Araneta City Cyberpark Explained

Araneta City Cyberpark
Location:Gen.Aguinaldo Ave. cor Gen. Mc Arthur Ave., Araneta City, Quezon City, Metro Manila, Philippines
Coordinates:14.6186°N 121.0544°W
Building Type:Office
Status:Under Development
Start Date:2007 (Telus,APAC,EGS House)
2014 (Cyberpark Tower 1)
2016 (Cyberpark Tower 2)
2019 (Cyberpark Tower 3)
Completion Date:2008 (Telus,APAC,EGS House)
2016 (Cyberpark Tower 1)
2018 (Cyberpark Tower 2)
2025(Cyberpark Tower 3)
Est Completion:2030 (planned)
Opening:2008 (Telus,APAC,EGS House)
2016 (Cyberpark Tower 1)
2018 (Cyberpark Tower 2)
1Q 2025 (Cyberpark Tower 3)
Roof:122m (400feet) (Cyberpark Tower 1 including helipad)
126m (413feet) (Cyberpark Tower 2 and Tower 3 including helipad)
Floor Count:30 (Cyberpark Tower 1)
31 (Cyberpark Tower 2 & Tower 3)
3 Basement Parking Levels
Elevator Count:12 Smart High-Speed Elevators (All Towers)
Cost: ($394.88 million)
per tower (estimate)[1]
Floor Area:5500002NaN2 (upon completion)
Architect:ASYA Design
Main Contractor:Metro Stonerich (Telus & Alorica House)
Megawide Construction Corporation (Tower 1 & Tower 2)
Datem Incorporated (Tower 3) [2]
Developer:ACI Inc.
Owner:ACI Inc.
Management:ACI Inc.
Website:

The Araneta City Cyberpark is a 8ha office development[3] located in the Araneta City in Cubao, Quezon City. Located along the southern part of the mixed-use commercial development, the office complex is currently undergoing a ₱20 billion redevelopment under a new master plan, consisting of five green office towers, retail spaces, and an outdoor park. The ongoing development currently includes 2 towers completed, and one tower topped off, with 1910002NaN2 of office space completed as of January 2021.

The complex is designed by ASYA Design and ACI Inc. serves as the owner and developer of the project. The redevelopment project is part of the Araneta City Master Plan.[4]

History

First Master Plan (2007-2008)

The Araneta City Cyberpark is part of the Araneta City master plan unveiled in 2000, and was rolled out in 2002, situated in an 8ha property along Gen. Aguinaldo, Gen. Araneta, and Gen. McArthur Avenues, primarily for Business Process Outsourcing/Information Technology (BPO-IT) office development. The development sits on a jeepney terminal servicing areas around Quezon City and the Province of Rizal, and the private Araneta White House (Bahay na Puti) complex. The development also sits on the former lot occupied by Fiesta Carnival, a 2ha amusement park formerly occupying the Shopwise Hypermarket complex. As the carnival declined in the 1990s due to rising competition from other amusement parks, mall-based entertainment, political unrest, and other technological shifts, the Araneta Group decided to move the carnival into an open lot located in the south west corner lot of the complex, across SM Cubao. Unfortunately, the outdoor complex did not click the public and was completely closed down years later.[5]

From the beginning of the late 1990s to 2001, the steady rise of the demand of business process outsourcing firms being founded in the country continues to contribute to the country's GDP through foreign and local investments, which also contributed to the creation of jobs in various sectors, and enabling the country to take a spot in the global outsourcing market in 2005 by attributing a total average of 3% of the total global output, making the BPO industry one of the fastest growing industries in the country.[6] Developments for BPO related industries flourished further during the Arroyo administration as part of their economic programs.[6] Due to the huge market potential of the industry and the successful launches of various BPO companies, the rising BPO industry also attracted the Araneta Group and prompted the company to launch the Cyberpark Master Plan in 2000, which also began to develop similar properties to cater the rapid rise of the industry, starting with the completion of the Gateway Office Building in 2005, which is primarily occupied by Accenture. The Cyberpark also became part of the finalized Araneta Center Redevelopment Plan in 2006, following the opening of the Gateway Mall in 2004, which also featured the Manhattan Gardens, the Gateway Tower, and a proposed 400-room business hotel, which became known today as Novotel Manila Araneta City. The first master plan of the Cyberpark was laid out in 2007, and began construction in the same year, before being completed in 2008. The complex is composed of 2 4-storey low-rise buildings, with 5 additional low rise buildings planned during the early planning phases. The two buildings were occupied by companies, such as Telus,[7] APAC Customer Services Inc., Advanced Contact Solutions, Agentworx Contact Solutions, and Expert Global Solutions.[8] [9] [10]

