Hamilton LRT explained

Hamilton B-Line
Type:Light rail
System:BLAST network
Status:Planned
Locale:Hamilton, Ontario
Start:McMaster University
End:Eastgate Square
Stations:17
Planopen:TBD
Owner:Metrolinx[1]
Character:At-grade
Linelength:14km (09miles)
Website:Official website
Map State:collapsed

The Hamilton LRT (also known as the B-Line) is a planned light rail line in Hamilton, Ontario, Canada, to operate along Main Street, King Street, and Queenston Road. It is one of five planned rapid transit lines which form Hamilton's proposed BLAST network. The 14km (09miles), 17-stop route is planned to extend from McMaster University to Eastgate Square via downtown Hamilton.[2]

The LRT was originally funded by the province of Ontario in 2015 but was then cancelled in 2019 due to rising costs. In February 2021, the province recommitted to the project, subject to additional funding from the Canadian federal government.[3] In May 2021, the federal government committed funding for the project as part of a larger spending package to fund rapid transit initiatives in the Greater Toronto and Hamilton Area.[4] Preliminary construction is expected to begin in 2024.[5] [6]

Route layout

The western terminus is to be built on Main Street in front of McMaster University. The line will continue east until Dundurn Street, where it will turn north to access King Street. After turning back east on King Street, the line continues through downtown Hamilton. At the King–Main intersection, the line will continue on Main Street until Queenston Circle and then Queenston Road until Eastgate Square.

Stops

Stop[7] Platform typeNotes
McMasterIsland/sideConnection to McMaster University Bus Terminal
LongwoodIsland
DundurnUnknownLocated east of a spur line leading to
QueenIsland
JamesSplitConnection to MacNab Transit Terminal and Hamilton GO Centre
MarySide
WellingtonSide
WentworthIsland
ShermanIsland
Scott ParkIsland
Gage ParkIsland
OttawaIsland
KenilworthIsland
QueenstonSide
ParkdaleSplit
NashSplit
EastgateIslandConnection to Eastgate Transit Terminal
Notes
  • All stops are located along the street's median except where noted below.

    History

    Planning and funding (2011–2017)

    A benefits case analysis was conducted, showing a net benefit for implementing LRT, and that it would be adequate dealing with long-term travel demand growth.[8] An environmental project report was completed in October 2011.[9]

    On May 26, 2015, the Government of Ontario announced a shorter route between McMaster University and Queenston Circle, but also including a segment of the A-Line to provide a direct connection to West Harbour GO Station, as well as a pedestrian corridor to the Hamilton GO Centre. The capital costs for the project would be $1 billion, funded entirely by the province. For the B-Line LRT, procurement was expected to begin in 2017 and line construction in 2019.[10] [11] The transit line was scheduled to open to the public in 2024.

    On February 2, 2017, the province scrapped the A-Line spur altogether, announcing it would opt for bus rapid transit along the entire A-Line corridor from Hamilton's waterfront to the airport.[12]

    On March 28, 2017, Hamilton City Council chose to delay the crucial Environmental Assessment vote to April 19, 2017,[13] citing they needed more time to read it for themselves. On April 19, 2017, City Council voted again to delay the Environmental Assessment, this time to April 26, 2017,[14] claiming the plan at that stage (which was to build Phase 1 from McMaster University to Queenston traffic circle) was indefensible and unfit as it did not go from a destination location to a destination location.

    On April 26, 2017, the province announced with the money saved from removing the spur line from King and James to the West Harbour GO Station, they would work with the City to get the Eastgate Square extension included in the capital funding. Later that evening City Council voted to submit the original Environmental Assessment from October 2011 which covers the original route from McMaster University to Eastgate Square.[15] The motion to submit the original Environmental Assessment was by Terry Whitehead, who was one of the project's harshest critics. The motion passed 10–5, with Councillor Robert Pasuta absent.

    On August 4, 2017, the Ontario Ministry of the Environment and Climate Change approved the Environmental Project Report (EPR) Addendum for Hamilton's Light Rail Transit (LRT) plan.

