Bujagali Hydroelectric Power Station Explained

Bujagali Dam
Dam Crosses:Victoria Nile
Location:Bujagali, Uganda
Dam Type:Gravity dam
Construction Began:2007
Opening:2012
Cost:US$862 million
Plant Turbines:5
Plant Capacity:250MW
Plant Annual Gen:1,100 GWh
Plant Commission:2012[1]
Location Map:Uganda#Africa#World
Location Map Caption:Location of Bujagali Power Station
Placement on map is approximate
Coordinates:0.4983°N 33.1375°W

The Bujagali Power Station is a hydroelectric power station across the Victoria Nile that harnesses the energy of its namesake, the Bujagali Falls, in Uganda. Construction began in 2007 and concluded in 2012. It was officially inaugurated on 8 October 2012 by Ugandan President Yoweri Museveni and Aga Khan IV in the presence of African politicians and investors.[1]

The 250-megawatt power station was the largest hydroelectric energy source in Uganda when it was commissioned. However, the planned Karuma and Ayago power stations would be larger. The funding for the station was a source of some concern, as investors joined and departed from the project. As of July 2014, the plant was managed by Bujagali Energy Limited, which selected Italian contractor Salini Impregilo to develop the project.[2]

Location

The power station lies across the Victoria Nile, about 15.5km (09.6miles) north-west of the central business district of the city of Jinja and immediately north of the former location of the Bujagali Falls. It is at the border between Buikwe District to the west and Jinja District to the east. The coordinates of Bujagali Power Station are 0° 29'54.00"N, 33° 08' 15.00"E (latitude:0.498325; longitude:33.137500).

History

As far back as 2001, the government of Uganda started to plan the construction of a hydroelectric power plant at Bujagali Falls. The original developers included AES Energy from the United States and the Madhvani Group from Uganda. In the midst of fraud investigations,[3] the first project was abandoned in 2003 when AES Energy pulled out of the deal, citing a protracted process because of objections from environmentalists.[4] The project was delayed due to protracted negotiations between investors and representatives of the Soga cult of the water spirit Budhagaali, whose main shrines were seen as inextricably linked to the strength of the waterfall. Ultimately agreement was reached between the parties.[5]

A new consortium, Bujagali Energy Limited, was created by Sithe Global Power LLC, from the United States, and Industrial Promotion Services, a division of the Aga Khan Fund for Economic Development, and was tasked with developing the project.[6] Construction of the dam and powerhouse started in June 2007. Salini Impregilo was selected to be the lead contractor.[7] The power station began commercial operations on 1 August 2012.[8] At the peak of construction activity, the project employed over 2,500 people, including about 2,200 Ugandan nationals.[9]

Ownership

As of September 2016, the shareholders in Bujagali Energy Limited were as outlined in this reference.[10] In May 2018, the Daily Nation newspaper reported that Jubilee Holdings Limited was set to invest an additional KSh4.4 billion (US$44 million) in the business, in addition to the KSh5.5 billion (US$55 million) that it had already invested.[11]

Rank !!Name of Owner!!Percentage Ownership
1Jubilee Investment Company[12]
2Government of Uganda
3Sithe Global Power65.0
4Industrial Promotion Services
5Aga Khan Fund for Economic Development
Total100.0

In mid-2018, SN Power (today Scatec) of Norway acquired the shareholding previously owned by Sithe Global Power of the United States. The acquisition of that shareholding, held through an SPV called SG Bujagali Holdings Limited (SGBH), was completed by 1 August 2018.[13] [14]

The ownership of the power station as of August 2018 is as illustrated in the table below.[13] [14]

Rank !!Name of Owner!!Percentage Ownership
1Jubilee Investment Company
2Government of Uganda
3SN Power (today Scatec)65.0
4Industrial Promotion Services
5Aga Khan Fund for Economic Development
Total100.0

Construction costs

The estimated costs for the dam and power plant was US$800 million. Another $62 million was spent on building a high voltage transmission line from Jinja to Kawanda, near Kampala, a distance of about 80km (50miles). Bujagali Energy Limited invested approximately US$190 million of its own money into the project. The rest of the funds were borrowed from the following international lenders:[15]

  1. International Finance Corporation (IFC), a member of the World Bank Group
  2. African Development Bank
  3. European Investment Bank
  4. German Investment Corporation
  5. KfW
  6. PROPARCO of France
  7. French Development Agency
  8. Netherlands Development Finance Company
  9. Absa Group Limited
  10. BNP Paribas
  11. Nedbank
  12. Standard Chartered Bank

In March 2018, the Board of Directors of IFC and MIGA approved plans to refinance in excess of US$400 million in construction debt owed by Bujagali Energy Limited, the project SPV. The approval includes US$423 million in guarantees, in support of the project. The refinancing will extend the tenor of the existing loans made in 2007, by the lenders listed above. This, along with tax waivers from the Ugandan government, will lower the cost of electricity to the consumer and stimulate economic growth in the country, where only 26 percent of the population (8 percent in rural areas) had access to grid-electricity at that time.[16]

Completion date

The project was completed in 2012, although partial power generation started in 2011.[17]

In April 2010, The EastAfrican, a Kenyan weekly publication, indicated that the opening of the dam would be phased, one unit at a time.[18] On 2 February 2012, Ugandan newspapers reported the commissioning of the first turbine of the power station.[19] In May 2012, the third 50-megawatt turbine was commissioned, bringing output to 150 megawatts.[20] On 15 June 2012, Ugandan press reports indicated that the fourth and fifth turbines had come online, bringing total output to 250 megawatts. The plant officially began commercial operation on 1 August 2012.[21] [22]

