Blue Grass Chemical Agent-Destruction Pilot Plant Explained

The Blue Grass Chemical Agent-Destruction Pilot Plant (BGCAPP) is a facility built to destroy the chemical weapons stockpile at the Blue Grass Army Depot (BGAD), near Richmond, Kentucky.

The last munition, an M55 rocket containing GB nerve agent, was destroyed July 7, 2023. It marked the last chemical weapon in the U.S. stockpile.

Since 1944, the Army stored 523 short tons (474 t) of nerve agents sarin (GB) and VX and mustard agent in 155mm projectiles, 8-inch projectiles and M55 rockets at BGAD. That was about 2% of the nation's original chemical weapons stockpile.

BGCAPP used neutralization to destroy the majority of the stockpile and Static Detonation Chamber units to augment the main plant.

Destruction of this stockpile was a requirement of the Chemical Weapons Convention, an international treaty to which the United States is a party. The Organisation for the Prohibition of Chemical Weapons is the implementing body of the Chemical Weapons Convention and monitored the progress of the nation's chemical weapons destruction programs. The Program Executive Office, Assembled Chemical Weapons Alternatives (PEO ACWA) oversaw the destruction of the Blue Grass chemical weapons stockpile and now is managing destruction of agent-contaminated secondary waste and closure activities.

Planning and organization

A systems contract was awarded in June 2003 to a joint venture team composed of Bechtel National, Inc., and Parsons Corporation. The Bechtel Parsons Blue Grass team was contracted to design, construct, systemize, and operate and close BGCAPP.[1]

In March 2005 the design-build-operate-close schedule was extended to make the program more affordable on an annual basis. Site preparation work and the construction of support buildings continued and final designs for the remaining BGCAPP facilities were completed in 2010. In June 2019, the Static Detonation Chamber began destroying mustard agent-filled projectiles. In January 2020, the BGCAPP main plant facility began destroying nerve agent-filled projectiles. The last munition was destroyed July 7, 2023.[2]

The destruction schedule exceeded the terms of the Chemical Weapons Convention deadline of April 29, 2012. The U.S. subsequently made a commitment to the OPCW to complete chemical weapons destruction by September 30, 2023, which it accomplished.

Closure activities (shut-down, dismantling, and restoration of site) are slated to be completed by 2026.

Legislation enacted by the U.S. Congress in 2007 (Public Laws 110-116 and 110-181) mandated the destruction of the remaining U.S. national chemical stockpile in accordance with the April 2012 date, but in no circumstances later than December 31, 2017. This deadline was subsequently extended to December 31, 2023, by the National Defense Authorization Act for Fiscal Year 2016 (Public Law 114-92).