Updated Master Plan (2012-present)

Following the success of the Cyberpark, the development led in an increase of demand for more office spaces within the area. Guided with the continuous success of the BPO industry and related companies within the area, as well as an increase of deals, partnerships, and potential investment opportunities between the Araneta Group and various BPO firms, and a rising trend of green office developments throughout the country, a newer and updated master plan was finalized, consisting of 5 PEZA certified and LEED-approved towers, with 3 levels of retail podium spaces, surrounding the future Gateway Mall 3 set to rise in the complex, and are also connected to malls and nearby buildings such as SM Cubao, Ali Mall, the Manhattan Gardens condominiums, the Araneta Coliseum, the New Frontier Theater, the Novotel Manila Araneta City and the upcoming Ibis Styles Araneta City.[11]

The early planning stages of the complex began in 2012, wherein among the plans laid out consists of an open-air outdoor park with an intersecting road in between the towers, while having a total of 5 levels for retail, directly connected via footbridges. In 2014, the master plan was finalized, wherein the development will consist of 5 towers with varied architectural designs. The implementation of the new master plan is set to cost ₱20 billion and commenced with the construction of Cyberpark Tower 1 in April 2014, the Cyberpark Tower 2 in February 2016, and the Cyberpark Tower 3 in 2023. The development is also outlined to interconnect all office towers within the Cyberpark through the complex's basement parking and retail levels, and will also include a planned road extension of the Gen. Araneta Avenue, linking the road to the P. Tuazon Boulevard.[12]

Location and features

The development is also connected to major transport hubs such as the MRT 3 Cubao Station, the LRT 2 Cubao Station and transport terminals, with future connections to the Gateway Mall 3, and the Gateway Mall 2, primarily attracting business process outsourcing and corporate services companies, with plans laid out to also cater Philippine Offshore Gaming Operators.[13] The complex also features a variety of green initiatives and an ultra-high-speed fiber optic network infrastructure, enhancing the city's network connectivity, capable of reaching 5G networks, in collaboration with Smart Communications and PLDT.[14] The targeted completion of the entire green office complex is set within 2030.[15]

Structures

The Araneta City Cyberpark consists of five LEED-approved towers, interconnected with direct connections with the proposed Gateway Mall 3 and other properties within the Araneta City. The following table lies the current updates of the towers as of August 2023:

data-sort-type="text" NameImagedata-sort-type="isoDate" Construction starteddata-sort-type="isoDate" CompletionHeightdata-sort-type="number" Current status
Telus Housedata-sort-value="2006-04-27" data-sort-value="2014-11-03" data-sort-value="2" Completed
Cyberpark Tower 1
data-sort-value="2006-04-27" data-sort-value="2014-11-03" 122m (400feet)data-sort-value="2" Completed
Cyberpark Tower 2data-sort-value="2006-04-27" data-sort-value="2014-11-03" 126m (413feet)data-sort-value="2" Completed
Cyberpark Tower 3data-sort-value="2006-04-27" data-sort-value="2014-11-03" 126m (413feet)data-sort-value="2" Topped Off
Cyberpark Tower 4data-sort-value="2006-04-27" data-sort-value="2014-11-03" data-sort-value="2" Under conceptual stage
Cyberpark Tower 5data-sort-value="2006-04-27" data-sort-value="2014-11-03" data-sort-value="2" Under conceptual stage

Buildings

Telus House

See also: Telus. The Telus House is one of the first low-rise, 4-storey buildings in the original Cyberpark plan completed in 2008, and currently houses Telus as its main tenant. The building has 15000m2 of total office space, and features retail stores located at the ground floor.

The building will soon be demolished in order to give way for the construction of the Gateway Mall 3, a 5-storey 100000m2 expansion project of the Gateway Mall, and the Cyberpark Tower 4. The future development will feature eco-friendly initiatives, additional retail spaces and an elevated, green, outdoor park, and is currently on the planning stage.