On 8 October 2012, the project was officially inaugurated by Ugandan President Yoweri Museveni and Aga Khan IV in the presence of African politicians and investors.[23]

The cost of power

As of October 2016, the dam's utilization rate was approximately 70 percent. The power generated cost the end-user about US$0.11/kilowatt-hour, which was the highest rate in the East African Community.[24] In September 2016, the government of Uganda began negotiations with equity partners and lenders to restructure the financing of the dam to reduce the cost to the end-user to about US$0.072/kilowatt-hours.[24]

See also

External links

Notes and References

  1. Web site: Museveni Commissions Bujagali Dam . 8 October 2012 . . 22 April 2014 . New Vision.
  2. Web site: Environmental Justice Atlas . Bujagali hydropower project, Uganda . 18 December 2015 . . 3 August 2020 . Barcelona, Spain.
  3. Web site: Africa Dam's Passage 'Eased by Bribes' . David . Pallister . 3 November 2003 . 22 April 2014 . The Guardian.
  4. Web site: AES Backs Out of Bujagali Dam Project . Sasha . Lilley . CorpWatch . 28 August 2003 . 22 April 2014 . 17 June 2017 . https://web.archive.org/web/20170617062807/http://corpwatch.org/article.php?id=8250 . dead .
  5. Book: Reid, Richard. A History of Modern Uganda. Cambridge University Press. 2017. 978-1-107-06720-2. United Kingdom. 287–288.
  6. Web site: About Bujagali Energy Limited . Bujagali Energy Limited . 22 April 2014 . https://web.archive.org/web/20140823032931/http://bujagali-energy.com/bujagali_aboutUs1.htm . 23 August 2014 . dead .
  7. Web site: Bujagali Falls Hydropower Dam, Jinja, Uganda . 22 April 2014 . Power Technology.
  8. Web site: Evolution of the 250MW Bujagali Dam . 7 October 2012 . 7 March 2015 . Ibrahim . Kasita . . Kampala.
  9. Web site: 1 April 2015 . Bujagali Dam Near Completion . 14 November 2018 . Frank . Mugabi . . Kampala . 23 February 2020 . https://web.archive.org/web/20200223205933/https://www.newvision.co.ug/new_vision/news/1013880/bujagali-dam-near-completion . dead .
  10. Web site: . 4 September 2016 . Uganda urges Bujagali investors to take haircut on project to reduce power costs . 1 June 2018 . Daniel Kalinaki . Nairobi.
  11. Web site: Jubilee Holdings to pump Sh4.4bn into Bujagali power plant . 1 June 2018 . . 31 May 2018 . John Mutua . Nairobi.
  12. Web site: Jubilee Wins 30-Year Pact to Operate Bujagali . 1 June 2018 . Victor . Juma . . 23 May 2014.
  13. Web site: SN Power to buy SGBH's stake in Bujagali HPP . WaterPowerMagazine.com . 19 April 2016 . Water Power Magazine . 1 May 2022 . London, United Kingdom.
  14. Web site: Uganda: SN Power acquires SGBH's shares in the Bujagali power plant . 1 August 2018 . Afrik21.africa . Jean Marie Takouleu . Paris, France.
  15. Web site: Nile Diverted Through Bujagali Powerhouse . 12 April 2011 . Daily Monitor Reporter . 22 April 2014 . Kampala . Daily Monitor.
  16. Web site: 1 June 2018 . Press Release . Washington, DC . IFC and MIGA Boards Support Bujagali Refinancing Package to Reduce Ugandan Electricity Costs . 8 March 2018 . . 23 February 2020 . https://web.archive.org/web/20200223205930/https://ifcextapps.ifc.org/ifcext/pressroom/IFCPressRoom.nsf/0/7C6FB1872C371C118525824A007D3E80 . dead .
  17. Web site: Uganda Infrastructure Report Q1:2010 . Companies and Markets . 22 April 2014 . dead . https://web.archive.org/web/20111005164715/http://www.companiesandmarkets.com/Summary-Market-Report/uganda-infrastructure-report-q1-2010-264741.asp . 5 October 2011 . dmy-all .
  18. Web site: Julius . Barigaba . 12 April 2010 . Bujagali Power Project To Come On Stream Unit By Unit In 2011 . . Nairobi . 5 May 2014.
  19. Web site: Moses . Walubiri . Bujagali Dam Opens Today . . 2 February 2012 . 4 May 2014.
  20. Web site: 1 June 2012 . Kampala . Vice President Commissions Third Bujagali Dam Unit . . 5 May 2014 . Charles . Kakamwa.
  21. Web site: 5 May 2014 . March 2013 . Bujagali: Powering Uganda From The Nile . International Water Power & Dam Construction . https://web.archive.org/web/20131022073124/http://www.alstom.com/Global/Power/Resources/Documents/Brochures/bujagali-uganda-kaplan-hydro-plant-advertorial.pdf# . 22 October 2013 . dead . dmy-all .
  22. Web site: Developing Bujagali, the Largest Private Sector Investment in Uganda . 1 November 2012 . 31 May 2016 . Ryan . Ketchum . Hydroworld.com.
  23. Web site: 7 Largest Hydropower Stations in Uganda. live. https://web.archive.org/web/20200717174303/https://www.world-energy.org/article/10704.html . 17 July 2020 . 16 July 2020. World Energy.
  24. Web site: Uganda to extend Bujagali tax breaks beyond mid-2017 over high power tariffs . 16 October 2016 . . Nairobi . Daniel K. Kalinaki . 16 October 2016.