History of chemical demilitarization in Kentucky

DecadeMilestones
1940s
  • BGAD begins storage of chemical weapons containing mustard agent.
1960s
  • BGAD begins storage of chemical weapons containing nerve agent.
1980s[3]
  • Public Law 99-145 designates the U.S. Army responsible for the destruction of the U.S. chemical weapons stockpile.
1990s[4]
  • Congress establishes the ACWA program to identify and demonstrate alternatives to incineration.
  • Congress ratifies the Chemical Weapons Convention treaty, which directs all member nations to destroy their chemical weapons and production facilities.
2000s
  • Public Law 107-248[5] assigns ACWA responsibility for destruction of chemical weapons stored in Kentucky if an alternative technology is chosen.
  • Department of Defense selects neutralization followed by supercritical water oxidation (SCWO) as the destruction method for the Kentucky stockpile.
  • Bechtel Parsons Blue Grass awarded the contract to design, build, and operate BGCAPP.
  • The Secretary of Defense affirms to Congress that there are no options by which the U.S. can destroy 100 percent of its chemical stockpile by the extended Chemical Weapons Convention treaty deadline of April 29, 2012.
  • BGCAPP Groundbreaking is held.
  • Public Laws 110-116[6] and 110-181[7] are enacted, mandating destruction of the chemical stockpile by April 2012 or in no case later than December 31, 2017.
  • Site preparation and basic facility infrastructure (perimeter fencing, lighting and underground utilities) is complete.
  • Vertical construction of the personnel support building, the maintenance building and the badging facility is complete.
  • Construction activities progress focusing on the facility's Munitions Demilitarization Building, Utility Power Centers, Fire Water Pump House, Utility Building and SCWO Building.
2010s
  • BGCAPP surpasses 4 million job hours worked without a lost-time injury.[8]
  • Construction activities progress focusing on the facility's Munitions Demilitarization Building, Utility Power Centers, Fire Water Pump House, Utility Building, SCWO Processing Building and Control and Support Building.
  • The Department of Defense accepts the final BGCAPP design.
  • The systemization phase begins at BGCAPP. Construction teams turn over the first subsystems to the start-up groups for systemization testing and commissioning to begin preparing the facilities for chemical weapons destruction operations. The construction teams turn over the first building, the Fire Water Pump House, and the first system, the 138 kV Power Center, to the systemization team.[9]
  • BGCAPP partners with the Blue Grass Chemical Activity to conduct an X-ray assessment of the mustard agent stockpile. The assessment shows that removal of mustard agent from projectiles would be difficult using the current BGCAPP design. The Blue Grass team evaluates the feasibility of utilizing Explosive Destruction Technology (EDT) to destroy this segment of the stockpile.[10]
  • BGCAPP is designated as a Voluntary Protection Program Star Status site by the U.S. Department of Labor's Occupational Safety and Health Administration.
  • In June 2013, BGAD and PEO ACWA completed an environmental assessment to meet the requirements of the National Environmental Policy Act, or NEPA, and Title 32 Code of Federal Regulations Part 651, to address any potential impacts of the installation and operation of EDT at the depot. The environmental assessment concluded that the installation and operation of an EDT will have no significant environmental impacts. A draft Finding of No Significant Impact was prepared and provided for public comment for a 60-day period. It was concluded that no additional analysis was necessary for the proposed action under NEPA.[11]
  • Bechtel Parsons Blue Grass received approval from PEO ACWA to begin initial work on an EDT system at the Blue Grass plant. Following a competitive procurement process, Bechtel Parsons selected the Static Detonation Chamber.[12]
  • The Blue Grass Chemical Agent-Destruction Pilot Plant received approval from the Kentucky Department for Environmental Protection in 2014 to begin initial construction activities of an EDT facility.
  • In 2014, systemization reached 25 percent completion at the BGCAPP.
  • In 2015, the Bechtel Parsons Blue Grass Team earned recertification of Star Status in the Occupational Safety and Health Administration's Voluntary Protection Program.
  • In June 2015, the Static Detonation Chamber (SDC) completed Factory Acceptance Testing at the Dynasafe workshop in Kristinehamn, Sweden. The SDC arrived at BGCAPP in August to be assembled, tested and installed.[13]
  • The SDC was assembled and installed at BGCAPP in early 2016.
  • In July 2017, the BGCAPP team began systemization or testing activities on the Energetics Batch Hydrolyzers and Metal Parts Treaters.[14]
  • In August 2017, 25 percent (i.e., 15 systems) of the systems and facilities at BGCAPP were turned over from the systemization team to the operations team.
  • In September 2017, the BGCAPP team began systemization or testing activities on the Rocket Handling System.
  • In November 2017, the team began pre-systemization activities in the Explosive Destruction Technology facility.
  • In late 2017, ACWA Test Equipment (ATE) was introduced in the plant to test and calibrate equipment.[15]
