including re-merging CMAL and Caledonian MacBrayne as was the case previously or indeed CMAL being absorbed into the function of Transport Scotland. A Scottish Parliament committee was critical of CMAL and ultimately has considered the proposals outlined in Project Neptune, recommending CMAL be abolished and a new public division of Transport Scotland established called Ferries Scotland. There have been numerous calls such as that from Kenny MacLeod, Chairman of Harris Development Trust, to scrap CMAL and reintegrate the organisation as an internal organ of Caledonian MacBrayne. These comments were also echoed in the media by the RMT Union.

References

External links

Notes and References

  1. Web site: Caledonian Maritime Assets Limited. Companies House. 31 May 2021.
  2. Web site: About Us . 2023-09-23 . CMAL Caledonian Maritime Assets Ltd . en.
  3. Web site: About Us . 2023-09-23 . CalMac Ferries . en.
  4. News: CalMac ferry contract confirmed. BBC News. 17 November 2007 . 20 September 2007.
  5. Web site: Ferries. CMAL. 2018-08-06.
  6. Web site: Deal to buy vessels as Northern Isles contract is extended. Caledonian Maritime Assets Ltd. 2018-04-27. 2018-05-15.
  7. Web site: Fleet Facts. CMAL. 2018-08-06.
  8. News: CalMac career complete for Raasay ferry . Michelle . Henderson . . 2 March 2018 . 17 March 2018.
  9. Web site: End of an era as last 'Island' class retires. Caledonian MacBrayne. 2018-06-04. 2018-04-09.
  10. Web site: Locations . 2023-09-23 . CMAL Caledonian Maritime Assets Ltd . en.
  11. Web site: Harbour Authority . 2023-09-23 . CMAL Caledonian Maritime Assets Ltd . en.
  12. News: 'Hybrid' CalMac ferry launched from Port Glasgow . BBC News. 17 December 2012 . 17 December 2012.
  13. News: Nicola Sturgeon launches pioneering hybrid ferry from Port Glasgow shipyard. Scottish Government. 29 September 2014. 3 September 2015.
  14. Web site: Hybrid Ferries Project. CMAL. 9 August 2016.
  15. Web site: Port-aiseig Bhreadhaig . 2023-09-23 . CMAL Caledonian Maritime Assets Ltd . en.
  16. News: CalMac@40 — Part Two. Clyde River Steamer Club. 9 August 2016.
  17. Web site: HySeas III. HySeas Consortium. 22 June 2021.
  18. Web site: Born again shipbuilder eyes Orkney's hydrogen. Gavin Lipsith. Riviera Maritime Media Ltd. 18 Feb 2019. 22 June 2021.
  19. Web site: Final HySeas III Workshop being-held in June. 27 May 2022. 21 August 2021. CMAL.
  20. Web site: Caledonian Maritime Assets Limited announces Scottish shipbuilder as preferred tenderer for two large ferries contract. 31 August 2015. 24 June 2017. CMAL.
  21. Web site: CMAL announces name of first LNG ferry. 1 June 2017. 24 June 2017. CMAL.
  22. News: Ferguson Marine selected as preferred bidder to build two ferries in Scotland. ship-technology.com. 2 September 2015. 3 September 2015.
  23. Web site: Fisher . Chris . 2023-08-30 . Hull 802 Name Decided by Public Vote . 2023-09-23 . CMAL Caledonian Maritime Assets Ltd . en.
  24. News: Clyde shipyard Ferguson set to go into administration. BBC News. 9 August 2019. 26 August 2019.
  25. Web site: Corporate Plan 2021-2024. CMAL. 22 June 2021.
  26. Web site: Major Calmac Ferry Replacement Project Begins. NI Ferry Site. 23 February 2021. 22 June 2021.
  27. Web site: Small Vessel Replacement Programme . 2023-05-13 . Caledonian Maritime Assets Ltd. en.
  28. Web site: SVRP public presentation. Caledonian Maritime Assets Ltd.
  29. Web site: SVRP: Procurement launched for small vessel replacement plan. Caledonian Maritime Assets Ltd. 16 July 2024. 20 August 2024.
  30. Web site: SVRP: Phase 2 Commences. 15 August 2024. 20 August 2024. Caledonian Maritime Assets Ltd.
  31. Web site: Plans to build two new CalMac ferries for Western Isles inter-island routes. 18 August 2024. 20 August 2024. Hebrides News.
  32. Web site: New vessels for Islay . 2023-05-13 . CMAL Caledonian Maritime Assets Ltd . en.
  33. Web site: Comms . Clark . 2023-01-13 . TWO NEW FERRIES FOR ISLAY REACH NEXT CONSTRUCTION MILESTONE . 2023-05-13 . CMAL Caledonian Maritime Assets Ltd . en.
  34. News: New Names for Islay Vessels Decided by Public Vote. Caledonian Maritime Assets Ltd. 18 May 2023. 19 May 2023.
  35. Web site: Fisher . Chris . 2023-05-25 . Key construction milestones met for MV Loch Indaal and first of two Little Minch ferries . 2023-09-23 . CMAL Caledonian Maritime Assets Ltd . en.
  36. Web site: New CalMac ferry built in Turkey delayed until 'end of year'. STV News. 9 August 2024. 19 August 2024. Matthew Fulton.
  37. Web site: Second Turkish-built CalMac ferry given launch date. BBC News. 20 August 2024. 3 May 2024.
  38. Web site: Preference for Green Renewal of New CMAL vessels is Cemre Shipyard once Again!. 4 December 2023. 3 February 2023. Cemre Shipyard.
  39. Web site: Two New Vessels for the Little Minch . 2023-05-13 . CMAL Caledonian Maritime Assets Ltd . en.
  40. Web site: Fisher . Chris . 2023-09-20 . Little Minch ferries reach major construction milestones . 2023-09-23 . CMAL Caledonian Maritime Assets Ltd . en.
  41. Web site: Name the new vessels for the Little Minch. 4 December 2023. 30 November 2023. Caledonian Maritime Assets.
  42. News: Vote names new Little Minch ferries. The Oban Times. 19 December 2023. 19 December 2023.
  43. Web site: New passenger vessels . 2023-09-23 . CMAL Caledonian Maritime Assets Ltd . en.
  44. Web site: Gourock, Dunoon, Kilcreggan programme . 2023-09-23 . CMAL Caledonian Maritime Assets Ltd . en.
  45. Web site: CMAL. May 2023. CMAL Corporate Plan 2024 - 2027 . 21 August 2024 . www.cmassets.co.uk.
  46. Web site: New Vessel for Mallaig - Lochboisdale . 2023-09-23 . CMAL Caledonian Maritime Assets Ltd . en.
  47. Web site: Gasay Ferry Terminal Development . 2023-09-23 . CMAL Caledonian Maritime Assets Ltd . en.
  48. Web site: https://www.cmassets.co.uk/wp-content/uploads/2024/02/Mallaig-Lochboisdale-New-Vessel-Updated-Public-Engagement-Q-and-A-Document-Feb-24.pdf,Mallaig-Lochboisdale New Vessel Public Engagement Q&A Document. CMAL. 22 August 2024. 21 February 2024.