Bletchley Flyover Explained

Bridge Name:Bletchley Flyover
Carries:Varsity line
Crosses:West Coast Main Line
Locale:Bletchley
Owner:Network Rail
Length:605m (1,985feet)
Number Spans:37
Num Track:2
Electrification:No
Rebuilt:2020 - 2021
Coordinates:51.9922°N -0.7353°W
Os Grid Reference:SP 868 335
Mapframe:yes
Mapframe-Zoom:13

The Bletchley Flyover is a railway viaduct that crosses the West Coast Main Line (WCML) just south of Bletchley railway station in Milton Keynes, England. It was originally a reinforced concrete railway viaduct that carried the former Varsity line between and from 1959 until its closure in 1968. The flyover was retained, but largely unused until 2021, when the East West Rail Alliance demolished then rebuilt the structure. It reopened for engineering use in early 2022.

Construction

The original structure was composed of 37 concrete spans,[1] resting on concrete piers. It is long.[2] Most of the spans are beam-shaped; two are double-length arches. Electrification pads were provided when the flyover was first built, despite there being no plans to electrify the line.

History

In 1959, the Bletchley Flyover was opened to carry the Varsity line over the West Coast Main Line (WCML) as part of the British Rail Modernisation Plan.[3] [4] The plan proposed to develop the Varsity Line as a freight link from the East Coast ports to South Wales, capable of handling up to 2,400 wagons of coal class traffic and empties daily.[5] However, following British Railways deciding not to proceed with the Swanbourne sidings plan, the line saw little use, with most freight traffic taking other routes.[6]

The Varsity line closed to passengers on 1 January 1968; it remained open to goods traffic until October 1993, when the bridge was mothballed.[7] The flyover was returned to use in 2006 along with a mile of track west of Bletchley to a loop at the Newton Longville Brickworks landfill site.[8]

2020/2021 rebuild

As part of the East West Rail project that will reopen the OxfordCambridge route, work to replace 14 of the spans began in April 2020.[7] [9] [10] Sections beside and over the WCML were removed in April and May.[11] [12] The arches crossing Buckingham Road (on the east side of WCML) started being removed on 5 July 2020.[13] "The final span was lifted out by crane in October and the last of the supporting piers and pillars were removed over the weekend of 9-10 January 2021".[14] At the early May 2021 holiday, 103 concrete girders were lifted into place to provide the bridge deck over the main line.[15]

During summer 2021, a new structure was built for use by East West Rail, in the form of a box tunnel around the WCML;[16] by February 2022, 1.5km (00.9miles) of track had been installed over the new flyover, enabling engineering trains to reach the eastern end of the construction site.[17]

The renovation project includes a plan to construct high level platforms for Bletchley station, just after the eastern end of the flyover. These platforms will serve East West Rail (only).

Notes and References

  1. News: Biggest cranes in Europe spotted in Milton Keynes ready for 295-tonne upgrade . https://web.archive.org/web/20200728084632/https://www.miltonkeynes.co.uk/news/transport/biggest-cranes-europe-spotted-milton-keynes-ready-295-tonne-upgrade-2841784 . 28 July 2020 . . 4 May 2020.
  2. Class 56 special over doomed Bletchley flyover line . . 200 . 12 May 1993. 6.
  3. The Bletchley Flyover . . 691 . November 1958. 737.
  4. https://web.archive.org/web/20200728084632/https://www.miltonkeynes.co.uk/news/transport/biggest-cranes-europe-spotted-milton-keynes-ready-295-tonne-upgrade-2841784 Biggest cranes in Europe spotted in Milton Keynes ready for 295-tonne upgrade
  5. Book: Klapper, C.F.. London's Lost Railways. 1976. Routledge & Kegan Paul. London. 0-710083-78-5. 101.
  6. Book: Fiennes, G F . Gerry Fiennes . I tried to run a Railway . Revised . 7. Chief Operating Officer, B.R. . . London . 9780711004474 . 1973.
  7. Bletchley Flyover Project . . July 2020. 737.
  8. Bletchley flyover reconstruction begins . . 861 . June 2020. 18.
  9. https://www.railjournal.com/infrastructure/britains-east-west-rail-project-makes-progress/ Britain’s East-West Rail project makes progress
  10. https://www.railengineer.co.uk/three-huge-cranes-remove-flyover-at-bletchley/ Three huge cranes remove flyover at Bletchley
  11. News: Biggest cranes in Europe spotted in Milton Keynes ready for 295-tonne upgrade [as] 60-year-old Bletchley Flyover gets a makeover ahead of Milton Keynes's new East-West rail link ]. Kevin Nicholls . 4 May 2020 . 5 May 2020 . Milton Keynes Citizen.
  12. Web site: EWR2 Project Newsletter - July 2020 . Mark Cuzner . East West Rail Alliance . July 2020 . 7 August 2020.
  13. News: Three of UK's largest cranes heave out sections of concrete railway flyover in Milton Keynes . Sally Murrer . 2 July 2020 . 26 July 2020 . Milton Keynes Citizen.
  14. Web site: January 2021 . Mark . Cuzner . EWR2 Project Newsletter Winter 2020/2021 . East West Rail Alliance.
  15. Bank holiday rail upgrades complete between London and Scotland . May 4, 2021 . Network Rail .
  16. Web site: November 2021 . EWR2 Project Newsletter Autumn 2021 . East West Rail Alliance . Mark . Cuzner. ("Project Updates")
  17. Web site: February 2022 . EWR2 Project Newsletter Winter 21/22 . East West Rail Alliance . Mark . Cuzner. (Project Progress)