Cyberpark Tower 1

The Cyberpark Tower 1 is the first tower of the project,[16] and standing 30 storeys high on the former EGS parking lot. Formerly known as the "Gateway Tower 2" project, which is named after the Gateway Tower, the construction of the tower started in February 2014, and was completed in May 2016. The Cyberpark Tower 1 has a total floor area of 940002NaN2 of office space, with 3 basement parking levels and 3 retail levels. The tower also features an asymmetrical window facade with floor-to-ceiling double glazed windows for energy efficiency, a rainwater collection system, and Solar panels located at the tower's roof deck.[17] The tower currently houses a variety of business process outsourcing companies such as Intouch (formerly 24-7 Intouch), ProbeCX (formerly Stellar), The Vibal Group, and Accenture, which serves as the tower's main tenant, and the company's third office within the area, aside from its current operations within the Gateway Tower. In 2019, Accenture began relocating their business activities from the Gateway Office Building to the Cyberpark Tower 1 in order to cater the company's expansion, which was completed in 2022.[18] [19] The tower is also occupied by gyms, beauty services stalls, banks, a 7-Eleven convenience store; restaurants, food stalls and coffee stores such as Taco Bell, CoCo Fresh Tea & Juice and Starbucks; and The Medical City Clinic Cubao Branch, located within the tower's commercial level area. The tower is also connected to nearby SM Cubao via Elevated Bridge. In November 2022, PartnerHero opened their first private office in the country, and occupies the 7th floor in the tower.[20] [21] On 31 August 2023, Everise became the tower's latest tenant, and serves as the company's first branch in Quezon City.[22]

One of the planned original tenants of the tower was Expert Global Solutions (EGS), after the company announced its plans to relocate their operation to the tower in early 2016. However, after lengthy negotiations with the Araneta Group and Alorica's acquisition of EGS, the plan was cancelled and the company decided to temporarily maintain their operations to the Alorica Building until March 2019, as the company moved its operations to the nearby Cyberpark Tower 2. The tower is also planned be directly connected to the upcoming Gateway Mall 3, and the Cyberpark Tower 4.

Cyberpark Tower 2

The Cyberpark Tower 2 is the second tower of the project, standing 31 storeys high on the former Jeepney Terminal servicing areas within Quezon City and the Province of Rizal, the Cyberpark Tower 2 has 970002NaN2 of office space, featuring a curved building design, floor-to-ceiling double-glazed energy-efficient windows, smart elevators, side balconies with planters, solar panels on the tower's rooftop, and a rainwater recovery system.[23] [24] [25] The final design of the tower was initially planned to include vertical trellises and erect a spire from the tower's side balconies, which was scrapped during the tower's construction phase.[4] Groundbreaking for the construction of the tower started in February 2016, while construction works began on the 3rd quarter of 2016, and was topped off in March 2018, before being fully completed in December 2018, as tenants and stores began occupying the tower.[25] [26]

The tower, like its predecessor, the Cyberpark Tower 1, has 3 basement parking levels with 2 levels of retail spaces and currently houses companies like Alorica, serving as one of the main tenants of the tower, occupying 7 floors aboveground and a recruitment hub located at the ground floor of the tower. The tower is also housed by the ACI Inc. and companies under by the Philippine Pizza Inc. (PPI), wherein both are subsidiaries of the Araneta Group, after relocating their operations from the Aurora Tower, the company's former headquarters, in 2019. Aside from Alorica, the tower is also housed by various BPO companies such as Ibex, which also occupies multiple floors of the tower, Acquire BPO, Offshore Business Processing, and HasTech IT Limited. On February 2023, R1 RCM, an American healthcare BPO company became the latest tenant to occupy the building.[27] On the third quarter of 2024, Genesys has relocated its operations to the Cyberpark Tower 2 from the nearby Cyberpark Tower 1. The tower is also occupied by banks, convenience stores, food stalls, and restaurants within the tower's commercial levels.[28] [29] [30]