    Procurement and cancellation (2017–2019)

    In 2018, before its election defeat, the previous Liberal government knew that the project cost had increased from $1 billion (established in 2014) to $2.85 billion, according to the Progressive Conservative government that succeeded it. However, Metrolinx continued to show the cost as $1 billion until late 2019.[16]

    On August 30, 2018, property acquisitions and other spending related to the project were put on hold by the newly elected provincial government.[17] About 50 percent of the properties still needed to be purchased before completing the light rail line.[18]

    Light rail was a key issue in the 2018 Hamilton municipal election.[19] Mayoral challenger Vito Sgro campaigned primarily on a platform of cancelling the B-Line project while incumbent mayor Fred Eisenberger was pro-LRT. On October 22, 2018, Eisenberger was re-elected to a second consecutive term (and third overall) receiving 54% of votes and claimed that the results indicated a "strong mandate on LRT to move forward."[20]

    On March 29, 2019, Ontario Transit Minister Jeff Yurek announced that project-related spending could resume after an eight-month freeze. He indicated that Metrolinx could now continue to purchase land along the route needed for LRT construction.[21] Four days later, Metrolinx announced the purchase of a 14.5-acre property which will be the site of an operations, maintenance and storage facility (OMSF) for the light rail vehicles.[22]

    Infrastructure Ontario (IO) and Metrolinx planned to deliver the Hamilton LRT project according to IO's Alternative Financing and Procurement (AFP) model which basically is a public–private partnership arrangement.[23] On February 2, 2017, Metrolinx and Infrastructure Ontario issued the request for qualifications to shortlist proponents to respond to a request for proposals.[24] On April 16, 2018, teams shortlisted by IO and Metrolinx allowed to bid on designing, building, financing, operating, and maintaining the LRT are:[25]

    The procurement of a dedicated fleet of light rail vehicles and the construction of a maintenance and storage facility were included in the deal. The deadline to submit bids was originally scheduled for April 2019 but was later extended by six months. As of 2019, no vehicles have been chosen, but the trains could be similar to the Flexity Freedom cars to be used in Waterloo Region's Ion rapid transit and Toronto's Eglinton Crosstown LRT or the Alstom Citadis Spirit cars ordered by Metrolinx as a backup fleet for Eglinton Crosstown LRT.[26] [27]

    On December 16, 2019, Doug Ford's government told the City of Hamilton that the project will be terminated "effective immediately", because the estimated cost of the project had risen to an "astonishing $5.5 billion".[28] [29] The Mayor of Hamilton, Fred Eisenberger, called the cancellation "a betrayal by the province to the City of Hamilton." The capital expenditures had increased from $1 billion excluding financing as of 2014 to $2.85 billion including financing at the time of project cancellation. Also, the Ford government is adding the 30-year estimated cost of $1 billion for operations and maintenance to the capital and financing costs. The City of Hamilton would have been expected to pay the LRT's operating and maintenance costs. The province has already spent $184 million on the project including the acquisition of 60 properties. Consortiums who were competing to construct the LRT would be entitled to compensation as a result of the cancellation. Transportation Minister Caroline Mulroney said the province has cancelled the Hamilton LRT, but not the Hurontario LRT with similar costs, because the Hurontario project was further along and bidders on the Hamilton LRT had raised concerns about costs.

    As a consolation, the provincial government offered the city $1 billion (the original estimated cost of the LRT line) to spend on other transit improvements. To this end, the provincial government set up a task force to decide on the best use for the money.[16] In March 2020, the task force reported their preference for the funds to be spent on higher-order transit (such as light rail or bus rapid transit) along the Hamilton LRT route.[30]

    Project revival (2020–present)

    In November 2020, there was talk of the project being revived. During an announcement in Hamilton, Ontario, Premier Doug Ford said he had been working closely with Hamilton mayor Fred Eisenberger on the file but said they would need funding support from the federal government to move forward with it. The following day, then federal Minister of Infrastructure and Communities Catherine McKenna said she supported the project, and that it was up to the province to formally endorse the LRT project and submit a business case for the federal government to review. Laborers' International Union of North America's Joseph Mancinelli cited the project as an ideal stimulant of economic recovery during the COVID-19 pandemic in Ontario.[31]

    On February 9, 2021, the province confirmed its commitment to the project and added the Hamilton LRT to its slate of priority transit projects in the GTHA. The proposed route would be a shorter 9km (06miles) kilometre line between McMaster University and Gage Avenue and would require an additional $1.5 billion in funding from the federal government.

    On May 11, 2021, Prime Minister Justin Trudeau announced $1.7 billion in federal funding for the Hamilton project. The capital costs would be split equally between the federal and provincial governments for the full 14-kilometre route.[32]

    On June 2, 2021, Metrolinx and the Ontario Ministry of Transportation met with Hamilton city council to discuss operating costs (which would be funded by the city) and to agree to negotiate a memorandum of understanding (MOU).[33] After a two-week delay, council voted 9–6 in favour of negotiating the MOU and proceeding with the LRT project.[34]

    On June 2, 2023, Metrolinx and City staff presented a project update to the City of Hamilton's LRT Sub-committee, in which Metrolinx is recommending a different delivery model and contract packaging strategy from what was previously contemplated under the former procurement process.[35] Instead of procuring project partners to deliver all aspects of the project by adopting a Public-Private Partnership (P3) contracting model, Metrolinx is recommending splitting up the Hamilton LRT project into 3 packages, as described below, and using different contract delivery methods following feedback from the market to decrease project risk, strengthen stakeholder management and improve interface between civil and systems scope:

