The Bjarkøy Fixed Link (Norwegian: Bjarkøyforbindelsen) is a fixed link which connects the three islands of Bjarkøya, Sandsøya, and Grytøya in Harstad Municipality in Troms county, Norway. The fixed link was completed in late 2018. A subsea road tunnel (Norwegian: Kvernsundtunnelen) connects the islands of Grytøya and Bjarkøya, and a bridge connects the islands of Grytøya and Sandsøya. The tunnel to Bjarkøya is long. The bridge to Grytøya is long plus a 900m (3,000feet) long causeway. The project also included of new road on Grytøya to connect the existing roads to the new undersea tunnel. The Bjarkøy Tunnel is designated as part of Norwegian County Road 867, while the Sandsøya Bridge is part of Norwegian County Road 124.[1]

History

The former municipality of Bjarkøy had a population of about 500 people. In a referendum in 2002, the residents voted to merge with the much larger neighboring Harstad Municipality if the fixed link was built, but since less than two-thirds of the vote approved it, it was not a binding vote. After further discussions, the municipalities were merged on 1 January 2013.[2] The financing of the project is based on financing from tolls, saved subsidies to the ferry operations, the savings of needed to build new ferry quays if the ferry service had continued, money saved through the municipal merger, and grants from Troms County Municipality. The total cost was then estimated at with a tentative completion date of 2016.[3]

Construction

Construction began in late 2014, and as of October 2015 the Bjarkøy tunnel bore reached from Grytøya.[4] In July 2016, weaknesses in the sea floor rock which threatened the flooding of the tunnel led to the reporting of an increased cost projection in excess of .[5] In July 2017, asphalting of the road surface inside the tunnel commenced with the projected completion date revised to autumn 2018.[6] The tunnel was formally opened on 15 December 2018 at a final cost of .[7]

References

68.9747°N 16.5761°W

Notes and References

  1. Web site: Fv. 867 / Fv. 124 Bjarkøyforbindelsene . . Norwegian . 17 August 2012 . https://web.archive.org/web/20170322003232/http://www.vegvesen.no/Fylkesveg/bjarkoyforbindelsene . 22 March 2017 . dead .
  2. Web site: Ugyldig folkeavstemning i Bjarkøy . https://archive.today/20120708041444/http://fil.nrk.no/nyheter/distrikt/troms_og_finnmark/1.210443 . dead . 8 July 2012 . . 7 September 2002 . Norwegian . 12 September 2011 .
  3. Web site: Angriper Bjarkøyforbindelsen . . Arvola . Øivind . 28 April 2011 . Norwegian . 12 September 2011.
  4. News: Inge Bjørn Hansen. Tunnelen er 1000 meter på veg. 22 January 2016. Hålogaland Avis. 13 October 2015. NO. https://web.archive.org/web/20160129110205/http://haalogalandavis.no/index.php?page=vis_nyhet&NyhetID=3202. 29 January 2016. dead.
  5. News: Pedersen. Linda. Bjarkøyforbindelsen blir mange millioner dyrere enn planlagt. 20 August 2017. Norsk Rikskringkasting AS. 5 July 2016. NO.
  6. Web site: Har startet asfalteringsarbeid i Kvernsuntunnelen. Statens vegvesen. 20 August 2017. NO. 11 July 2017.
  7. Web site: Åpnet Bjarkøyforbindelsene . ByggFakta . Byggfakta DOCU . 4 July 2020 . NO . 17 December 2018.