B3 oil field explained

B3 oil field
Country:Poland
Region:Baltic Sea
Locblocks:B
Offonshore:Offshore
Discovery:1981
Startofproduction:1992
Api:42-43
Est Gas Bcm:168
Recover Oil Bbl:11
Coordinates:55.3600 N, 18.0300 E
Operator:Orlen
Owner:Orlen
Oil Production Bbl/D:1151
Production Gas Mmscm/D:18085
Peakofproduction:2003
Producingformations:Sandstone, Middle Cambrian

B3 is a major oil and gas field in the Baltic Sea. The field is located 80 km north of the Polish coastal town Rozewie. The crude oil is also referred to as Rozewie crude. Processing, drilling and accommodation is based on the jack up rig Baltic Beta located in the field. Most of the oil is shipped by tanker to the Gdańsk refinery as a part of the refinery feedstock. The associated gas is transmitted by pipeline to the combined heat and power (CHP) plant in Wladyslawowo.

History

Exploration of the Baltic Sea for oil and gas was undertaken over the period 1975 to 1990. The B3 field was discovered in the offshore Polish Exclusive Economic Zone in 1981.[1] This exploratory work was carried out by Petrobaltic a Polish state-owned enterprise, but with shareholders in Russia and East Germany. With the collapse of the Soviet Union Petrobaltic re-launched itself as a Polish state-owned organization. Its priorities shifted from exploratory drilling to appraisal with a view to producing commercial quantities of oil and gas. Two appraisal wells were drilled in the B3 field and an extended well test in Spring 1992 proved the viability of the field. The first 30,000 barrels of crude oil was sent to the Gdansk refinery in June 1992.

Petrobaltic eventually became LOTOS Petrobaltic. In 2022 LOTOS merged with Orlen, under which name the field is now operated.

The field

The B3 field properties are summarised in the table.

B3 field reservoir[2] !Parameter!Value
FieldB3
ReservourSandstone
Geological ageMiddle Cambian
Depth, m966-1450
Thickness, m50
°API gravity42 to 43
Sulfur, wt %0.12
CharacterLight, sweet
Gas oil ratio85 m3 per m3
Water depth at site, m85

Production

Having established the viability of the B3 field through the appraisal wells, commercial operations began in 1992. The jack up rig Baltic Beta was located on the field to undertake the processing of well fluids and provide the accommodation. This rig was formerly the West Beta owned by Smedvig. Most of the oil produced from B3 is shipped by tanker to Gdansk and fed to the Gdańsk refinery as part of the refinery feedstock. The associated gas is sent through a pipeline to the CHP generating plant in Wladyslawowo.

Further subsea wells were drilled to produce oil and gas from remote parts of the reservoir. Water injection was deployed to further evacuate the relatively low-pressure reservoir. By 2000 there were 12 production wells and five water injection wells. These were drilled through four subsea templates. The injection water plant has a design capacity of 35,000 barrels per day. This was sufficient to maintain production of 10,000 barrels per day. The reservoir has a  low gas to oil ratio of 85 m3gas/m3 of oil. About 10% of the gas was used as fuel and purge gas on the installation. The remainder was flared. In 2001 compression facilities were added to Baltic Bravo and a 75 km 115 mm diameter pipeline to transfer gas to the CHP plant at Władysłwowo.

The oil and gas resources in the Polish Exclusive Economic Zone of the Baltic Sea accounted for 19.7% of all Polish oil an gas resources.[3]

Peak production from the field was in 2003.[4]

The B3 field production of crude oil and liquid gas during the period 2008-15 is shown in the following table.[5]

Year!2008!2009!2010!2011!2012!2013!2014!2015
Crude oil production, thousand tonnes166.4157.2155.5145.5152.5145.6160.1131.9
Liquid gas production, million m318.317.316.915.716.816.017.817.8
The B3 field production 2019-22 is shown in the following table.[6]
Quarter and Year!Q1 2019!Q2 2019!Q3 2019!Q3 2020!Q2 2021!Q3 2021!Q4 2021!Q1 2022
Production, boe/d1,6861,1831,2141,8732,3102,5942,2982,000
Change year on year+54%+69%+20%+23%+1%
Change quarter on quarter-14%+16%+12%-11%-13%
The production of oil and condensate in 2019 was 0.42 million barrels/year. The amounts of gas produced was 6.6 million m3/year.[7]

Future development

The B3 reservoir has been identified as being potentially suitable for injection of carbon dioxide, captured from a large CO2 emitter, to achieve enhanced oil recovery of crude oil from the reservoir.

See also

External links

Notes and References

  1. Web site: Poland driving oil and gas projects across the Baltic . 4 December 2023.
  2. Web site: 2014 . Final Report on the Prospective sites for the Geological Storage of CO2 in the South Baltic Sea . 5 December 2023.
  3. Web site: Polish energy security in the oil sector . 5 December 2023.
  4. Web site: Oil & gas field profile: B3 Conventional Oil Field, Poland . 5 December 2023.
  5. Web site: 2016 . LOTOS_Databook_2015_UP_EN.xls .
  6. Web site: Lotos Annual reports . 4 December 2023.
  7. Web site: B 3 Oil and Gas Field (Poland) . 4 December 2023.