  • In December 2017, Kentucky Department for Environmental Protection opened a 45-day public comment period[16] on the GB Sampling and Research, Development & Demonstration permit modifications.
  • In January 2018, the BGCAPP team successfully completed the Systemization Demonstration Procedure[17] for the Energetics Neutralization System.
  • In February 2018, the BGCAPP team tested pre-filter banks for proper filtration and air flow[18] and the team introduced nitrogen[19] into the plant for the first time.
  • In March 2018, the BGCAPP systemization team turned over 21 of 59 Blue Grass plant systems to operations.[20]
  • By July 2018, the BGCAPP systemization team turned over more than half of the 59 systems to operations.[21]
  • In October 2018, plant workers were fitted for and received M40 masks as part of their standard personal protective equipment.[22]
  • In November 2018, the Blue Grass plant received 44 M60 training rockets from the Blue Grass Army Depot.[23]
  • On May 29, 2019, an event was held to mark the start of chemical weapons destruction operations.[24]
  • In June 2019, the Static Detonation Chamber entered the operations phase with the successful destruction of the first mustard agent-filled munition on June 7.[25]
  • On June 7, 2019, the Static Detonation Chamber, now called the Static Detonation Chamber 1200, entered the operations phase with the successful destruction of the first mustard agent–filled munition.
  • In July 2019, the Blue Grass Army Depot commander signed a document verifying no significant impact to the environment is anticipated from the proposed additional Static Detonation Chamber for the Blue Grass plant.[26]
2020s
  • On January 17, 2020, the BGCAPP main plant entered the operational phase with the destruction of the first 8-inch projectile containing GB nerve agent.
  • In March 2020, the first concrete foundation was placed for a support building for the new, larger Static Detonation Chamber 2000 facility, which was added to augment the main plant processing.
  • In May 2020, the first destruction campaign at BGCAPP was completed when all 8-inch projectiles containing GB nerve agent were destroyed using neutralization.[27]
  • In August 2020, the decision was made to not use the supercritical water oxidation system to process hydrolysate, the product of the neutralization process.[28]
  • On January 10, 2021, BGCAPP destroyed 155mm projectiles containing VX nerve agent for the first time.[29]
  • In March 2021, program officials announced hydrolysate, the product of nerve-agent neutralization at BGCAPP, will be destroyed at Veolia North America near Port Arthur, Texas.[30]
  • On May 28, 2021, the second destruction campaign was completed as the final VX 155mm projectiles were destroyed.[31]
  • On July 9, 2021, BGCAPP destroyed M55 rockets containing VX nerve agent for the first time, marking the start of the fourth of five destruction campaigns.[32]
  • On September 4, 2021, the third destruction campaign was completed as the final mustard 155mm projectiles in Kentucky were destroyed.[33]
  • On October 7, 2021, BGCAPP shipped the first tankers of hydrolysate for destruction at Veolia North America near Port Arthur, Texas.
  • On November 1, 2021, BGCAPP shipped the first boxes of non-contaminated rocket motors to Anniston Army Depot for destruction in a Static Detonation Chamber.
  • On April 19, 2022, BGCAPP destroyed the last M55 rocket containing VX nerve agent, thus completing the fourth and penultimate destruction campaign.[34]
  • On July 6, 2022, the fifth and final destruction campaign began when the first M55 rocket containing GB nerve agent was destroyed.[35]
  • As of September 9, 2022, 50% of the original stockpile of chemical agent at BGCAPP has been destroyed.[36]
  • On January 27, 2023, the Static Detonation Chamber 2000 entered the operations phase with the successful destruction of the first containerized rocket warhead previously drained of GB nerve agent in the main plant.[37]
  • On February 17, 2023, BGCAPP reached 50% destruction of the M55 rockets containing GB nerve agent, in the plant's fifth and final destruction campaign.
  • As of February 24, 2023, 75% of the original stockpile of chemical agent at BGCAPP has been destroyed.
  • On April 12, 2023, the last VX nerve agent rocket motor from BGCAPP was destroyed in the Static Detonation Chamber at the Anniston Army Depot in Alabama.[38]
  • On May 2, 2023, BGCAPP reached 75% destruction complete of the M55 rockets containing GB nerve agent.
  • On July 7, 2023, BGCAPP destroyed the last M55 rocket containing GB nerve agent, completing the destruction of munitions stored at BGAD and the end of the declared U.S. stockpile.[39]
  • On July 14, 2023, the Kentucky Department for Environmental Protection granted BGCAPP a Temporary Authorization Request to begin closure activities in the main plant.
  • On September 27, 2023, the Kentucky Department for Environmental Protection approved a Resource Conservation and Recovery Act permit modification to conduct the closure phase at BGCAPP.
  • On October 25, 2023, the Static Detonation Chamber 1200 destroyed the first containerized rocket warhead previously drained of VX nerve agent in the main plant as part of secondary-waste operations during closure.
  • On August 5, 2024, BGCAPP reached 50% destruction of containerized rocket warheads containing residual amounts of GB nerve agent as part of secondary-waste destruction in the Static Detonation Chamber 2000 during the plant’s closure phase.