Cyberpark Tower 3

The Cyberpark Tower 3 is third tower of the project, and is the latest tower being built in the complex, which is currently under construction, soon to rise on the former Alorica (EGS) Building site.[31] [1] The tower will be similarly designed to the Cyberpark Tower 2, standing 31 storeys high, and having 970002NaN2 of office spaces, while having 910002NaN2 of gross floor area. The tower also features a curved building design with floor-to-ceiling double-glazed energy-efficient windows, smart elevators, side balconies with planters, solar panels, and a rainwater recovery system.[32] [33] [34] [17] The demolition of the Alorica Building began in June 2019, while the groundbreaking for the construction of the tower started afterwards, in September 2019. The tower is originally slated to be completed in 2022, however, due to the effects of the COVID-19 pandemic in the Philippines, as well as market driven factors, financial problems and a case settlement with Megawide Construction Corporation regarding the construction issues of the Cyberpark Tower 2, the Gateway Mall 2 and the Ibis Styles Araneta City,[35] [36] [37] the construction of the tower was temporarily delayed.[38] In August 2022, the general contractor for the project was awarded to Datem Incorporated, while the tower's groundbreaking phase continued in December 2022.[2] On 6 February 2023, the first concrete pouring of the tower began in a ceremony attended by various Araneta Group officials, along with Binibining Pilipinas contestants. The tower is expected to be completed within the first quarter of 2025.[39] [40] [41] [42] [43]

On June 27, 2024, the tower was officially topped off and was attended by officials of the Araneta Group; JLL Philippines, which serves as the Araneta City's real estate advisor, and Telus, wherein the company serves as the tower's main tenant upon completion, as the company will move its overall operations to the tower from the Telus House located along the complex. The tower is set to be completed in the second quarter of 2025.[44] [45] [46] [47]

Cyberpark Tower 4

The Cyberpark Tower 4 is the fourth tower of the project, which will rise as a 30-storey office building, and is planned to be built on the current site of the Telus House and across Cyberpark Tower 2, with a direct connection to the Gateway Mall 3. The tower will also have the same features with its predecessors, and is currently on the planning stages.[31]

Cyberpark Tower 5

The fifth and final office building planned in the Cyberpark complex, which is currently in the planning stages. The Cyberpark Tower 5 is a planned 40-storey office building planned to be built on the Araneta City Jeepney Terminal and the private Araneta White House complex, which includes the Colombian Honorary Consulate. The tower will be located alongside the Cyberpark Tower 2, the Cyberpark Tower 3, and P. Tuazon Boulevard. The planned tower will feature an oval-shaped building design, and is currently in the planning stages.[31] [41]