    1. Advance Enabling Works: Early strategic relocation of select private and public utilities (mainly off corridor).
    2. Package 1 - Civil Works and Utilities (alliance): Primarily Third Party assets are designed, constructed, commissioned and handed over to asset owners. The proponent would also conduct works related to private and public utilities (relocation and renewal of longitudinal utilities), civil structures (eg. bridges, grade separations), roadworks and the urban realm (eg. streetscape, pedestrian and cycling facilities, and HSR integration).
    3. Package 2 - Stops, Rail and Systems (delivery model TBD): Works related to LRT guideway, rail, and systems, as well as the Operations, Maintenance and Storage Facility (OMSF) and integration of Light Rail Vehicles (LRVs) for Revenue Service. Metrolinx is discussing with the City on the potential to include operations and maintenance as part of this contract. If included, this package may be delivered as a P3 Design-Build-Finance-Operate-Maintain (DBFOM).[36]

    In October 2023, Metrolinx appointed AECOM to serve as the technical advisor for its Hamilton LRT.[37]

    By November 2023, Metrolinx introduced a design change affecting access to the planned Operations, Maintenance and Storage (OMSF) facility on Chatham Street as well as a change in alignment of the mainline. The mainline would cross Highway 403 via a rebuilt and widened Main Street bridge instead of via a rail-only flyover bridge. This change followed a decision by the City of Hamilton to convert Main Street from one-way to two-way traffic and is intended to save cost.[38] Access to the OMSF will be via Frid Street instead of via the busier Longwood Road. The mainline would shift from Main Street west to King Street via Dundurn Street, adding two 90 degree turns to the route. The Dundurn stop would be relocated along Dundurn Street to be closer to Hamilton's Innovation District instead of along King Street.[39]