Technology

The Department of Defense conducted studies[40] to evaluate potential impacts of the elimination of these weapons using incineration and non-incineration methods for the plant. Four technologies were considered:

Neutralization

The Department of Defense initially selected neutralization followed by supercritical water oxidation for use at the depot. In 2020, the decision was made to not use the supercritical water oxidation system and instead ship the nerve agent hydrolysate to a permitted treatment, storage and disposal facility.

The neutralization method consisted of the following steps:

Explosive Destruction Technology (EDT)

After an X-ray assessment of the mustard munitions stockpile showed that the agent had significantly solidified in the rounds—making removal of mustard agent from projectiles difficult using neutralization—ACWA decided to explore use of Explosive Destruction Technology (aka Explosive Demolition Technology, Explosive Detonation Technology, EDT) for these projectiles.

EDT uses heat/pressure from explosion or just heat to destroy munitions; it is not considered incineration and does not require disassembly of weapons. Three general types of technologies can destroy chemical weapons:

Bechtel Parsons Blue Grass received approval from PEO ACWA to begin initial work on an Explosive Destruction Technology system at the Blue Grass plant. Following a competitive procurement process, Bechtel Parsons selected the Static Detonation Chamber.[42]

In June 2015, the SDC completed Factory Acceptance Testing at the Dynasafe workshop in Kristinehamn, Sweden. The SDC was assembled and installed at BGCAPP in 2016.[43]

In May 2018, EDT technicians brought the air filtration system online for the first time.[44]

In July 2018, construction substantially completed and testing began on EDT plant equipment in remote operations mode.[45]

In February 2019, a total of 24 B586 conventional munitions were processed in the Static Detonation Chamber as part of systemization activities.[46]

On June 7, 2019, the Static Detonation Chamber, now called the Static Detonation Chamber 1200, entered the operations phase with the successful destruction of the first mustard agent-filled munition.

On September 4, 2021, the final mustard 155mm projectiles in Kentucky were destroyed in the Static Detonation Chamber 1200.

On October 25, 2023, after being retrofitted with a new off-gas treatment system and completing systemization, the Static Detonation Chamber 1200 began destroying drained, containerized rocket warheads containing residual amounts of VX nerve agent. The containerized rocket warheads are considered agent-contaminated secondary waste and are being destroyed as part of the plant's closure phase.

Static Detonation Chamber (SDC)

In September 2019, BGCAPP received state approval to begin work on a second, larger SDC, called the SDC 2000. Workers broke ground January 22, 2020. The site includes the main structure housing the detonation chamber, a storage magazine and support buildings.

It began operations on January 27, 2023, destroying the first containerized rocket warhead containing residual amounts of GB nerve agent.

BGCAPP used the new, larger SDC 2000 to destroy undrained rocket warheads, M55 rocket overpacks and rockets not suitable to be processed in the main plant. It continues to use it to destroy agent-contaminated secondary waste such as containerized, drained rocket warheads, which will continue into the plant's closure phase.

In September 2021, after the final mustard munition was destroyed at BGCAPP, the original SDC, now known as the SDC 1200, began a changeover process. On October 25, 2023, it began destroying drained, containerized rocket warheads containing residual amounts of VX nerve agent. The containerized rocket warheads, which previously had been drained in the main plant, are classified as agent-contaminated secondary waste.

The SDC 2000 and SDC 1200 both are estimated to continue operations until early 2025 as part of the plant's closure phase.

Closure

Closure is the final phase of the project, coming after chemical weapons destruction operations have been completed. Closure encompasses planning, preparation and disposal of agent-contaminated and non-contaminated secondary waste; facility and equipment decontamination; and decommissioning and demolition of facilities in accordance with public law and U.S. Army direction. In addition, personal property is dispositioned, real property is returned to BGAD, environmental permits are closed and the contract is closed.

Public outreach

The Blue Grass Chemical Stockpile Outreach Office permanently closed to the public in 2024, but staff continues to be available at bgoutreach@iem.com.

The Blue Grass Chemical Stockpile Outreach Office was established to serve as the community's primary information resource on chemical weapons destruction in Kentucky. Although the outreach office closed in April 2024 as part of overall BGCAPP closure activities, the BGCAPP outreach staff continues to respond to inquiries, provides information to stakeholders and guest speakers for civic groups, and interfaces with the governor-appointed Kentucky Chemical Demilitarization Citizens' Advisory Commission and its Chemical Destruction Community Advisory Board.

