Baguashan Tunnel (THSR) explained

Baguashan Tunnel
八卦山隧道
Line:THSR
Location:Bagua PlateauChanghua CountyChanghuaFenyuanDacunYuanlin
Coordinates:24.0648°N 120.6084°W
System:THSR
Status:complete
Start:石牌里, Changhua, Changhua County
End:東北里, Yuanlin, Changhua County
Startwork:Apr 9, 2001
Opened:Jan 5,2007
Owner:Taiwan High Speed Rail Corporation
Operator:Taiwan High Speed Rail
Traffic:High-speed rail
Construction:507 days
Length:7357m (24,137feet)
Linelength:7357m (24,137feet)
Tracklength:7357m (24,137feet)
Notrack:Double
El:AC 25KV
Speed:315km/h
Hielevation:200m (700feet)
Lowelevation:26m (85feet)
Height:11.76m (38.58feet)

Baguashan Tunnel is a railway tunnel through Baguashan in Taiwan, located between Taichung HSR station and Changhua HSR station. With a route length of 7,357 meters, it is the longest tunnel on Taiwan High Speed Rail. Mileage of Baguashan Tunnel is TK173+021to TK180+378.[1] [2]

History

References

Notes and References

  1. Web site: 台灣高速鐵路 C260 標 八卦山隧道. MAA.Ltd. 27 April 2020.
  2. Web site: 台灣高速鐵路 C260標. 大陸工程公司. 27 April 2020.