Notes and References

  1. News: Reyes . Rizal Raoul . Araneta group boosting its position in cyberparks Rizal Raoul Reyes . BusinessMirror . 25 February 2023.
  2. News: Cyberpark . Datem, Inc. | Your Trusted Builder.
  3. Web site: July 24, 2018 . Araneta Center Cyberpark: The newest premier business district in the Metro | Marane A. Plaza . BusinessMirror.
  4. Web site: The Araneta Group . February 19, 2018 . www.aranetagroup.com . en.
  5. Web site: December 11, 2010 . Reminiscing Cubao: The Fiesta Carnival .
  6. Web site: Abaricio . Mark Daniel . The History of Outsourcing in the Philippines: A Timeline . KDCI . 11 March 2022.
  7. News: Araneta Center Cyber Park welcomes Telus Internat . Philstar.com.
  8. Web site: - Manhattan Garden City . yourpropertyconsultant.weebly.com/ . February 28, 2018.
  9. Web site: Araneta Center Cyber Park expands with more BPO firms. .
  10. Web site: Cubao Projects Ground Breaking Ceremonies – Metrostonerich-Alpha .
  11. Web site: Overview . aranetacenter.net/cyberpark/index.php . February 28, 2018.
  12. Web site: Araneta Group unveils P20-B masterplan for Cyberpark Complex in Cubao. July 24, 2019 .
  13. News: Nicolas . Jino . Araneta to develop new budget hotel in Cubao . BusinessWorld Online . 25 March 2018.
  14. News: Mercurio . Richmond . PLDT, Smart pick Araneta City for launch of 5G lifestyle hubPLDT, Smart pick Araneta City for launch of 5G lifestyle hub . Philstar.com.
  15. Web site: 2019 Araneta City Corporate AVP . .
  16. Web site: Cyberpark Tower 1 . megawide.com.ph/ . February 28, 2018.
  17. Web site: Araneta City. December 20, 2023 .
  18. Web site: Araneta City. December 20, 2023 .
  19. Web site: Cyberpark Tower One . Megawide Construction Corporation.
  20. News: PartnerHero opens first private office in the country . Manila Bulletin . 9 November 2022.
  21. News: PartnerHero excited to announce opening of first fully private office in PHL - BusinessMirror . 21 November 2022.
  22. News: EVERISE OPENS NEWEST PHILIPPINES SITE IN ARANETA CITY, QUEZON CITY . www.prnewswire.com . en.
  23. Web site: Araneta breaks ground on CyberPark Tower 2 for BPO locators . bworldonline.com/ . February 28, 2018.
  24. Web site: Araneta City. December 20, 2023 .
  25. Web site: Cyberpark Tower 2 . ASYA.
  26. Web site: March 19, 2018 . Araneta group tops off 2nd office tower in Cyberpark | VG Cabuag . BusinessMirror.
  27. Web site: https://www.facebook.com/r1rcmphilippines/posts/pfbid02DKP3Jdz38Bf3VtKJ4vQ1YbpvTJnaUbifr35PnT8BjAqpNX1Kakmn69H8bN6BpSk4l?__cft__[0=AZUGAL7TxmVZQXAFGi0eTXPEpCV0NKYlovK32aV-oFEEyP2ik2niAdlrK9xXYxZtpu5caATchAGZaoPGArymKeTt17CmEahkUxRD9C76VZe33Hu6D916vFTga3Nz0wTr4U4AInohxhJDAbzz2d0lqwVSZJFcyKjsF3gs6XCz1LqUX1MTs8Ynxdur8yD1KTHiiaRXNWWWKvF3Fo2W46gNFUzQ&__tn__=%2CO%2CP-R We are excited to announce that due to our remarkable growth, we have expanded and are now open in Cubao, Cybergate 2! ]. .
  28. Web site: June 7, 2019 . BPO giant ibex doubles PH network to 6 offices, adds 3,000 jobs | Bilyonaryo Business News .
  29. Web site: Business.
  30. News: Cabuenas . Jon Viktor D. . IBEX invests $13.5M in expanding PHL operations . en . GMA News Online .
  31. News: August 6, 2019 . The Araneta Center Cyberpark pushes for green initiatives . BusinessMirror . October 5, 2019.
  32. Web site: March 26, 2018 . Araneta Center targets 3rd tower development . The Manila Times.
  33. Web site: Araneta Group rethinks planned office building amid business process outsourcing slowdown. .
  34. Web site: Araneta City. December 20, 2023 .
  35. News: Megawide opposes ACI's counterclaim, plans arbitration filing . BusinessWorld Online . 18 April 2023.
  36. News: Cabuag . V. G. . Araneta, Megawide clash over construction cost of Cubao buildings VG Cabuag . BusinessMirror . 18 April 2023.
  37. News: Lelis . Brix . Araneta Group owes P180M to Megawide . The Manila Times . 13 January 2024 . en.
  38. News: May 31, 2019 . BPO industry growth seen slowing down . BusinessMirror .
  39. News: Araneta unit to open P4-B third tower of Cyberpark in 2025 . BusinessWorld Online . 6 February 2023.
  40. Web site: Araneta City holds concrete pouring ceremony for Cyberpark 3 .
  41. News: Araneta City rises as a new office center . May 15, 2022 . June 30, 2022 . https://web.archive.org/web/20220630232705/https://www.cnnphilippines.com/business/2022/4/25/Araneta-City-rises-as-a-new-office-center.html . dead .
  42. News: Reyes . Rizal Raoul . April 19, 2022 . Office landlords responding to business requirements Rizal Raoul Reyes . BusinessMirror .
  43. News: Almazan . Faye . April 14, 2022 . Araneta City adds office district . en . The Manila Times .
  44. News: 28 June 2024 . Araneta City tops off off Cyberpark 3 in Cubao . Manila Standard.
  45. News: Monzon . Alden M. . Araneta Group eyes completion of third Cyberpark tower in Q2 2025 . INQUIRER.net . 28 June 2024 . en.
  46. Web site: Martinez . Denny . Enriquez . Jeffrey . Araneta City holds topping off ceremony for Cyberpark 3 . aranetacity.com.
  47. News: Araneta City expands IT zone with Cyberpark 3 . malaya.com.ph . 3 July 2024.