References

External links

37.7171°N -84.2077°W

Notes and References

  1. News: Chemical weapons disposal process unveiled. January 20, 2004. The Advocate-Messenger. May 26, 2024.
  2. Web site: US Completes Chemical Weapons Stockpile Destruction Operations. July 7, 2023. defense.gov . May 10, 2024.
  3. Web site: Public Law 99-145. uscode.house.gov. July 3, 2017.
  4. Web site: Program Timeline. Program Executive Office, Assembled Chemical Weapons Alternatives. peoacwa.army.mil. April 3, 2017.
  5. Web site: Public Law 107-248. October 23, 2002. www.congress.gov. July 3, 2017.
  6. Web site: Public Law 110-116. www.congress.gov. July 3, 2017.
  7. Web site: Public Law 110-181. www.congress.gov. July 3, 2017.
  8. News: Design of chemical weapons destruction facility concludes. August 2, 2010. Richmond Register. April 3, 2017.
  9. News: First building operational at Richmond's chemical agent destruction plant. Clemons. Becca. May 31, 2011. Lexington Herald-Leader. April 3, 2017.
  10. Web site: U.S. Army Chemical Materials Agency: Project Manager for Non-Stockpile Chemical Materiel: X-Ray Assessment of 155mm Mustard Projectiles Stored at Blue Grass Army Chemical Activity, Richmond, Kentucky. U.S. Army Chemical Materials Agency. peoacwa.army.mil. April 3, 2017.
  11. Book: Front Matter Assessment of Explosive Destruction Technologies for Specific Munitions at the Blue Grass and Pueblo Chemical Agent Destruction Pilot Plants The National Academies Press. 2009 . en. 10.17226/12482. 978-0-309-12683-0 .
  12. Web site: Facts: Static Detonation Chamber (SDC) Program Executive Office, Assembled Chemical Weapons Alternatives (PEO ACWA). April 3, 2017.
  13. Web site: BGCAPP Explosive Destruction Technology Program Executive Office, Assembled Chemical Weapons Alternatives (PEO ACWA). www.peoacwa.army.mil. en-US. April 3, 2017.
  14. Web site: Facts: Blue Grass-Specific Equipment Program Executive Office, Assembled Chemical Weapons Alternatives (PEO ACWA). www.peoacwa.army.mil. en-US. September 26, 2017.
  15. Web site: Experts Renew Efforts at Blue Grass Mustard Destruction Project Program Executive Office, Assembled Chemical Weapons Alternatives (PEO ACWA). www.peoacwa.army.mil. October 26, 2017 . en-US. December 21, 2017.
  16. Web site: State Agency Opens Permit Public Comment Period Program Executive Office, Assembled Chemical Weapons Alternatives (PEO ACWA). www.peoacwa.army.mil. December 27, 2017 . en-US. March 28, 2018.
  17. Web site: Team Completes Demonstration of Key System Program Executive Office, Assembled Chemical Weapons Alternatives (PEO ACWA). www.peoacwa.army.mil. January 30, 2018 . en-US. March 28, 2018.
  18. Web site: Technicians Use Mist and Light to Test Filters Program Executive Office, Assembled Chemical Weapons Alternatives (PEO ACWA). www.peoacwa.army.mil. February 7, 2018 . en-US. March 28, 2018.
  19. Web site: Nitrogen Introduced into Blue Grass Plant for First Time Program Executive Office, Assembled Chemical Weapons Alternatives (PEO ACWA). www.peoacwa.army.mil. February 21, 2018 . en-US. March 28, 2018.
  20. Web site: Experts: 21 Systems Turned Over to Operations Program Executive Office, Assembled Chemical Weapons Alternatives (PEO ACWA). www.peoacwa.army.mil. March 29, 2018 . en-US. June 18, 2018.
  21. Web site: More Than Half of Blue Grass Systems Turned Over to Operations. July 27, 2018 .
  22. Web site: Protective Masks Issued Ahead of Plant Operations. October 19, 2018 .
  23. Web site: Plant Receives Army Training Rockets. 27 November 2018 .
  24. Web site: Stakeholders Recognize Start of Kentucky Chemical Weapons Destruction at Event. 31 May 2019 .
  25. Web site: 30 Munitions Destroyed at BGAD. Six. Taylor. June 12, 2019. Richmond Register. live. https://web.archive.org/web/20190613004235/https://www.richmondregister.com/news/munitions-destroyed-at-bgad/article_db38fdca-725e-5f4c-9cf6-db83f62a0ceb.html . June 13, 2019 .