    Operations

    External links

    Notes and References

    1. Web site: McGreal. Ryan. Ministry Approves Hamilton LRT Environmental Report. Raise The Hammer. August 3, 2017.
    2. Web site: Frequently Asked LRT Questions. July 4, 2017. hamilton.ca. February 1, 2019. June 29, 2022. https://web.archive.org/web/20220629101014/https://www.hamilton.ca/city-initiatives/priority-projects/frequently-asked-lrt-questions. dead.
    3. Web site: Craggs . Samantha . LRT is back on the table in Hamilton — but depends on the feds, province says . CBC . February 11, 2021 . February 9, 2021.
    4. News: Beattie. Samantha. May 11, 2021. Federal government to spend $12B on Toronto, Hamilton transit. CBC News. May 11, 2021.
    5. Web site: As LRT process edges along, King Street businesses say they're not getting the info they need . January 22, 2023 . .
    6. Web site: Mann . Ken . Key LRT decision ratified by Hamilton city council . Global News . September 17, 2021 . September 15, 2021.
    7. Web site: Hamilton LRT design drawing/map. Hamilton.ca. February 16, 2018. https://web.archive.org/web/20190727032727/https://d3fpllf1m7bbt3.cloudfront.net/sites/default/files/media/browser/2017-05-25/hamilton-lrt-environmental-pr-appendix-b-design-plates-and-cross-sections.pdf. July 27, 2019.
    8. Web site: B-Line Facts. City of Hamilton. April 9, 2012.
    9. Web site: Hamilton Rapid Transit Preliminary Design and Feasibility Study: B-Line . SNC Lavalin, Steer Davies Gleave . October 2011 . City of Hamilton . April 9, 2012 . September 24, 2015 . https://web.archive.org/web/20150924024726/http://www.hamiltonrapidtransit.ca/wp-content/uploads/2011/10/1-EPR_Main-Cover.pdf . dead .
    10. News: Ontario Investing Up to $1 Billion for Light Rail Transit in Hamilton. news.ontario.ca. August 5, 2017. en.
    11. News: Canadian Press and Hamilton Spectator . Hamilton to get a new LRT and GO Train station . February 17, 2019 . thestar.com . May 26, 2015 . en.
    12. News: Ontario Moving Forward with More Transit Options for Hamilton . February 17, 2019 . news.ontario.ca . Ministry of Transportation . February 2, 2017 . en.
    13. News: Hamilton's LRT project stalled for further debate by councillors. March 29, 2017. The Hamilton Spectator. May 1, 2017.
    14. News: 13 hours and no vote: LRT grinds to a halt. April 20, 2017. The Hamilton Spectator. May 1, 2017.
    15. News: Hamilton's light-rail transit project gets green light to move forward. April 27, 2017. The Hamilton Spectator. May 1, 2017.
    16. News: Final decision expected on Hamilton's disastrous light-rail project as angry residents look for closure . . Oliver . Moore . February 21, 2020 . February 25, 2020.
    17. Web site: Thompson . Shiona . Metrolinx pumps the brakes on Hamilton land purchases for LRT . Global News . April 4, 2019 . August 30, 2018.
    18. Web site: Only project paused by Ford government spending halt is Hamilton's LRT . CBC . April 4, 2019 . August 30, 2018.
    19. News: Van Dongen . Matthew . Poll shows Hamilton mayoral race a dead heat over LRT . . October 18, 2018 . November 1, 2018.
    20. Web site: Eisenberger wins Hamilton mayor's race over anti-LRT challenger Sgro . CBC . November 1, 2018.
    21. Web site: Van Dongen . Matthew . Hamilton LRT back on track after province lifts funding "freeze" . The Hamilton Spectator . April 5, 2019 . March 29, 2019.
    22. Web site: Mann . Ken . Hamilton LRT takes another step forward . Global News . April 6, 2019 . April 2, 2019.
    23. Web site: March 29, 2018 . Finch West, Hurontario LRTs advance . May 31, 2018.
    24. Web site: Ontario . Infrastructure . Request for Qualifications issued for Hamilton LRT . May 6, 2023 . www.newswire.ca . en.
    25. Web site: April 18, 2018 . RFP issued for Hamilton light rail project in Ontario . April 19, 2018.
    26. Web site: Metrolinx statement on Alstom/Bombardier . May 12, 2017 . Metrolinx . September 22, 2022 . https://web.archive.org/web/20220922011616/https://www.metrolinx.com/en/aboutus/mediarelations/news/20170512_MetrolinxStatement_AlstomBombardier.aspx . dead .
    27. News: Spurr . Ben . May 13, 2017 . How do TTC's streetcar options compare? It's Bombardier versus Alstom . . May 13, 2017.
    28. Statement by Mayor Fred Eisenberger on Hamilton's Light Rail Transit (LRT) project. December 16, 2019. hamilton.ca. https://web.archive.org/web/20191216205715/https://www.hamilton.ca/government-information/news-centre/news-releases/statement-by-mayor-fred-eisenberger-hamiltons-light. December 16, 2019. live.
    29. News: No provincial funding for LRT, mayor calls move a 'betrayal' of Hamilton. cbc.ca. December 16, 2019. en.
    30. Web site: April 9, 2020. Hamilton Transportation Task Force Report. February 11, 2021. www.ontario.ca.
    31. Web site: Ontario premier says Hamilton LRT is a 'good project' that needs federal backing . Polewski, L . Global News . November 13, 2020 . December 26, 2020.
    32. Web site: Lawson . Andrea . Federal government to provide $1.7B in funding for Hamilton LRT - CHCH . www.chch.com . May 11, 2021 . May 11, 2021.
    33. Web site: Rankin . Christine . LRT postponed again as Hamilton councillors wait 2 more weeks for crucial vote . CBC . June 5, 2021 . June 2, 2021.
    34. Web site: Mann . Ken . GIC vote to accept $3.4B offered for Hamilton LRT, council votes next week . Global News . June 24, 2021 . June 16, 2021.
    35. Web site: Hamilton Light Rail Transit (LRT) Project Update - Light Rail Transit Sub-committee - June 02, 2023 . June 2, 2023 . pub-hamilton.escribemeetings.com.
    36. Web site: January 25, 2022 . Metrolinx considering Alliance contract to de-risk Hamilton LRT project - constructconnect.com . June 2, 2023 . Daily Commercial News . en-US.
    37. Web site: AECOM teams up with Metrolinx as technical advisor for Hamilton LRT project . Mass Transit . 4 January 2024 . 19 October 2023.
    38. Web site: Mitchell . Don . Hamilton LRT change will shift route to Dundurn Street, eliminating rail bridge . Global News . November 17, 2023.
    39. Web site: Important steps taken towards progressing the Hamilton LRT . . November 15, 2023 . https://web.archive.org/web/20231116020636/https://www.metrolinx.com/en/news/important-steps-taken-towards-progressing-the-hamilton-lrt . November 16, 2023 . live .
    40. Web site: B-Line bus schedule. Hamilton Street Railway. June 4, 2015. September 9, 2016. https://web.archive.org/web/20160909223415/http://www2.hamilton.ca/NR/rdonlyres/5078DFE7-3CEB-4730-A152-336852CCCE4A/0/June2014_Bline.pdf. dead.
    41. News: Hayes . Molly . LRT storage barn proposal gets initial nod of residents . The Hamilton Spectator . October 13, 2016 . November 1, 2018.