  26. Web site: Recommend Approval of the Finding of No Significant Impact for the Referenced Environmental Assessment, May 2019. live. https://web.archive.org/web/20200726004808/https://www.peoacwa.army.mil/wp-content/uploads/ACW-19-0107-COMBINED-PDF-RECORD-OF-FONSI-ACTIVITY.pdf . 2020-07-26 .
  27. Web site: Six. Taylor. May 15, 2020. BGCAPP destroys all 8-inch projectiles. live. https://web.archive.org/web/20200605131733/https://www.richmondregister.com/news/bgcapp-destroys-all-8-inch-projectiles/article_f6b05aec-96c5-11ea-8237-1b574cda6b9b.html . June 5, 2020 . Richmond Register.
  28. Web site: Chisenhall. Jeremy. Tanker trucks may move Kentucky nerve agent waste that can't be disposed of on site. live. https://web.archive.org/web/20200911153457/https://www.kentucky.com/news/local/counties/madison-county/article245492510.html . September 11, 2020 . Lexington Herald Leader.
  29. Web site: January 11, 2021. VX nerve agent destruction begins at Blue Grass Army Depot. live. Richmond Register. https://web.archive.org/web/20210112043224/https://www.richmondregister.com/news/vx-nerve-agent-destruction-begins-at-blue-grass-army-depot/article_4e93116b-67e2-5029-907e-dbc7a124c24a.html . January 12, 2021 .
  30. Web site: Johnson. Stu. Disposal of Nerve and Mustard Agent Moves Forward in 2021. March 3, 2021. July 6, 2021. www.weku.org. en.
  31. Web site: Plant completes destruction of projectiles with nerve agent. June 4, 2021. July 6, 2021. AP NEWS. en.
  32. Web site: report. Register staff. First nerve agent rockets destroyed at Blue Grass Army Depot. September 20, 2021. Richmond Register. July 12, 2021 . en.
  33. Web site: September 9, 2021. Projectiles containing mustard agent destroyed. September 29, 2021. AP NEWS. en.
  34. Web site: April 20, 2022. Entire U.S. Stockpile of VX Nerve Agent Eliminated. April 20, 2022. PEO ACWA. en.
  35. Web site: July 7, 2022 . Work begins on last chemical weapons stockpile in Kentucky . September 30, 2022 . AP NEWS . en.
  36. Web site: September 12, 2022 . Half of Blue Grass Chemical Agent Stockpile Destroyed - Program Executive Office, Assembled Chemical Weapons Alternatives (PEO ACWA) . September 30, 2022 . en-US.
  37. Web site: Ramp-up of new nerve munition detonation chamber continues this week . February 2023 .
  38. Web site: April 19, 2023. Anniston Destroys All VX Rocket Motors from Kentucky. April 24, 2023. en-US. https://web.archive.org/web/20230419210945/https://www.peoacwa.army.mil/2023/04/19/anniston-destroys-all-vx-rocket-motors-from-kentucky/. April 19, 2023. live.
  39. Web site: Johnson . Stu . July 11, 2023 . The U.S. has destroyed the last of its declared chemical weapons stockpile . .
  40. Book: Council, National Research. Letter Report of Review and Assessment of the Proposals for Design and Operation of Designated Chemical Agent Destruction Pilot Plants (DCAPP-Blue Grass). July 12, 2006. 10.17226/11694 . 978-0-309-10222-3 .
  41. Web site: Explosive Destruction System Program Executive Office, Assembled Chemical Weapons Alternatives (PEO ACWA). www.peoacwa.army.mil. en-US. April 3, 2017.
  42. Web site: How the Static Detonation Chamber Will Augment the Blue Grass Chemical Agent-Destruction Pilot Plant. Program Executive Office, Assembled Chemical Weapons Alternatives. 2013. peoacwa.army.mil. April 3, 2017.
  43. Book: The National Academies of Science Engineering and Medicine. Review of the Design of the Dynasafe Static Detonation Chamber (SDC) System for the Anniston Chemical Agent Disposal Facility. 2010. 10.17226/12971 . 978-0-309-15907-4 . April 3, 2017.
  44. Web site: Technicians Start Air Filtration System for First Time Program Executive Office, Assembled Chemical Weapons Alternatives (PEO ACWA). www.peoacwa.army.mil. May 16, 2018 . en-US. June 18, 2018.
  45. Web site: BGCAPP Monthly Recap – July 2018 Program Executive Office, Assembled Chemical Weapons Alternatives (PEO ACWA). www.peoacwa.army.mil. en-US. September 19, 2018.
  46. Web site: Crew Tests Equipment Procedures with Conventional Munitions. February 27, 2019 .